Show Job Controls
Bid Cobra

MONTAGUE US 81 (0013-02-021)

Items: 30

County: MONTAGUE
Length: N/A
Highway: US 81
District: WICHITA FALLS
Control Number: 0013-02-021
DBE Goal: N/A
Project: NH 2017(269)
Guaranty: N/A
Time: 74 WORKING DAYS
Engineer's Estimate: $6,431,588.89
Date: 11/04/2016 (9 years ago)
Contract Number: N/A
Type: SEAL COAT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$6,431,588.89
$5,209,700.38
Over/Under Est: -19% -$1,221,888.51
Over/Under Est: -13.34% -$857,775.26
Amt Left: 6.99% $364,113.25
Over/Under Est: -11.15% -$717,148.42
Amt Left: 9.69% $504,740.09
Delta: -2.52% -$140,626.84
Over/Under Est: -7.69% -$494,836.87
Amt Left: 13.96% $727,051.64
Delta: -3.89% -$222,311.55

Bid Items & Bid Tabulations

30 Total 0 of 30
MONTAGUE  |  US 81  |  WICHITA FALLS  |  0013-02-021  |  11/04/2016  |  $6,431,588.89  |  NH 2017(269)  |  SEAL COAT  |  74 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RONALD R. WAGNER & CO., LP
NORTHEASTERN PAVERS, INC.
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
LIPHAM ASPHALT AND PAVING COMPANY, LLC
ASPH (AC-20-5TR)
GAL 1,159,997.000 $2.000 $1.889 $1.800 $1.720 $2.050
AGGR(TY-PB GR-3 SAC-B)
CY 4,831.000 $65.000 $49.120 $63.000 $60.000 $56.000
AGGR(TY-PB GR-5 SAC-B)
CY 7,989.000 $65.000 $49.480 $63.000 $61.000 $58.000
AGGR(TY-PE GR-4 SAC-B)
CY 16,013.000 $65.000 $50.450 $63.000 $61.000 $57.000
MOBILIZATION
LS 1.000 $659,401.940 $200,781.000 $285,000.000 $585,000.000 $415,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $5,000.000 $0.010 $0.010 $1,000.000 $7,500.000
INTERSECTIONS (SURF TREAT)
SY 25,884.000 $2.500 $1.850 $1.100 $1.500 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 975.000 $0.100 $0.010 $0.010 $0.010 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 103,871.000 $0.100 $0.010 $0.010 $0.010 $1.000
REFL PAV MRK TY I (W)8"(SLD)(060MIL)
LF 300.000 $0.350 $0.300 $1.000 $1.000 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 3,614.000 $1.000 $0.500 $0.400 $0.400 $0.400
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 2,926.000 $0.650 $0.220 $0.220 $0.217 $0.217
RE PM W/RET REQ TY I (W)4"(SLD)(060MIL)
LF 1,188,762.000 $0.150 $0.140 $0.150 $0.148 $0.148
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,219,229.000 $0.250 $0.220 $0.220 $0.215 $0.215
RE PM W/RET REQ TY I (Y)4"(BRK)(060MIL)
LF 415,020.000 $0.170 $0.140 $0.150 $0.148 $0.148
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 183,295.000 $0.250 $0.220 $0.220 $0.215 $0.215
RE PM W/RET REQ TY I (Y)4"(SLD)(060MIL)
LF 2,601,785.000 $0.160 $0.140 $0.150 $0.148 $0.148
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 999,134.000 $0.250 $0.220 $0.220 $0.217 $0.217
PREFAB PAV MRK TY C (W) (18") (SLD)
LF 182.000 $10.000 $10.000 $8.000 $8.000 $8.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 893.000 $10.000 $12.000 $12.000 $12.000 $12.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 14.000 $200.000 $200.000 $195.000 $195.000 $195.000
PREFAB PAV MRK TY C (W) (WORD)
EA 14.000 $200.000 $200.000 $200.000 $200.000 $200.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 3.000 $500.000 $400.000 $400.000 $400.000 $400.000
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 1,133.000 $10.000 $12.000 $12.000 $12.000 $12.000
REFL PAV MRKR TY II-A-A
EA 60,191.000 $2.500 $2.500 $2.250 $2.250 $2.250
REFL PAV MRKR TY II-C-R
EA 9,081.000 $3.150 $2.500 $2.250 $2.250 $2.250
ELIM EXT PAV MRK & MRKS (24")
LF 584.000 $3.000 $2.000 $5.000 $5.000 $5.000
ELIM EXT PAV MRK & MRKS (ARROW)
EA 14.000 $50.000 $24.000 $50.000 $50.000 $50.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 10.000 $50.000 $50.000 $50.000 $50.000 $50.000
ELIM EXT PAV MRK & MRKS (RR XING)
EA 5.000 $90.000 $100.000 $150.000 $150.000 $150.000
Totals: $6,431,588.890 $5,209,700.383 $5,573,813.630 $5,714,440.496 $5,936,752.046