Bid Cobra

MONTGOMERY FM 1097 (1259-01-049)

Items: 81

County: MONTGOMERY
Length: 0.0000 MILES
Highway: FM 1097
District: HOUSTON
Control Number: 1259-01-049
DBE Goal: 7.0%
Project: F 2025(635)
Guaranty: $80,000.00
Time: 179 WORKING DAYS
Engineer's Estimate: $4,016,607.05
Date: 04/04/2025 (1 year ago)
Contract Number: 4253221
Type: INSTALL/UPGRADE DRAINAGE STRUCTURE(S)
Project ID: A00131128
Contract Type: Federal
Project Description: CONSTRUCT DRAINAGE IMPROVEMENTS INCLUDING CULVERT REPLACEMENTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
MATTHEW CONNELLY
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$4,016,607.05
$3,494,494.80
Over/Under Est: -13% -$522,112.25
Over/Under Est: -9.11% -$365,845.50
Amt Left: 4.47% $156,266.75
$3,694,691.87
Over/Under Est: -8.01% -$321,915.18
Amt Left: 5.73% $200,197.07
Delta: -1.20% -$43,930.32
Over/Under Est: -4.57% -$183,511.32
Amt Left: 9.69% $338,600.93
Delta: -3.75% -$138,403.86
Over/Under Est: -3.1% -$124,367.40
Amt Left: 11.38% $397,744.85
Delta: -1.54% -$59,143.92
Over/Under Est: 16% $642,745.31
Amt Left: 33.33% $1,164,857.56
Delta: -19.71% -$767,112.71
Over/Under Est: 25.14% $1,009,735.95
Amt Left: 43.84% $1,531,848.20
Delta: -7.88% -$366,990.64
Over/Under Est: 38.65% $1,552,466.45
Amt Left: 59.37% $2,074,578.70
Delta: -10.80% -$542,730.50
Subcontractor Percentage Amount
TRIPLE J ENTERPRISES, LLC 7.94% $289,819.57
KLP COMMERCIAL, L.L.C. 6.10% $222,657.35
TRAFFIC SIGNS & LINES, LLC 3.92% $143,084.73
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 3.52% $128,484.24
HODGES BROTHERS, INC. 2.99% $109,138.60
STRUCTURAL INTEGRITY GROUP LLC 1.20% $43,801.45
DUSTROL, INC. 0.87% $31,756.05
Total: 26.54% $968,741.99

Bid Items & Bid Tabulations

81 Total 0 of 81
MONTGOMERY  |  FM 1097  |  HOUSTON  |  1259-01-049  |  04/04/2025  |  $4,016,607.05  |  F 2025(635)  |  INSTL/UPGRADE DRAINAGE STRUCT(S)  |  179 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ROMAN EMPERORS ROAD, LLC
SER CONSTRUCTION PARTNERS, LLC
BRICE HIGHWAY LLC
TEXAS MATERIALS GROUP, INC.
MB WESTERN INDUSTRIAL CONTRACTING CO.
FORDE CONSTRUCTION COMPANY, INC.
