MITCHELL FM 1308 (0518-01-020)

Items: 55

County: MITCHELL
Length: N/A
Highway: FM 1308
District: ABILENE
Control Number: 0518-01-020
DBE Goal: 500.0%
Project: BR 2024(634)
Guaranty: N/A
Time: 123 WORKING DAYS
Engineer's Estimate: $1,523,337.14
Date: 12/05/2023 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
RYAN SAYLES
LARISSA HALFORD
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,523,337.14
$1,415,995.00
Over/Under Est: -7.05% -$107,342.14
Over/Under Est: -6.4% -$97,528.74
Amt Left: 0.69% $9,813.40
$1,525,733.90
Over/Under Est: 0.16% $2,396.76
Amt Left: 7.75% $109,738.90
Delta: -7.01% -$99,925.50
Over/Under Est: 5.63% $85,699.36
Amt Left: 13.63% $193,041.50
Delta: -5.46% -$83,302.60
Subcontractor Percentage Amount
J. R. (JOE) RAMON & SONS, INC. 1.76% $24,921.51
BARRICADES UNLIMITED 0.00% $0.00
Total: 1.76% $24,921.51

Bid Items & Bid Tabulations

55 Total 0 of 55
MITCHELL  |  FM 1308  |  ABILENE  |  0518-01-020  |  12/05/2023  |  $1,523,337.14  |  BR 2024(634)  |  BRIDGE REPL  |  123 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DELGADO'S CONTRACTORS, LLC
A GREATER AUSTIN DEVELOPMENT COMPANY, LLC
PMCO CONSTRUCTION LLC
COPPELL CONSTRUCTION CO., INC.
REMOVING STAB BASE AND ASPH PAV (6")
SY 651.000 $33.640 $50.000 $9.000 $28.500 $22.000
EXCAVATION (ROADWAY)
CY 162.000 $40.000 $45.000 $44.000 $42.000 $50.000
EXCAVATION (CHANNEL)
CY 377.000 $70.000 $45.000 $33.000 $46.000 $55.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 486.000 $60.000 $85.000 $31.000 $58.000 $66.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 1,880.000 $2.000 $3.000 $2.000 $3.000 $1.500
VEGETATIVE WATERING
MG 15.800 $80.000 $102.990 $300.000 $150.000 $20.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 116.000 $12.000 $8.000 $15.000 $4.000 $3.500
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 112.000 $150.000 $250.000 $148.500 $215.000 $108.000
PRIME COAT (MC-30)
GAL 162.000 $20.000 $20.000 $45.000 $50.000 $16.000
ASPH (MULTI OPTION)
GAL 324.000 $22.000 $15.000 $25.000 $50.000 $18.000
ASPH (AC-20-5TR)
GAL 291.000 $15.000 $15.000 $25.000 $50.000 $71.000
AGGR(TY-B GR-3 SAC-B)
CY 7.000 $800.000 $500.000 $2,000.000 $2,000.000 $805.000
AGGR(TY-PB GR-4 SAC-B)
CY 7.000 $1,000.000 $500.000 $2,000.000 $2,000.000 $855.000
STRUCT EXCAV (BRIDGE)
CY 29.200 $95.000 $54.150 $130.000 $110.000 $80.000
CEM STABIL BKFL
CY 56.600 $375.000 $275.000 $500.000 $376.000 $500.000
DRILL SHAFT (24 IN)
LF 464.000 $300.000 $565.000 $305.000 $430.000 $430.000
CL C CONC (ABUT)
CY 25.400 $2,250.000 $2,100.000 $2,060.000 $2,550.000 $2,600.000
CL C CONC (CAP)
CY 20.800 $2,250.000 $2,000.000 $2,360.000 $2,950.000 $2,500.000
CL C CONC (COLUMN)
CY 4.900 $2,250.000 $2,200.000 $4,080.000 $4,450.000 $5,300.000
REINF CONC SLAB (SLAB BEAM)
SF 4,390.000 $50.000 $32.500 $35.600 $43.000 $34.000
APPROACH SLAB
CY 81.300 $1,500.000 $1,050.000 $955.000 $1,000.000 $1,100.000
PRESTR CONC SLAB BEAM (4SB12)
LF 474.000 $264.750 $300.000 $263.850 $250.000 $336.000
PRESTR CONC SLAB BEAM (5SB12)
LF 474.000 $285.000 $300.000 $263.850 $260.000 $345.000
EPOXY WATERPROOF FINISH
SF 308.000 $25.000 $50.000 $26.000 $40.000 $40.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 169.000 $275.000 $275.000 $350.000 $264.000 $315.000
RIPRAP (MOW STRIP)(4 IN)
CY 24.000 $1,000.000 $600.000 $1,150.000 $940.000 $900.000
RAIL (TY T223)
LF 268.000 $200.000 $180.000 $265.000 $220.000 $275.000
ARMOR JOINT
LF 81.300 $190.000 $200.000 $196.000 $150.000 $185.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $100,000.000 $60,000.000 $108,000.000 $65,000.000 $125,000.000
MOBILIZATION
LS 1.000 $138,485.200 $75,000.000 $148,000.000 $153,000.000 $165,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $8,000.000 $3,300.000 $4,000.000 $6,000.000 $4,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 56.000 $50.000 $75.000 $66.000 $60.000 $60.000
ROCK FILTER DAMS (REMOVE)
LF 56.000 $16.250 $25.000 $15.000 $12.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 78.000 $38.500 $45.000 $25.000 $70.000 $23.000
CONSTRUCTION EXITS (REMOVE)
SY 78.000 $12.000 $15.000 $11.000 $15.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 428.000 $5.180 $10.000 $10.100 $6.150 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 428.000 $1.420 $2.000 $3.000 $1.850 $1.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 200.000 $20.000 $15.000 $12.000 $7.500 $6.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 200.000 $10.000 $5.000 $3.000 $1.500 $1.000
MTL W-BEAM GD FEN (TIM POST)
LF 150.000 $80.000 $35.000 $28.000 $31.000 $30.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $2,000.000 $1,750.000 $2,100.000 $1,360.000 $1,300.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,800.000 $1,800.000 $2,200.000 $1,460.000 $1,400.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $5,000.000 $4,000.000 $3,715.000 $3,300.000 $3,200.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $1,800.000 $1,000.000 $1,650.000 $1,665.000 $500.000
REMOVE SM RD SN SUP&AM
EA 4.000 $400.000 $500.000 $220.000 $130.000 $100.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $150.000 $75.000 $61.000 $63.000 $45.000
INSTL OM ASSM (OM-3L)(TWT)GND
EA 2.000 $600.000 $75.040 $165.000 $1,392.000 $50.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 4.000 $80.000 $50.000 $55.000 $183.000 $15.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $120.000 $75.000 $50.000 $56.000 $45.000
PAVEMENT SEALER 6"
LF 745.000 $2.000 $5.500 $5.500 $5.500 $5.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 700.000 $3.000 $5.500 $5.500 $5.500 $5.000
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 88.000 $2.000 $5.500 $5.500 $6.350 $5.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 350.000 $3.000 $5.500 $5.500 $5.650 $5.000
REFL PAV MRKR TY II-A-A
EA 9.000 $80.000 $33.000 $33.000 $42.000 $30.000
PAV SURF PREP FOR MRK (6")
LF 1,138.000 $2.000 $5.500 $5.500 $5.500 $5.000
Totals: $1,523,337.140 $1,415,995.002 $1,425,808.400 $1,525,733.900 $1,609,036.500