Show Job Controls
Bid Cobra

MONTGOMERY SL 494 (0177-14-038)

Items: 66

County: MONTGOMERY
Length: 0.0000 MILES
Highway: SL 494
District: HOUSTON
Control Number: 0177-14-038
DBE Goal: 0.0%
Project: F 2026(598)
Guaranty: $98,000.00
Time: 109 WORKING DAYS
Engineer's Estimate: $4,713,675.29
Date: 05/06/2026 (5 weeks ago)
Contract Number: 5263015
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00130695
Contract Type: Federal
Project Description: BASE REPAIR, 1.5-INCH OVERLAY, PAVEMENT MARKINGS, AND TURN LANES AT KNOX ROAD
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
MATTHEW CONNELLY
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$4,713,675.29
$5,153,277.70
Over/Under Est: 9.33% $439,602.41
Over/Under Est: 21.78% $1,026,752.97
Amt Left: 11.39% $587,150.56
Over/Under Est: 23.84% $1,123,773.70
Amt Left: 13.28% $684,171.29
Delta: -1.69% -$97,020.73
$5,856,409.71
Over/Under Est: 24.24% $1,142,734.42
Amt Left: 13.64% $703,132.01
Delta: -0.32% -$18,960.72
Over/Under Est: 27.31% $1,287,492.77
Amt Left: 16.45% $847,890.36
Delta: -2.47% -$144,758.35
$6,462,752.50
Over/Under Est: 37.11% $1,749,077.21
Amt Left: 25.41% $1,309,474.80
Delta: -7.69% -$461,584.44

