MONTGOMERY IH 45 (0675-08-114)

Items: 97

County: MONTGOMERY
Length: N/A
Highway: IH 45
District: HOUSTON
Control Number: 0675-08-114
DBE Goal: N/A
Project: CC 675-8-114
Guaranty: N/A
Time: 252 WORKING DAYS
Engineer's Estimate: $7,368,740.09
Date: 06/29/2022 (3 years ago)
Contract Number: N/A
Type: CONSTRUCT FRONTAGE ROADS
Mail/Deliver Bids To: N/A
MATTHEW CONNELLY
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$7,368,740.09
$7,473,853.32
Over/Under Est: 1.43% $105,113.23
Over/Under Est: 4.9% $360,963.56
Amt Left: 3.42% $255,850.33
Over/Under Est: 6.04% $445,015.04
Amt Left: 4.55% $339,901.81
Delta: -1.09% -$84,051.48
Over/Under Est: 10.07% $742,149.96
Amt Left: 8.52% $637,036.73
Delta: -3.80% -$297,134.92
Over/Under Est: 14.89% $1,097,096.53
Amt Left: 13.27% $991,983.30
Delta: -4.38% -$354,946.57
Over/Under Est: 19.86% $1,463,332.43
Amt Left: 18.17% $1,358,219.20
Delta: -4.33% -$366,235.90
Over/Under Est: 20.28% $1,494,580.01
Amt Left: 18.59% $1,389,466.78
Delta: -0.35% -$31,247.58
$10,686,324.05
Over/Under Est: 45.02% $3,317,583.96
Amt Left: 42.98% $3,212,470.73
Delta: -20.57% -$1,823,003.95
Subcontractor Percentage Amount
WILLOW CITY SIGN & RAIL, INC. 0.87% $65,022.52
THIRD COAST SERVICES LLC 0.77% $57,548.67
BROCK CONSTRUCTION, LLC 0.71% $53,064.36
A&J REBAR LLC 0.66% $49,327.43
CEN TEX HYDROSEED, INC. 0.63% $47,085.28
HIGHWAY 1 LLC 0.45% $33,632.34
PRIMATE CONSTRUCTION, LP 0.31% $23,168.95
SOUTHEAST GRINDING AND GROOVING LLC 0.12% $8,968.62
LONESTAR TRAFFIC SAFETY, LLC 0.07% $5,231.70
J.KRU LAND SERVICES, LLC 0.05% $3,736.93
CURB PLANET INC. 0.01% $747.39
QUALITY TURF FARMS, L.C. 0.00% $0.00
Total: 4.65% $347,534.19

Bid Items & Bid Tabulations

97 Total 0 of 97
MONTGOMERY  |  IH 45  |  HOUSTON  |  0675-08-114  |  06/29/2022  |  $7,368,740.09  |  CC 675-8-114  |  CONSTRUCT FRONTAGE ROADS  |  252 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAMES CONSTRUCTION GROUP, LLC
MAIN LANE INDUSTRIES LTD.
STERLING DELAWARE HOLDING COMPANY, INC.
R CONSTRUCTION CIVIL, LLC
HARPER BROTHERS CONSTRUCTION LLC
SER CONSTRUCTION PARTNERS, LLC
TEXAS MATERIALS GROUP, INC.
ISI CONTRACTING, INC.
