Show Job Controls
Bid Cobra

MILLS FM 574 (1028-01-030)

Items: 81

County: MILLS
Length: N/A
Highway: FM 574
District: BROWNWOOD
Control Number: 1028-01-030
DBE Goal: N/A
Project: BR 2023(214)
Guaranty: N/A
Time: 238 WORKING DAYS
Engineer's Estimate: $3,842,353.25
Date: 09/07/2022 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$3,842,353.25
$3,930,712.13
Over/Under Est: 2.3% $88,358.88
Over/Under Est: 9.17% $352,405.45
Amt Left: 6.72% $264,046.57
Over/Under Est: 15.8% $606,933.12
Amt Left: 13.19% $518,574.24
Delta: -6.07% -$254,527.67
Over/Under Est: 16.25% $624,352.75
Amt Left: 13.64% $535,993.87
Delta: -0.39% -$17,419.63
Subcontractor Percentage Amount
PRATER DIRT WORK LLC 16.73% $683,689.77
TEXAS SHAFTS, INC. 7.38% $301,591.78
TEXAS MATERIALS GROUP, INC. 6.60% $269,716.23
ROADWAY SPECIALTIES, INC. 4.08% $166,733.67
AARON CONCRETE CONTRACTORS, LLC 1.09% $44,544.04
D. I. J. CONSTRUCTION, INC. 0.71% $29,014.93
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.66% $26,971.62
S & S BRIDGE PAINTING, INC. 0.53% $21,659.03
TRAFFIC HIGHWAY MAINTENANCE, LLC 0.32% $13,077.15
GK CONSTRUCTION, LLC 0.19% $7,764.56
HOUSTON SAWING & DRILLING 0.16% $6,538.58
TORO BRAVO CONSTRUCTION, LLC 0.13% $5,312.59
TORO BRAVO CONSTRUCTION, LLC 0.00% $0.00
JR WEST TEXAS CONCRETE LLC 0.00% $0.00
Total: 38.58% $1,576,613.95