Bid Items & Bid Tabulations

66 Total 0 of 66
MONTGOMERY  |  SL 494  |  HOUSTON  |  0177-14-038  |  05/06/2026  |  $4,713,675.29  |  F 2026(598)  |  SURF/ROADWAY RESTOR  |  109 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DURWOOD GREENE CONSTRUCTION CO.
ENVIRONMENTAL ALLIES, INC.
TEXAS MATERIALS GROUP, INC.
HAYDEN PAVING, INC.
FOUTSCO PAVING COMPANY, LLC
POSILLICO CIVIL, INC.
PREPARING ROW
STA 26.000 $1,500.000 $2,500.000 $3,000.000 $1,250.000 $4,000.000 $500.000 $15,000.000
REMOV CONC (MOWSTRIP)
LF 3,724.000 $20.000 $25.000 $22.000 $26.000 $28.000 $20.000 $3.000
REMOV CONC (CURB)
LF 900.000 $7.000 $15.000 $6.000 $13.750 $50.000 $15.000 $7.000
RMV (18") TRT/UNTRT BASE & ASPH PAV
SY 3,834.000 $6.500 $10.000 $14.000 $0.100 $13.500 $20.000 $30.000
SUBGR WIDEN (DC)
STA 26.000 $300.000 $2,500.000 $1,050.000 $1,930.000 $2,750.000 $400.000 $820.000
EMBANK (VEH)(DC)(TY C)
CY 1,278.000 $25.000 $30.000 $30.000 $26.500 $11.000 $35.000 $43.000
BACKFILL (TY A)
STA 332.000 $150.000 $150.000 $300.000 $311.000 $200.000 $125.000 $420.000
BLOCK SODDING
SY 5,801.000 $5.000 $6.250 $7.000 $6.000 $5.000 $4.650 $9.000
VEGETATIVE WATERING
TGL 143.000 $75.000 $30.000 $35.000 $84.500 $45.000 $1.000 $20.000
SLV, HAUL, & STKPL REL APH PV (9")
SY 3,834.000 $20.000 $10.000 $7.500 $0.100 $7.000 $7.000 $1.000
SP MIXES SP-B PG64-22
TON 1,725.000 $125.000 $130.000 $150.000 $175.000 $155.000 $150.000 $220.000
SP MIXES SP-D SAC-A PG70-22
TON 14,556.000 $140.000 $170.000 $160.000 $151.000 $165.000 $168.400 $165.000
TACK COAT
GAL 30,817.000 $1.000 $3.000 $5.000 $0.110 $4.730 $0.100 $10.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 16,737.000 $60.000 $40.000 $73.000 $96.000 $75.000 $75.000 $80.000
PLANE ASPH CONC PAV (0" TO 1.5")
SY 8,740.000 $2.200 $7.000 $3.750 $15.000 $5.000 $1.000 $9.000
CEM STABIL BKFL
CY 95.000 $150.000 $1.000 $125.000 $125.000 $60.000 $150.000 $75.000
CONC STR REPAIR(RAPID DECK REP(PRT DPT)
SF 100.000 $190.000 $150.000 $120.000 $200.000 $225.000 $125.000 $106.000
RIPRAP (MOW STRIP)(4 IN)
CY 179.000 $600.000 $850.000 $850.000 $970.000 $900.000 $800.000 $650.000
MOBILIZATION
LS 1.000 $226,421.000 $200,000.000 $224,545.660 $375,000.000 $200,000.000 $300,000.000 $114,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $5,000.000 $7,000.000 $8,000.000 $1,580.000 $6,000.000 $75,000.000 $2,600.000
TMA (STATIONARY)
DAY 148.000 $225.000 $300.000 $400.000 $254.000 $250.000 $1.000 $330.000
TMA (MOBILE OPERATION)
DAY 150.000 $200.000 $150.000 $475.000 $1.000 $425.000 $1.000 $740.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,700.000 $3.000 $3.000 $4.000 $1.000 $5.000 $1.000 $3.600
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,700.000 $1.000 $1.000 $1.000 $0.500 $2.000 $1.000 $1.200
CONC CURB (DOWEL)(SLOTTED)
LF 900.000 $22.000 $65.000 $6.500 $22.000 $75.000 $65.000 $37.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 71,440.000 $0.190 $0.250 $0.300 $0.090 $0.200 $0.190 $0.200
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 19,170.000 $0.210 $0.280 $0.400 $0.160 $0.200 $0.190 $0.200
MTL W-BEAM GD FEN (TIM POST)
LF 3,625.000 $24.000 $27.000 $26.500 $23.750 $23.000 $24.000 $27.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 14.000 $1,630.000 $2,250.000 $2,000.000 $2,052.000 $2,000.000 $1,600.000 $1,900.000
SHORT RADIUS (28")
LF 180.000 $50.000 $45.000 $50.000 $24.000 $32.500 $38.000 $43.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 4.000 $1,500.000 $1,500.000 $1,600.000 $1,490.000 $1,420.000 $1,200.000 $1,500.000
MTL BM GD FEN TRANS (31"-28")
EA 4.000 $500.000 $1,200.000 $1,200.000 $858.000 $815.000 $990.000 $1,200.000
REMOVE METAL BEAM GUARD FENCE
LF 3,625.000 $2.500 $3.500 $3.550 $2.000 $2.000 $2.000 $4.000