PREPARING ROW
STA 74.450 $3,500.000 $4,274.000 $5,000.000 $4,894.730 $3,500.000 $4,750.000 $3,100.000 $2,710.000 $922.000
REMOVING CONC (PAV)
SY 433.000 $10.000 $22.580 $90.000 $26.000 $20.000 $19.000 $42.200 $50.000 $8.000
REMOVING CONC (RIPRAP)
SY 579.000 $12.000 $6.300 $25.000 $8.000 $15.000 $7.630 $19.500 $20.000 $15.000
EXCAVATION (ROADWAY)
CY 15,473.000 $9.000 $8.640 $10.000 $5.000 $13.000 $10.000 $3.300 $7.000 $29.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 38,073.000 $13.000 $9.930 $10.000 $13.000 $13.000 $15.000 $17.200 $17.000 $22.000
BLOCK SODDING
SY 60,976.000 $3.500 $4.600 $5.500 $4.970 $4.000 $4.970 $5.500 $5.000 $4.700
STRAW OR HAY MULCH
SY 12,805.000 $0.250 $0.250 $0.500 $0.460 $0.190 $0.460 $0.500 $0.260 $0.280
BROADCAST SEED (TEMP) (WARM)
SY 610.000 $0.150 $0.250 $3.000 $2.970 $3.000 $2.970 $3.300 $0.750 $0.280
DRILL SEED (TEMP)(WARM OR COOL)
SY 12,195.000 $0.120 $0.300 $0.200 $0.180 $0.120 $0.180 $0.200 $0.120 $0.330
FERTILIZER
AC 15.240 $665.000 $750.000 $870.000 $866.200 $800.000 $866.200 $950.000 $1,250.000 $835.000
VEGETATIVE WATERING
MG 1,829.200 $18.000 $28.000 $15.000 $21.000 $30.000 $28.000 $35.000 $23.000 $31.000
LIME TRT (EXST MATL) (6")
SY 14,518.000 $5.000 $3.710 $3.500 $3.000 $3.000 $2.500 $5.600 $3.000 $6.800
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
TON 197.000 $200.000 $298.520 $300.000 $285.000 $275.000 $295.000 $280.000 $225.000 $211.000
CEMENT
TON 197.000 $200.000 $254.970 $180.000 $200.000 $210.000 $200.000 $180.000 $240.000 $194.000
CEMENT TREAT (EXIST MATL) (6")
SY 14,518.000 $4.000 $2.780 $3.000 $4.000 $3.000 $2.500 $5.600 $3.000 $16.000
CEM TRT(PLNT MX) (CL N)(TY E)(GR 4)(6")
SY 29,036.000 $17.000 $19.790 $20.000 $25.000 $23.000 $25.000 $16.900 $25.000 $18.800
ASPHALT STAB BASE (GR 4)(PG 64)
TON 1,644.000 $110.000 $117.270 $100.000 $114.000 $120.000 $109.000 $137.500 $150.000 $128.000
CONC PVMT (CONT REINF - CRCP) (10")
SY 26,886.000 $70.000 $83.670 $85.000 $84.000 $99.000 $92.500 $100.000 $110.000 $109.000
CEM STABIL BKFL
CY 4,169.000 $45.000 $45.890 $50.000 $50.000 $48.000 $65.000 $53.000 $57.000 $59.000
CEMENT STAB BACKFILL (INLET OR MH)
CY 410.000 $45.000 $45.890 $50.000 $50.000 $48.000 $65.000 $53.000 $66.000 $59.000
TRENCH EXCAVATION PROTECTION
LF 3,866.000 $2.500 $1.060 $1.000 $1.000 $1.000 $1.000 $0.100 $6.000 $2.200
DRILL SHAFT (SIGN MTS) (24 IN)
LF 15.000 $110.000 $622.060 $210.000 $210.000 $220.000 $210.000 $298.000 $170.000 $301.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 10.000 $225.000 $255.000 $255.000 $255.000 $330.000 $255.000 $281.000 $260.000 $284.000
CL C CONC (COLLAR)
EA 1.000 $2,000.000 $2,729.270 $3,000.000 $430.000 $1,500.000 $2,325.000 $1,458.000 $1,400.000 $1,330.000
RIPRAP (CONC)(5 IN)
CY 7.000 $440.000 $481.810 $800.000 $520.000 $800.000 $850.000 $676.000 $800.000 $520.030
CONC BOX CULV (5 FT X 3 FT)
LF 87.000 $300.000 $492.890 $520.000 $500.000 $460.000 $600.000 $475.000 $530.000 $998.940