R CONSTRUCTION CIVIL, LLC
GREY SKY CONSTRUCTION LLC
PREPARING ROW
STA 12.000 $8,000.000 $10,000.000 $1,285.300 $14,300.000 $10,000.000 $1,525.000 $14,000.000 $5,000.000 $35,000.000
REMOV CONC (MOWSTRIP)
LF 413.000 $16.000 $20.000 $15.800 $10.150 $23.000 $12.000 $26.000 $15.000 $50.000
REMOV CONC (RIPRAP)
SY 1,066.000 $35.000 $30.000 $8.300 $9.600 $15.000 $15.000 $7.000 $30.000 $50.000
REMOV CONC (MISC)
SY 49.000 $82.000 $30.000 $13.400 $52.670 $27.000 $27.000 $58.000 $75.000 $100.000
RMV (13") TRT/UNTRT BASE & ASPH PAV
SY 346.000 $23.000 $12.000 $111.400 $36.060 $26.000 $6.500 $32.000 $40.000 $20.000
EXCAV (ROADWAY)
CY 565.000 $45.000 $30.000 $80.500 $40.510 $45.000 $18.000 $55.000 $25.000 $20.000
EXCAV (CHANNEL)
CY 2,398.000 $30.000 $35.000 $36.200 $25.240 $21.000 $23.000 $30.000 $25.000 $50.000
EMBANK (FNL)(DC)(TY C)
CY 1,761.000 $51.000 $35.000 $4.300 $46.020 $12.000 $31.000 $30.000 $50.000 $50.000
BLOCK SODDING
SY 6,741.000 $10.000 $10.000 $6.100 $5.500 $7.000 $6.200 $6.000 $8.000 $10.000
DRILL SEED (TEMP_WARM_COOL)
SY 5,449.000 $1.450 $1.000 $0.400 $0.250 $1.500 $0.500 $0.500 $0.750 $0.500
FERTILIZER
AC 2.250 $1,535.000 $2,000.000 $989.400 $1,500.000 $1,300.000 $1,000.000 $950.000 $2,600.000 $3,500.000
VEGETATIVE WATERING
TGL 270.000 $90.000 $190.000 $39.600 $52.250 $30.000 $45.000 $65.000 $185.000 $20.000
ASPHALT TRT BASE (GR 2)(PG 64)
TON 458.000 $156.000 $160.000 $197.900 $138.000 $134.000 $163.000 $230.000 $170.000 $185.000
D-GR HMA TY-D PG70-22 (LEVEL-UP)
TON 1,422.000 $165.000 $160.000 $185.000 $148.000 $155.000 $175.000 $164.000 $180.000 $200.000
D-GR HMA TY-D SAC-A PG76-22
TON 355.000 $210.000 $200.000 $215.300 $165.000 $173.000 $195.000 $190.000 $200.000 $220.000
TACK COAT
GAL 515.000 $4.500 $5.000 $13.400 $4.500 $4.000 $5.400 $4.000 $6.000 $10.000
PLANE ASPH CONC PAV (1.5")
SY 4,274.000 $2.000 $2.000 $7.100 $4.090 $2.000 $2.500 $5.000 $10.500 $20.000
CUT & RESTORE ASPH PAVING
SY 140.000 $225.000 $230.000 $308.500 $227.600 $250.000 $237.000 $325.000 $300.000 $250.000
CEM STABIL BKFL
CY 345.000 $95.000 $230.000 $67.500 $83.790 $130.000 $260.000 $100.000 $75.000 $300.000
CEMENT STAB BACKFILL (INLET OR MH)
CY 42.000 $75.000 $150.000 $67.500 $83.790 $130.000 $260.000 $95.000 $75.000 $350.000
TRENCH EXCAVATION PROTECTION
LF 109.000 $6.000 $15.000 $1.200 $2.590 $50.000 $12.000 $10.000 $15.000 $10.000
TEMPORARY SPL SHORING
SF 10,428.000 $50.000 $20.000 $31.300 $15.740 $47.000 $24.000 $60.000 $59.500 $65.000
CL E CONC (SEAL SLAB)(NON-REINF)
CY 23.000 $1,960.000 $600.000 $605.200 $489.910 $600.000 $600.000 $650.000 $965.000 $5,000.000
CL A CONC (CHANNEL LINING)
CY 349.000 $245.000 $500.000 $736.000 $618.240 $850.000 $600.000 $950.000 $1,300.000 $2,000.000
RIPRAP (CONC)(4 IN)
CY 140.000 $1,024.000 $650.000 $552.100 $677.470 $700.000 $635.000 $716.000 $1,400.000 $550.000
RIPRAP (MOW STRIP)(4 IN)
CY 69.000 $1,000.000 $650.000 $539.500 $710.420 $850.000 $640.000 $982.000 $875.000 $550.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 100.000 $245.000 $200.000 $365.100 $314.580 $215.000 $275.000 $270.000 $285.000 $185.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 420.000 $270.000 $200.000 $365.800 $313.880 $195.000 $225.000 $270.000 $285.000 $250.000
RIPRAP (STONE PROTECTION)(30 IN)
CY 75.000 $313.000 $200.000 $426.700 $332.100 $250.000 $250.000 $300.000 $285.000 $350.000
CONC BOX CULV (10 FT X 7 FT)