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $250.000 $200.000 $250.000 $263.000 $250.000 $200.000 $170.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 14.000 $240.000 $200.000 $235.000 $158.000 $150.000 $200.000 $170.000
GUARDRAIL END TREATMENT (INSTALL)
EA 18.000 $3,000.000 $3,500.000 $3,550.000 $3,235.000 $3,075.000 $3,100.000 $3,700.000
GUARDRAIL END TREATMENT (REMOVE)
EA 18.000 $200.000 $250.000 $220.000 $210.000 $200.000 $200.000 $205.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 25.000 $200.000 $300.000 $285.000 $332.000 $250.000 $250.000 $275.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 3.000 $350.000 $400.000 $335.000 $385.000 $320.000 $300.000 $360.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 5.000 $350.000 $900.000 $850.000 $753.000 $760.000 $550.000 $860.000
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 400.000 $20.000 $28.000 $27.500 $38.500 $25.000 $40.000 $28.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 211.000 $450.000 $550.000 $535.000 $510.500 $495.000 $675.000 $556.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $900.000 $750.000 $715.000 $690.000 $685.000 $775.000 $770.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 6.000 $800.000 $950.000 $925.000 $837.000 $830.000 $1,000.000 $933.000
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
EA 1.000 $1,200.000 $1,692.000 $1,650.000 $1,721.000 $1,600.000 $1,000.000 $1,700.000
IN SM RD SN SUP&AM (RAIL MOUNT)
EA 1.000 $5,000.000 $6,000.000 $5,750.000 $7,211.000 $5,345.000 $7,500.000 $6,050.000
REMOVE SM RD SN SUP&AM
EA 107.000 $80.000 $85.000 $90.000 $84.000 $70.000 $90.000 $80.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 39.000 $25.000 $30.000 $27.000 $34.000 $32.500 $25.000 $26.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 291.000 $1.000 $2.500 $3.300 $0.750 $2.500 $1.000 $3.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,808.000 $0.850 $2.500 $2.750 $0.750 $2.500 $1.000 $3.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 5,787.000 $0.900 $1.200 $1.100 $1.160 $1.000 $0.880 $1.500
ALL-WTHER PM TY I (W)6"(SLD)(100MIL)
LF 77,017.000 $0.800 $0.750 $0.950 $0.750 $0.900 $0.520 $1.000
ALL-WTHER PM TY I (W)6"(BRK)(100MIL)
LF 478.000 $1.150 $0.750 $1.550 $0.750 $1.500 $0.540 $2.000
ALL-WTHER PM TY I (Y)6"(SLD)(100MIL)
LF 64,160.000 $0.850 $0.750 $0.950 $0.750 $0.900 $0.520 $1.000
ALL-WTHER PM TY I (Y)6"(BRK)(100MIL)
LF 4,193.000 $0.880 $0.800 $1.100 $0.800 $1.000 $0.540 $1.500
ALL-WTHER PM TY I (W) 8"(DOT)(100MIL)
LF 505.000 $1.250 $2.000 $2.200 $1.210 $2.000 $1.000 $3.000
PREFAB PM TY C (W)(24")(SLD)
LF 1,117.000 $12.500 $14.000 $17.750 $13.700 $17.000 $12.000 $20.000
PREFAB PM TY C (W)(ARROW)
EA 56.000 $200.000 $230.000 $240.000 $226.000 $205.000 $200.000 $240.000
PREFAB PM TY C (W)(DBL ARROW)
EA 1.000 $300.000 $400.000 $500.000 $279.000 $450.000 $300.000 $505.000
PREFAB PM TY C (W)(WORD)
EA 49.000 $300.000 $265.000 $350.000 $237.000 $285.000 $280.000 $330.000
PREFAB PM TY C (W)(RR XING)
EA 7.000 $550.000 $500.000 $725.000 $421.000 $690.000 $350.000 $780.000
REFL PAV MRKR TY I-C
EA 343.000 $5.000 $6.300 $5.750 $6.350 $5.000 $4.000 $6.000
REFL PAV MRKR TY II-A-A
EA 2,893.000 $5.000 $6.300 $5.500 $6.350 $5.000 $3.790 $6.000
ELIM EXT PM & MRKS (6")
LF 3,430.000 $0.750 $0.550 $1.100 $0.470 $1.000 $1.000 $1.500
PAV SURF PREP FOR MRK (6")
LF 3,430.000 $0.500 $0.150 $0.250 $0.110 $0.200 $1.000 $0.250
REMOV RDSD FLSH BCN AM (SOLAR PWRD)
EA 2.000 $1,000.000 $1,900.000 $1,650.000 $1,500.000 $1,800.000 $1,500.000 $2,100.000
Totals: $4,713,675.290 $5,153,277.700 $5,740,428.260 $5,837,448.990 $5,856,409.710 $6,001,168.060 $6,462,752.500
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FORCE ACCOUNT WORK (PART) $5,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $13,704.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $25,708.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,750.00
Total: $46,162.00