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
LF 219.000 $700.000 $594.570 $550.000 $500.000 $570.000 $600.000 $496.000 $530.000 $670.420
RC PIPE (CL III)(18 IN)
LF 30.000 $90.000 $208.490 $225.000 $130.000 $160.000 $150.000 $164.000 $93.000 $111.780
RC PIPE (CL III)(24 IN)
LF 2,368.000 $105.000 $88.840 $80.000 $95.000 $85.000 $150.000 $91.000 $100.000 $117.570
RC PIPE (CL III)(30 IN)
LF 3,145.000 $135.000 $106.340 $95.000 $115.000 $105.000 $160.000 $112.000 $140.000 $139.660
RC PIPE (CL III)(36 IN)
LF 1,107.000 $170.000 $137.410 $140.000 $150.000 $140.000 $170.000 $158.000 $170.000 $199.150
RC PIPE (ARCH)(CL III)(DES 3)
LF 17.000 $200.000 $262.820 $380.000 $280.000 $250.000 $250.000 $361.000 $300.000 $355.100
INLET (COMPL)(TY AAD)
EA 7.000 $10,200.000 $8,438.420 $8,000.000 $9,200.000 $9,500.000 $10,200.000 $8,100.000 $8,700.000 $7,231.970
MANH (COMPL)(TY A)
EA 6.000 $8,000.000 $6,458.280 $6,000.000 $6,500.000 $6,500.000 $9,700.000 $10,300.000 $6,600.000 $6,116.870
INLET (COMPL)(CURB)(TY C)
EA 33.000 $6,000.000 $5,943.700 $5,500.000 $6,200.000 $6,000.000 $8,825.000 $10,800.000 $5,500.000 $3,614.910
JCT BOX (COMPL)(SPL)
EA 1.000 $65,000.000 $43,135.420 $35,000.000 $42,000.000 $35,000.000 $50,000.000 $81,370.000 $58,000.000 $40,741.760
INLET (COMPL)(EXT TY C)
EA 23.000 $2,500.000 $1,566.910 $1,800.000 $2,000.000 $2,000.000 $1,825.000 $2,668.000 $1,200.000 $3,614.910
WINGWALL (PW - 2) (HW=5 FT)
EA 1.000 $12,000.000 $16,548.380 $25,000.000 $16,000.000 $20,000.000 $40,250.000 $34,500.000 $22,000.000 $23,503.610
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $1,400.000 $1,585.670 $1,800.000 $950.000 $1,500.000 $1,900.000 $1,901.000 $1,300.000 $3,638.420
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 1.000 $1,800.000 $1,709.890 $2,250.000 $1,800.000 $1,700.000 $2,500.000 $3,918.000 $1,800.000 $3,638.420
SET (TY II) (DES 3) (RCP) (3: 1) (C)
EA 1.000 $2,100.000 $1,597.810 $6,750.000 $1,700.000 $1,900.000 $2,400.000 $3,832.000 $1,700.000 $4,751.370
REMOV STR (SET)
EA 1.000 $400.000 $440.290 $5,000.000 $350.000 $3,000.000 $975.000 $553.000 $600.000 $1,134.890
REMOV STR (HEADWALL)
EA 1.000 $1,400.000 $2,073.080 $3,000.000 $2,000.000 $5,000.000 $5,000.000 $880.000 $5,000.000 $2,269.780
MOBILIZATION
LS 1.000 $670,000.000 $740,000.000 $770,000.000 $780,000.000 $425,000.000 $45,000.000 $860,000.000 $640,000.000 $1,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $5,000.000 $3,791.450 $5,000.000 $2,200.000 $6,000.000 $5,600.000 $1,825.000 $4,000.000 $1,706.510
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 351.000 $40.000 $36.790 $36.800 $36.790 $37.000 $36.790 $41.000 $31.000 $31.760
ROCK FILTER DAMS (REMOVE)
LF 351.000 $12.000 $11.810 $11.800 $11.810 $12.000 $11.810 $13.000 $10.000 $9.120
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $30.000 $38.500 $38.500 $38.500 $40.000 $38.500 $42.000 $27.000 $23.770