LF 200.000 $1,100.000 $1,600.000 $1,492.600 $2,132.670 $2,500.000 $2,500.000 $2,140.000 $2,125.000 $1,500.000
RC PIPE (CL III)(18 IN)
LF 40.000 $140.000 $120.000 $95.400 $117.890 $120.000 $120.000 $150.000 $120.000 $95.000
RC PIPE (CL III)(24 IN)
LF 393.000 $140.000 $150.000 $109.400 $139.090 $130.000 $150.000 $130.000 $140.000 $150.000
MANH (COMPL)(PRM)(72IN)
EA 2.000 $10,715.000 $6,600.000 $8,367.200 $14,874.420 $6,200.000 $18,000.000 $15,000.000 $7,500.000 $12,500.000
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 1.000 $4,300.000 $6,500.000 $4,282.100 $9,976.660 $5,600.000 $9,000.000 $4,200.000 $2,800.000 $12,500.000
INLET (COMPL)(POD)(FG)(3FTX3FT)
EA 1.000 $8,000.000 $5,000.000 $5,474.800 $12,866.910 $7,700.000 $9,000.000 $6,400.000 $5,300.000 $12,500.000
INL(CMP)(PAZD-CZ)(FG)(3FTX3FT-3FTX3FT)
EA 3.000 $6,430.000 $6,000.000 $5,499.200 $13,500.030 $6,300.000 $9,000.000 $6,400.000 $5,400.000 $12,500.000
WINGWALL (PW - 2) (HW=10 FT)
EA 1.000 $68,600.000 $50,000.000 $60,480.000 $55,851.220 $70,000.000 $50,000.000 $75,000.000 $45,000.000 $80,000.000
WINGWALL (SW - 0) (HW=13 FT)
EA 1.000 $26,000.000 $60,000.000 $74,702.100 $79,593.680 $90,000.000 $55,000.000 $78,000.000 $65,000.000 $90,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $1,500.000 $2,000.000 $2,173.400 $2,744.140 $1,200.000 $1,200.000 $2,500.000 $1,700.000 $1,850.000
REMOV STR (HEADWALL)
EA 2.000 $2,700.000 $2,000.000 $1,624.900 $8,899.030 $10,000.000 $3,000.000 $2,300.000 $20,000.000 $2,500.000
REMOV STR (PIPE)
LF 244.000 $60.000 $30.000 $50.100 $92.480 $100.000 $30.000 $90.000 $75.000 $50.000
REMOVING ROCK RIPRAP
LF 222.000 $175.000 $50.000 $27.900 $70.040 $35.000 $60.000 $150.000 $35.000 $100.000
MOBILIZATION
LS 1.000 $361,625.000 $300,000.000 $360,000.000 $360,000.000 $373,000.000 $350,000.000 $468,000.000 $500,000.000 $500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $5,000.000 $8,000.000 $2,069.300 $3,289.930 $15,000.000 $5,000.000 $22,000.000 $10,000.000 $15,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 358.000 $150.000 $120.000 $82.600 $142.270 $100.000 $100.000 $180.000 $300.000 $150.000
TMA (STATIONARY)
DAY 80.000 $275.000 $300.000 $302.600 $470.960 $260.000 $250.000 $200.000 $1,000.000 $250.000
TMA (MOBILE OPERATION)
HR 72.000 $90.000 $100.000 $58.200 $136.100 $60.000 $250.000 $200.000 $165.000 $550.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 82.000 $51.000 $55.000 $58.200 $45.000 $90.000 $60.000 $51.000 $100.000 $50.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 26.000 $75.000 $155.000 $87.300 $45.000 $93.000 $89.000 $75.000 $125.000 $50.000
ROCK FILTER DAMS (REMOVE)
LF 108.000 $15.000 $30.000 $29.100 $20.000 $20.000 $30.000 $28.000 $20.000 $20.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $35.000 $30.000 $34.900 $22.000 $25.000 $60.000 $75.000 $35.000 $40.000
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $12.000 $10.000 $11.600 $11.000 $10.000 $30.000 $29.000 $20.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,632.000 $4.000 $5.000 $2.300 $2.100 $5.000 $5.000 $5.000 $2.600 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,632.000 $1.250 $2.000 $0.600 $0.500 $1.500 $2.500 $2.000 $0.650 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 148.000 $10.000 $10.000 $10.500 $7.000 $10.000 $11.000 $10.000 $6.500 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 148.000 $2.500 $2.000 $2.300 $2.000 $2.000 $2.500 $3.000 $3.500 $9.000
