MONTGOMERY SH 75 (0110-03-084)
Items: 57
County: MONTGOMERY
Length: 2.9210 MILES
Highway: SH 75
District: HOUSTON
Control Number: 0110-03-084
DBE Goal: 0.0%
Project: C 110-3-84
Guaranty: $85,000.00
Time: 70 WORKING DAYS
Engineer's Estimate: $4,233,682.55
Date: 02/07/2025 (1 year ago)
Contract Number: 2253212
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00130693
Project Description: BASE REPAIR, 2 INCH MILL, AND 2 INCH OVERLAY
Mail/Deliver Bids To: N/A
ABE GUZMAN
MATTHEW CONNELLY
MONTGOMERY SH 75 (0110-03-084)
Project Name: N/A
Project: C 110-3-84
Length: 1.6980 MILES
Project Type: CONSTRUCTION
Limits From: SL 336N
Limits To: SH 105
Project Description: BASE REPAIR, 2 INCH MILL, AND 2 INCH OVERLAY
MONTGOMERY SH 75 (0110-04-203)
Project Name: SH 75, SH 105 TO GLADSTELL ST
Project: C 110-4-203
Length: 1.2230 MILES
Project Type: OVERLAY
Limits From: SH 105
Limits To: GLADSTELL ST
Project Description: BASE REPAIR, 2 INCH MILL, AND 2 INCH OVERLAY
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,233,682.55 | |||
| $3,303,124.11 |
-21.98%
-$930,558.44
|
|||
| $3,596,899.10 |
-15.04%
-$636,783.45
|
8.89%
$293,774.99
|
||
| $3,665,994.35 |
-13.41%
-$567,688.20
|
10.99%
$362,870.24
|
-1.92%
-$69,095.25
|
|
| $3,868,838.57 |
-8.62%
-$364,843.98
|
17.13%
$565,714.46
|
-5.53%
-$202,844.22
|
|
| $5,142,255.90 |
21.46%
$908,573.35
|
55.68%
$1,839,131.79
|
-32.91%
-$1,273,417.33
|
|
| $5,150,319.35 |
21.65%
$916,636.80
|
55.92%
$1,847,195.24
|
-0.16%
-$8,063.45
|
E
Engineer's Estimate
$4,233,682.55
$3,303,124.11
Over/Under Est:
-21.98%
-$930,558.44
$3,596,899.10
Over/Under Est:
-15.04%
-$636,783.45
Amt Left:
8.89%
$293,774.99
$3,665,994.35
Over/Under Est:
-13.41%
-$567,688.20
Amt Left:
10.99%
$362,870.24
Delta:
-1.92%
-$69,095.25
$3,868,838.57
Over/Under Est:
-8.62%
-$364,843.98
Amt Left:
17.13%
$565,714.46
Delta:
-5.53%
-$202,844.22
$5,142,255.90
Over/Under Est:
21.46%
$908,573.35
Amt Left:
55.68%
$1,839,131.79
Delta:
-32.91%
-$1,273,417.33
$5,150,319.35
Over/Under Est:
21.65%
$916,636.80
Amt Left:
55.92%
$1,847,195.24
Delta:
-0.16%
-$8,063.45
| Subcontractor | Percentage | Amount |
|---|---|---|
| TRP CONSTRUCTION GROUP, LLC | 6.37% | $216,056.68 |
| WILLOW CITY SIGN & RAIL, INC. | 1.81% | $61,391.30 |
| SUPERIOR TRAFFIC CONTROL, LLC | 0.25% | $8,479.46 |
| Total: | 8.43% | $285,927.44 |
Bid Items & Bid Tabulations
57
Total
0 of 57