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $10.000 $9.860 $9.850 $9.860 $10.000 $9.860 $11.000 $12.000 $11.880
TEMP SEDMT CONT FENCE (INSTALL)
LF 5,392.000 $3.000 $3.530 $3.500 $5.000 $3.500 $3.530 $3.900 $4.000 $3.850
TEMP SEDMT CONT FENCE (REMOVE)
LF 5,392.000 $1.300 $0.910 $1.000 $0.910 $1.000 $0.910 $1.000 $1.000 $2.780
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 424.000 $5.000 $5.770 $7.000 $5.770 $6.000 $5.770 $6.300 $4.000 $4.760
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 204.000 $6.000 $7.430 $9.000 $7.430 $8.000 $7.730 $8.200 $5.000 $7.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 628.000 $0.900 $1.670 $2.000 $1.670 $2.000 $1.670 $1.800 $1.000 $1.080
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 1,680.000 $50.000 $22.550 $38.000 $18.000 $70.000 $85.000 $84.100 $12.000 $146.270
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 1,680.000 $8.000 $7.930 $10.000 $15.000 $15.000 $15.000 $13.400 $12.000 $15.400
CONC CURB (MONO) (TY II)
LF 11,892.000 $6.000 $4.070 $5.000 $3.000 $4.000 $7.500 $3.900 $8.000 $6.210
CONC CURB (DOWEL) (TY II)
LF 251.000 $7.000 $11.980 $9.000 $12.000 $25.000 $13.500 $10.700 $40.000 $8.400
DRIVEWAYS (CONC)
SY 1,165.000 $63.000 $69.180 $84.000 $80.000 $100.000 $110.000 $97.200 $130.000 $89.130
CONC SIDEWALKS (6")
SY 6,978.000 $78.000 $52.520 $56.000 $48.000 $75.000 $85.000 $73.200 $66.000 $187.040
CURB RAMPS (TY 7)
EA 2.000 $2,000.000 $2,081.200 $3,000.000 $5,000.000 $3,500.000 $4,000.000 $1,936.000 $1,800.000 $1,556.750
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,500.000 $1,200.000 $1,200.000 $1,200.000 $1,300.000 $1,200.000 $990.000 $400.000 $1,116.030
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 2.000 $24,000.000 $25,750.000 $25,750.000 $25,750.000 $27,000.000 $25,750.000 $35,000.000 $26,000.000 $26,716.890
REMOVE RD IL ASM (TRANS-BASE)
EA 1.000 $2,000.000 $395.000 $395.000 $395.000 $1,500.000 $395.000 $435.000 $400.000 $439.610
IN RD IL (TY SA) 50T-8 (400W EQ) LED
EA 1.000 $4,100.000 $5,900.000 $5,900.000 $5,900.000 $7,000.000 $5,900.000 $6,490.000 $6,000.000 $6,137.290
CONDT (PVC) (SCH 40) (3") (CONC ENCSE)
LF 1,675.000 $13.000 $19.750 $19.750 $19.750 $30.000 $19.750 $21.700 $20.000 $20.540
CONDT (PVC) (SCH 80) (2")
LF 325.000 $10.000 $12.000 $12.000 $12.000 $16.000 $12.000 $13.200 $12.000 $12.480
CONDT (PVC) (SCH 80) (3") (BORE)
LF 225.000 $20.000 $29.000 $29.000 $29.000 $50.000 $29.000 $31.900 $30.000 $30.170
ELEC CONDR (NO.6) BARE
LF 325.000 $1.500 $1.950 $1.950 $1.950 $2.300 $1.950 $2.100 $2.000 $2.030
ELEC CONDR (NO.6) INSULATED
LF 650.000 $2.000 $2.100 $2.100 $2.100 $2.400 $2.100 $2.300 $2.200 $2.180
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $600.000 $600.000 $600.000 $600.000 $600.000 $600.000 $7,667.000 $750.000 $728.080
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $590.000 $1,760.000 $850.000 $850.000 $900.000 $850.000 $990.000 $920.000 $1,016.820
REMOVE SM RD SN SUP&AM