CONSTRUCTING DETOURS
SY 4,083.000 $140.000 $100.000 $125.000 $141.920 $70.000 $100.000 $110.000 $125.000 $40.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
LF 2,740.000 $16.000 $20.000 $15.000 $12.830 $14.000 $25.000 $20.000 $32.000 $50.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 2)
LF 480.000 $22.000 $25.000 $15.000 $16.000 $14.000 $30.000 $39.000 $45.000 $50.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 8,120.000 $25.000 $18.000 $10.400 $6.040 $4.000 $20.000 $10.000 $20.000 $30.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 1,440.000 $25.000 $26.000 $10.400 $5.680 $4.000 $30.000 $10.000 $20.000 $30.000
PORT CTB (STKPL)(LOW PROF)(TY 1)
LF 2,740.000 $22.000 $10.000 $15.000 $13.200 $14.000 $10.000 $18.000 $25.000 $30.000
PORT CTB (STKPL)(LOW PROF)(TY 2)
LF 480.000 $35.000 $10.000 $15.000 $16.540 $14.000 $10.000 $42.000 $30.000 $30.000
DRIVEWAYS (CONC)
SY 65.000 $95.000 $120.000 $139.600 $278.340 $160.000 $125.000 $244.000 $160.000 $120.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,225.000 $33.000 $25.000 $26.200 $22.500 $24.000 $31.000 $27.000 $30.000 $25.000
REMOVE METAL BEAM GUARD FENCE
LF 369.000 $4.000 $5.000 $2.900 $2.500 $3.000 $2.500 $3.200 $3.000 $6.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,520.000 $2,700.000 $3,666.600 $3,150.000 $3,200.000 $3,500.000 $3,500.000 $4,000.000 $3,850.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $360.000 $400.000 $291.000 $250.000 $260.000 $378.000 $215.000 $300.000 $1,500.000
WIRE FENCE (TY A)
LF 144.000 $34.000 $40.000 $40.700 $10.000 $20.000 $41.000 $42.000 $20.000 $10.000
WIRE FENCE (REMOVE)
LF 144.000 $5.500 $7.000 $11.600 $2.000 $10.000 $41.000 $40.000 $5.000 $5.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $1,000.000 $1,500.000 $1,065.100 $915.000 $950.000 $1,170.000 $953.560 $1,200.000 $1,500.000
REMOVE SM RD SN SUP&AM
EA 1.000 $110.000 $150.000 $98.900 $85.000 $85.000 $130.000 $280.000 $100.000 $250.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 26,888.000 $0.500 $0.500 $0.400 $0.420 $0.300 $0.500 $0.350 $0.550 $0.500
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 23,658.000 $0.500 $0.600 $0.400 $0.420 $0.300 $0.500 $0.350 $0.550 $0.500
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 3,288.000 $1.400 $2.500 $2.400 $1.270 $3.600 $2.500 $2.200 $1.500 $1.000
RE PROFILE PM TY I(Y)6"(SLD)(100MIL)
LF 3,734.000 $0.850 $3.000 $2.400 $1.270 $3.600 $2.500 $2.200 $1.500 $1.000
RE PROFILE PM TY I(Y)6"(BRK)(100MIL)
LF 51.000 $0.850 $6.000 $5.800 $1.270 $12.000 $6.000 $5.300 $1.500 $1.000
REFL PAV MRKR TY II-A-A
EA 116.000 $7.000 $8.000 $7.000 $7.000 $7.000 $7.000 $6.400 $10.000 $6.000
ELIM EXT PM & MRKS (6")
LF 7,073.000 $0.700 $1.000 $0.600 $0.490 $0.510 $0.650 $0.600 $0.650 $1.000
UNDERSEAL COURSE
GAL 172.000 $7.600 $5.000 $17.500 $4.500 $4.000 $915.000 $4.000 $6.000 $6.000
HIGH FRICTION SURFACE TREATMENT
SY 1,395.000 $23.000 $25.000 $61.100 $21.500 $40.000 $61.000 $40.000 $40.000 $40.000
Totals: $4,016,607.050 $3,494,494.800 $3,650,761.550 $3,694,691.870 $3,833,095.730 $3,892,239.650 $4,659,352.360 $5,026,343.000 $5,569,073.500
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $20,330.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $6,750.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $6,115.00
Total: $33,195.00