MONTGOMERY FM 1097 (1259-01-049)
Items: 81
County: MONTGOMERY
Length: 0.0000 MILES
Highway: FM 1097
District: HOUSTON
Control Number: 1259-01-049
DBE Goal: 7.0%
Project: F 2025(635)
Guaranty: $80,000.00
Time: 179 WORKING DAYS
Engineer's Estimate: $4,016,607.05
Date: 04/04/2025 (1 year ago)
Contract Number: 4253221
Type: INSTALL/UPGRADE DRAINAGE STRUCTURE(S)
Project ID: A00131128
Contract Type: Federal
Project Description: CONSTRUCT DRAINAGE IMPROVEMENTS INCLUDING CULVERT REPLACEMENTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ABE GUZMAN
MATTHEW CONNELLY
MONTGOMERY FM 1097 (1259-01-049)
Project Name: N/A
Project: F 2025(635)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: AT ATKINS CREEK
Limits To: .
Project Description: CONSTRUCT DRAINAGE IMPROVEMENTS INCLUDING CULVERT REPLACEMENTS
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,016,607.05 | |||
| $3,494,494.80 |
-13%
-$522,112.25
|
|||
| $3,650,761.55 |
-9.11%
-$365,845.50
|
4.47%
$156,266.75
|
||
| $3,694,691.87 |
-8.01%
-$321,915.18
|
5.73%
$200,197.07
|
-1.20%
-$43,930.32
|
|
| $3,833,095.73 |
-4.57%
-$183,511.32
|
9.69%
$338,600.93
|
-3.75%
-$138,403.86
|
|
| $3,892,239.65 |
-3.1%
-$124,367.40
|
11.38%
$397,744.85
|
-1.54%
-$59,143.92
|
|
| $4,659,352.36 |
16%
$642,745.31
|
33.33%
$1,164,857.56
|
-19.71%
-$767,112.71
|
|
| $5,026,343.00 |
25.14%
$1,009,735.95
|
43.84%
$1,531,848.20
|
-7.88%
-$366,990.64
|
|
| $5,569,073.50 |
38.65%
$1,552,466.45
|
59.37%
$2,074,578.70
|
-10.80%
-$542,730.50
|
E
Engineer's Estimate
$4,016,607.05
1
Awarded
$3,494,494.80
Over/Under Est:
-13%
-$522,112.25
$3,650,761.55
Over/Under Est:
-9.11%
-$365,845.50
Amt Left:
4.47%
$156,266.75
$3,694,691.87
Over/Under Est:
-8.01%
-$321,915.18
Amt Left:
5.73%
$200,197.07
Delta:
-1.20%
-$43,930.32
$3,833,095.73
Over/Under Est:
-4.57%
-$183,511.32
Amt Left:
9.69%
$338,600.93
Delta:
-3.75%
-$138,403.86
$3,892,239.65
Over/Under Est:
-3.1%
-$124,367.40
Amt Left:
11.38%
$397,744.85
Delta:
-1.54%
-$59,143.92
$4,659,352.36
Over/Under Est:
16%
$642,745.31
Amt Left:
33.33%
$1,164,857.56
Delta:
-19.71%
-$767,112.71
$5,026,343.00
Over/Under Est:
25.14%
$1,009,735.95
Amt Left:
43.84%
$1,531,848.20
Delta:
-7.88%
-$366,990.64
$5,569,073.50
Over/Under Est:
38.65%
$1,552,466.45
Amt Left:
59.37%
$2,074,578.70
Delta:
-10.80%
-$542,730.50
| Subcontractor | Percentage | Amount |
|---|---|---|
| TRIPLE J ENTERPRISES, LLC | 7.94% | $289,819.57 |
| KLP COMMERCIAL, L.L.C. | 6.10% | $222,657.35 |
| TRAFFIC SIGNS & LINES, LLC | 3.92% | $143,084.73 |
| TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. | 3.52% | $128,484.24 |
| HODGES BROTHERS, INC. | 2.99% | $109,138.60 |
| STRUCTURAL INTEGRITY GROUP LLC | 1.20% | $43,801.45 |
| DUSTROL, INC. | 0.87% | $31,756.05 |
| Total: | 26.54% | $968,741.99 |
Bid Items & Bid Tabulations
81
Total
0 of 81
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $20,330.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $6,750.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $6,115.00 |
| Total: | $33,195.00 |