EA 4.000 $88.000 $85.000 $85.000 $85.000 $90.000 $85.000 $110.000 $85.000 $104.020
INSTALL LRSS (STRUCT STEEL)
LB 509.200 $5.000 $6.000 $6.000 $6.000 $6.000 $6.000 $14.100 $6.000 $13.330
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 56.000 $28.000 $25.000 $25.000 $25.000 $30.000 $25.000 $33.000 $35.000 $33.380
REMOVE DELIN & OBJECT MARKER ASSMS
EA 56.000 $33.000 $20.000 $20.000 $20.000 $20.000 $20.000 $44.000 $10.000 $22.880
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 2,014.000 $1.500 $2.000 $2.000 $2.000 $2.000 $2.000 $0.400 $2.000 $1.560
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 1,033.000 $1.500 $2.000 $2.000 $2.000 $2.000 $2.000 $1.300 $2.000 $1.560
REFL PAV MRKR TY I-A
EA 21.000 $3.500 $10.000 $10.000 $10.000 $11.000 $10.000 $5.500 $10.000 $10.400
REFL PAV MRKR TY II-C-R
EA 184.000 $4.000 $10.000 $10.000 $10.000 $11.000 $10.000 $5.200 $10.000 $6.240
ELIM EXT PAV MRK & MRKS (6")
LF 2,531.000 $0.600 $0.750 $0.750 $0.750 $0.800 $0.750 $0.400 $0.800 $0.750
ELIM EXT PAV MRK & MRKS (ARROW)
EA 2.000 $55.000 $80.000 $80.000 $80.000 $80.000 $80.000 $77.000 $85.000 $67.610
ELIM EXT PAV MRK & MRKS (WORD)
EA 2.000 $55.000 $80.000 $80.000 $80.000 $80.000 $80.000 $110.000 $85.000 $67.610
PAV SURF PREP FOR MRK (6")
LF 7,178.000 $0.100 $0.100 $0.100 $0.100 $0.100 $0.100 $0.100 $0.100 $0.160
PAV SURF PREP FOR MRK (8")
LF 1,227.000 $0.120 $0.200 $0.200 $0.200 $0.200 $0.200 $0.200 $0.200 $0.210
PAV SURF PREP FOR MRK (12")
LF 428.000 $0.300 $0.500 $0.500 $0.500 $0.550 $0.500 $0.300 $0.500 $0.310
PAV SURF PREP FOR MRK (ARROW)
EA 2.000 $10.000 $10.000 $10.000 $10.000 $10.000 $10.000 $22.000 $10.000 $26.010
MULTIPOLYMER PAV MRK (W)(6")(SLD)
LF 826.000 $1.400 $1.250 $1.250 $1.250 $1.300 $1.250 $0.600 $1.300 $2.340
MULTIPOLYMER PAV MRK (W)(6")(BRK)
LF 3,176.000 $1.000 $1.250 $1.250 $1.250 $1.300 $1.250 $0.600 $1.300 $2.340
MULTIPOLYMER PAV MRK (W)(8")(SLD)
LF 491.000 $2.000 $2.000 $2.000 $2.000 $2.000 $2.000 $1.100 $2.000 $3.170
MULTIPOLYMER PAV MRK (Y)(8")(SLD)
LF 736.000 $1.500 $2.000 $2.000 $2.000 $2.000 $2.000 $1.100 $2.000 $3.170
MULTIPOLYMER PAV MRK (Y)(12")(SLD)
LF 428.000 $4.000 $8.000 $8.000 $8.000 $8.000 $8.000 $3.300 $8.000 $6.240
MULTIPOLYMER PAV MRK (BLK)(6")(BRK)
LF 3,176.000 $1.000 $2.000 $2.000 $2.000 $2.000 $2.000 $0.700 $2.000 $2.760
MULTIYPOLYMER PAV MRK (W) (ARROW)
EA 2.000 $175.000 $350.000 $350.000 $350.000 $350.000 $350.000 $160.000 $350.000 $265.260
TMA (STATIONARY)
DAY 20.000 $300.000 $185.910 $600.000 $50.000 $450.000 $300.000 $176.000 $250.000 $417.580
TMA (MOBILE OPERATION)
HR 56.000 $75.000 $53.540 $300.000 $50.000 $200.000 $60.000 $71.000 $68.000 $41.750
ITS GND BOX(PCAST) TY 1 (243636)W/APRN
EA 1.000 $3,200.000 $3,625.000 $3,625.000 $3,625.000 $5,700.000 $3,625.000 $3,990.000 $3,700.000 $4,034.430
Totals: $7,368,740.090 $7,473,853.320 $7,729,703.650 $7,813,755.146 $8,110,890.050 $8,465,836.628 $8,832,072.520 $8,863,320.100 $10,686,324.056