MONTGOMERY FM 1488 (0523-09-023)
Items: 45
County: MONTGOMERY
Length: 17.4250 MILES
Highway: FM 1488
District: HOUSTON
Control Number: 0523-09-023
DBE Goal: 0.0%
Project: F 2026(602)
Guaranty: $56,000.00
Time: 651 WORKING DAYS
Engineer's Estimate: $2,821,414.65
Date: 05/06/2026 (5 weeks ago) Changed
Contract Number: 5263218
Type: LANDSCAPE DEVELOPMENT
Project ID: A00199223
Contract Type: Federal
Project Description: LANDSCAPE DEVELOPMENT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ABE GUZMAN
MATTHEW CONNELLY
MONTGOMERY FM 1488 (0523-09-023)
Project Name: N/A
Project: F 2026(602)
Length: 4.0240 MILES
Project Type: CONSTRUCTION
Limits From: FM 1774
Limits To: SH 149
Project Description: LANDSCAPE DEVELOPMENT
MONTGOMERY FM 1488 (0523-10-049)
Project Name: FM 1488; FM 149 TO IH 45
Project: F 2026(602)
Length: 0.0000 MILES
Project Type: LANDSCAPE & SCENIC ENHANCEMENT
Limits From: FM 149
Limits To: IH 45
Project Description: LANDSCAPE DEVELOPMENT
MONTGOMERY SH 105 (0338-03-094)
Project Name: SH 105; FM 2854 TO IH 45
Project: F 2026(603)
Length: 13.4010 MILES
Project Type: LANDSCAPE & SCENIC ENHANCEMENT
Limits From: FM 2854
Limits To: IH 45
Project Description: LANDSCAPE DEVELOPMENT
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,821,414.65 | |||
| $2,127,626.65 |
-24.59%
-$693,788.00
|
|||
| $2,335,690.50 |
-17.22%
-$485,724.15
|
9.78%
$208,063.85
|
||
| $2,468,442.19 |
-12.51%
-$352,972.46
|
16.02%
$340,815.54
|
-5.68%
-$132,751.69
|
|
| $2,611,819.54 |
-7.43%
-$209,595.11
|
22.76%
$484,192.89
|
-5.81%
-$143,377.35
|
|
| $6,058,825.04 |
114.74%
$3,237,410.39
|
184.77%
$3,931,198.39
|
-131.98%
-$3,447,005.50
|
E
Engineer's Estimate
$2,821,414.65
1
Awarded
$2,127,626.65
Over/Under Est:
-24.59%
-$693,788.00
$2,335,690.50
Over/Under Est:
-17.22%
-$485,724.15
Amt Left:
9.78%
$208,063.85
$2,468,442.19
Over/Under Est:
-12.51%
-$352,972.46
Amt Left:
16.02%
$340,815.54
Delta:
-5.68%
-$132,751.69
$2,611,819.54
Over/Under Est:
-7.43%
-$209,595.11
Amt Left:
22.76%
$484,192.89
Delta:
-5.81%
-$143,377.35
$6,058,825.04
Over/Under Est:
114.74%
$3,237,410.39
Amt Left:
184.77%
$3,931,198.39
Delta:
-131.98%
-$3,447,005.50
Bid Items & Bid Tabulations
45
Total
0 of 45
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| ENVIRONMENTAL: CONTRACTOR FORCE ACCOUNT WORK (PART) | $4,750.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $3,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $13,125.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,625.00 |
| Total: | $23,500.00 |