Bid Items & Bid Tabulations

81 Total 0 of 81
MILLS  |  FM 574  |  BROWNWOOD  |  1028-01-030  |  09/07/2022  |  $3,842,353.25  |  BR 2023(214)  |  BRIDGE REPL  |  238 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ACME BRIDGE COMPANY, INC.
STATELINE CONSTRUCTION, LLC
COPPELL CONSTRUCTION CO., INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
PREPARING ROW
STA 13.700 $2,500.000 $4,050.000 $5,000.000 $10,000.000 $10,500.000
EXCAVATION (ROADWAY)
CY 324.000 $22.000 $31.900 $20.000 $50.000 $30.000
EXCAVATION (CHANNEL)
CY 370.000 $22.000 $37.000 $25.000 $50.000 $30.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 6,570.000 $15.000 $35.630 $15.840 $30.000 $30.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 4,565.000 $2.500 $0.680 $0.800 $0.650 $2.000
BROADCAST SEED (TEMP) (WARM)
SY 2,283.000 $1.750 $1.100 $0.850 $0.700 $1.000
BROADCAST SEED (TEMP) (COOL)
SY 2,282.000 $1.750 $1.100 $0.850 $0.700 $1.000
VEGETATIVE WATERING
MG 104.000 $25.000 $73.560 $5.000 $50.000 $1.000
SOIL RETENTION BLANKETS (CL 2) (TY G)
SY 4,565.000 $3.000 $1.250 $5.250 $4.000 $3.000
PROOF ROLLING
HR 4.000 $100.000 $89.180 $75.000 $400.000 $100.000
CEM STABIL BKFL
CY 98.000 $320.000 $275.000 $300.000 $250.000 $250.000
FLOWABLE BACKFILL
CY 16.000 $350.000 $293.000 $350.000 $400.000 $250.000
TRENCH EXCAVATION PROTECTION
LF 330.000 $20.000 $9.000 $10.000 $55.000 $5.000
TEMPORARY SPL SHORING
SF 1,667.000 $25.000 $57.700 $25.000 $60.000 $40.000
DRILL SHAFT (36 IN)
LF 456.000 $300.000 $277.000 $300.000 $323.000 $250.000
DRILL SHAFT (48 IN)
LF 512.000 $325.000 $516.000 $550.000 $583.000 $400.000
CL C CONC (ABUT)
CY 58.200 $1,320.000 $1,370.000 $1,700.000 $1,700.000 $1,600.000
CL C CONC (CAP)
CY 51.900 $1,320.000 $1,940.000 $2,000.000 $2,000.000 $1,800.000
CL C CONC (COLUMN)
CY 63.600 $1,320.000 $1,240.000 $1,900.000 $2,000.000 $1,700.000
REINF CONC SLAB
SF 13,680.000 $30.000 $28.100 $31.000 $33.250 $35.000
APPROACH SLAB
CY 54.600 $800.000 $924.000 $900.000 $1,100.000 $900.000
PRESTR CONC GIRDER (TX28)
LF 834.000 $280.000 $251.000 $200.000 $246.840 $245.000
PRESTR CONC GIRDER (TX54)
LF 1,434.000 $300.000 $270.000 $300.000 $246.840 $340.000
RIPRAP (STONE COMMON)(DRY)(8 IN)
CY 64.000 $250.000 $196.000 $165.000 $220.000 $200.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,486.000 $135.000 $152.000 $140.000 $85.000 $200.000
RIPRAP (MOW STRIP)(4 IN)
CY 68.000 $600.000 $784.000 $700.050 $700.000 $600.000
RAIL (TY T223)
LF 808.000 $140.000 $99.690 $185.000 $175.000 $160.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 108.000 $170.000 $267.000 $250.000 $261.000 $200.000
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
LF 11.000 $1,300.000 $1,650.000 $1,500.000 $1,000.000 $2,000.000
RC PIPE (CL III)(36 IN)
LF 330.000 $120.000 $178.000 $170.000 $230.000 $200.000
HEADWALL (CH - FW - 0) (DIA= 36 IN)
EA 1.000 $10,000.000 $9,500.000 $10,000.000 $9,500.000 $10,000.000
HEADWALL (CH - FW - 30) (DIA= 36 IN)
EA 1.000 $10,500.000 $9,580.000 $12,500.000 $11,000.000 $12,000.000
WINGWALL (PW - 1) (HW=7 FT)
EA 1.000 $30,000.000 $22,700.000 $25,000.000 $22,000.000 $25,000.000
WINGWALL (PW - 1) (HW=8 FT)
EA 1.000 $35,000.000 $26,400.000 $30,000.000 $25,000.000 $30,000.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $200,000.000 $116,000.000 $150,000.000 $273,500.000 $200,000.000
MOBILIZATION
LS 1.000 $344,000.000 $365,000.000 $400,000.000 $420,000.000 $380,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $4,000.000 $2,880.000 $4,000.000 $4,180.000 $8,000.000
ROCK FILTER DAMS (REMOVE)
LF 125.000 $8.000 $10.600 $10.000 $15.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,280.000 $5.000 $3.200 $3.750 $4.000 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,280.000 $2.000 $1.050 $1.250 $1.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 110.000 $8.000 $6.400 $40.000 $7.000 $8.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 110.000 $4.000 $1.050 $15.000 $1.000 $1.000
ROCK FILTER DAMS (INSTALL) (TY 2) (6:1)
LF 125.000 $40.000 $31.800 $50.000 $65.000 $1.000
CONSTRUCTING DETOURS
SY 296.000 $100.000 $90.700 $85.000 $270.000 $100.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 12.000 $5,000.000 $3,490.000 $7,000.000 $3,631.000 $3,500.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 870.000 $90.000 $117.000 $110.000 $103.000 $120.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 720.000 $15.000 $7.300 $25.000 $12.000 $18.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 870.000 $11.000 $26.800 $40.000 $7.000 $50.000
DRIVEWAYS (ACP)
SY 257.000 $80.000 $129.000 $100.000 $75.000 $70.000
MTL W-BEAM GD FEN (STEEL POST)
LF 950.000 $30.000 $33.100 $33.250 $35.000 $30.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,750.000 $3,160.000 $3,800.000 $3,000.000 $3,200.000
REMOVE METAL BEAM GUARD FENCE
LF 300.000 $3.000 $2.100 $6.000 $2.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $300.000 $270.000 $300.000 $300.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,600.000 $3,610.000 $3,800.000 $4,100.000 $3,200.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $3,000.000 $1,350.000 $3,250.000 $1,500.000 $3,200.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $2,000.000 $795.000 $2,000.000 $900.000 $1,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $9,000.000 $9,210.000 $13,200.000 $10,000.000 $12,000.000
WIRE FENCE (TY C)
LF 1,340.000 $16.000 $15.900 $17.500 $20.000 $20.000
GATE (TY 1)
EA 1.000 $1,000.000 $2,120.000 $3,000.000 $2,000.000 $2,000.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 2.000 $1,000.000 $529.000 $250.000 $600.000 $800.000
REMOVE SM RD SN SUP&AM
EA 2.000 $300.000 $159.000 $250.000 $180.000 $500.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 8.000 $25.000 $10.600 $50.000 $22.000 $20.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 10,800.000 $1.800 $0.690 $1.500 $0.650 $1.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 272.000 $8.000 $5.600 $7.500 $6.000 $6.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 6,050.000 $2.000 $0.780 $3.000 $0.650 $1.000
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 24.000 $6.000 $15.900 $20.000 $10.000 $15.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 240.000 $5.000 $1.750 $10.000 $5.000 $5.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 2,740.000 $1.500 $2.050 $3.000 $1.500 $2.000
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 2,740.000 $1.500 $2.050 $3.000 $1.500 $2.000
REFL PAV MRKR TY II-A-A
EA 35.000 $15.000 $10.600 $7.500 $5.000 $10.000
ELIM EXT PAV MRK & MRKS (4")
LF 600.000 $3.000 $2.650 $3.000 $1.000 $5.000
ELIM EXT PV MRK & MRKS (RUMBLE STRIP)
LF 160.000 $3.000 $3.200 $15.000 $14.000 $15.000
PAV SURF PREP FOR MRK (4")
LF 1,680.000 $2.000 $0.010 $2.000 $0.650 $2.000
D-GR HMA TY-B PG64-22
TON 1,675.000 $175.000 $149.000 $167.000 $150.000 $150.000
TACK COAT
GAL 363.000 $20.000 $7.600 $6.000 $8.000 $10.000
TIP TESTING(DRILL SHAFT)
EA 3.000 $10,000.000 $3,180.000 $5,000.000 $6,000.000 $5,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 64.000 $50.000 $141.000 $150.000 $115.000 $150.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,000.000 $11,800.000 $12,000.000 $25,000.000 $25,000.000
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 160.000 $25.000 $16.900 $30.000 $19.000 $20.000
TMA (STATIONARY)
DAY 28.000 $300.000 $138.000 $225.000 $190.000 $300.000
TMA (MOBILE OPERATION)
HR 128.000 $75.000 $83.100 $75.000 $90.000 $30.000
Totals: $3,842,353.250 $3,930,712.130 $4,194,758.700 $4,449,286.370 $4,466,706.000