MILAM FM 908 (0858-02-026)

Items: 56

County: MILAM
Length: 0.0000 MILES
Highway: FM 908
District: BRYAN
Control Number: 0858-02-026
DBE Goal: 0.0%
Project: C 858-2-26
Guaranty: $19,000.00
Time: 30 WORKING DAYS
Engineer's Estimate: $934,783.20
Date: 06/04/2025 (1 year ago)
Contract Number: 6253025
Type: BICYCLE AND PEDESTRIAN IMPROVEMENTS
Project ID: A00190494
Project Description: PEDESTRIAN IMPROVEMENTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JAMES KREAMER
RENE PEQUENO
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$934,783.20
$714,788.50
Over/Under Est: -23.53% -$219,994.70
Over/Under Est: -21.89% -$204,646.93
Amt Left: 2.15% $15,347.77
Over/Under Est: -8.01% -$74,846.40
Amt Left: 20.31% $145,148.30
Delta: -17.78% -$129,800.53
Over/Under Est: -2.67% -$24,948.60
Amt Left: 27.29% $195,046.10
Delta: -5.80% -$49,897.80
Over/Under Est: 13.81% $129,056.80
Amt Left: 48.83% $349,051.50
Delta: -16.93% -$154,005.40
Over/Under Est: 25% $233,654.77
Amt Left: 63.47% $453,649.47
Delta: -9.83% -$104,597.97
$1,223,968.00
Over/Under Est: 30.94% $289,184.80
Amt Left: 71.23% $509,179.50
Delta: -4.75% -$55,530.03
Subcontractor Percentage Amount
D. I. J. CONSTRUCTION, INC. 2.31% $16,511.61
Total: 2.31% $16,511.61

Bid Items & Bid Tabulations

56 Total 0 of 56
MILAM  |  FM 908  |  BRYAN  |  0858-02-026  |  06/04/2025  |  $934,783.20  |  C 858-2-26  |  BICYCLE AND PEDESTRIAN IMPRVS  |  30 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GARRET SHIELDS INFRASTRUCTURE
TI-ZACK CONCRETE, LLC
TALBERT COMPANIES LLC
CROSS PLUS CONSTRUCTION, LLC
TEXAS STEEL INDUSTRIAL PLACING, LLC
KNIFE RIVER CORPORATION - SOUTH
PATIN CONSTRUCTION LLC
REMOV CONC (PAV)
SY 68.000 $40.000 $20.000 $67.060 $23.750 $45.000 $75.000 $72.000 $50.000
REMOV CONC (PAVERS)
SY 3.000 $495.000 $20.000 $152.000 $23.750 $45.000 $250.000 $550.000 $100.000
REMOV CONC (DRIVEWAYS)
SY 152.000 $22.000 $20.000 $60.000 $28.750 $45.000 $60.000 $64.000 $50.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 144.000 $37.000 $20.000 $63.330 $28.750 $45.000 $50.000 $181.000 $50.000
REMOV CONC (CURB OR CURB & GUTTER)
LF 625.000 $19.000 $30.000 $14.590 $11.250 $20.000 $40.000 $110.000 $25.000
REMOV CONC (RETAINING WALLS)
SY 72.000 $90.000 $20.000 $5.070 $138.900 $35.000 $250.000 $196.000 $55.000
REMOV CONC (RAIL)
LF 328.000 $62.000 $30.000 $27.800 $31.250 $51.000 $40.000 $59.000 $40.000
EMBANK (FNL)(OC)(TY C)
CY 415.000 $136.000 $50.000 $109.880 $95.040 $45.000 $75.000 $62.450 $50.000
FURN & PLACE TOPSOIL (4")
SY 86.000 $7.000 $5.000 $10.600 $5.738 $24.000 $20.000 $21.000 $5.000
BLOCK SODDING
SY 86.000 $25.000 $12.000 $11.000 $11.205 $15.000 $20.000 $15.000 $15.000
BROADCAST SEED (TEMP_WARM_COOL)
SY 86.000 $1.000 $1.000 $3.300 $1.161 $4.000 $5.000 $12.200 $5.000
VEGETATIVE WATERING
TGL 3.600 $2,500.000 $500.000 $1.100 $82.229 $166.000 $100.000 $280.000 $500.000
LANDSCAPE TREAT (TY I)
EA 1.000 $6.500 $5,000.000 $4,400.000 $2.700 $2,100.000 $500.000 $1,500.000 $2,500.000
PRIME COAT (MC-30)
GAL 17.000 $6.500 $10.000 $5.500 $21.600 $15.000 $50.000 $72.000 $10.000
D-GR HMA TY-D SAC-A PG64-22
TON 81.000 $120.000 $250.000 $275.000 $303.750 $199.000 $400.000 $600.000 $350.000
CONC PVMT (CRCP)(FAST TRK) (13")
SY 68.000 $160.000 $300.000 $595.490 $321.688 $750.000 $850.000 $340.000 $250.000
RETAINING WALL (CAST-IN-PLACE)
SF 873.000 $285.000 $120.000 $56.100 $76.250 $30.000 $225.000 $133.000 $100.000
RAIL (HANDRAIL)(TY A)
LF 429.000 $225.000 $100.000 $111.100 $96.250 $150.000 $150.000 $126.000 $115.000
ADJUSTING MANHOLES
EA 7.000 $2,600.000 $2,000.000 $1,302.860 $1,781.250 $500.000 $1,500.000 $2,400.000 $1,500.000
ADJUSTING MANHOLES (UTILITY BOX)
EA 13.000 $1,000.000 $1,000.000 $701.540 $1,437.500 $899.000 $1,250.000 $2,100.000 $1,500.000
PIPE (PVC) (SCH 40) (5 IN)
LF 8.000 $100.000 $50.000 $385.000 $270.000 $99.000 $210.000 $220.000 $750.000
PIPE (PVC) (SCH 40) (6 IN)
LF 2.000 $120.000 $100.000 $440.000 $202.500 $99.000 $220.000 $900.000 $750.000
PIPE (PVC) (SCH 40) (8 IN)
LF 4.000 $150.000 $100.000 $605.000 $297.000 $99.000 $750.000 $500.000 $750.000
MOBILIZATION
LS 1.000 $69,243.200 $70,000.000 $81,076.050 $332,100.000 $85,000.000 $106,000.000 $199,000.000 $50,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $3,750.000 $5,000.000 $2,750.000 $16,200.000 $10,000.000 $10,000.000 $16,000.000 $15,000.000
TMA (STATIONARY)
DAY 30.000 $300.000 $500.000 $1.100 $371.250 $1,200.000 $350.000 $500.000 $2,000.000
TMA (MOBILE OPERATION)
DAY 4.000 $800.000 $500.000 $1.100 $540.000 $500.000 $350.000 $900.000 $1,500.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 150.000 $8.000 $8.000 $1.100 $6.875 $15.000 $20.000 $10.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 150.000 $3.000 $1.000 $1.100 $1.875 $15.000 $10.000 $5.000 $2.000
COLORED TEXTURED CONC (4")
SY 167.000 $200.000 $100.000 $192.800 $100.000 $300.000 $300.000 $256.000 $1,000.000
LANDSCAPE PAVERS
SY 6.000 $120.000 $200.000 $170.500 $675.000 $500.000 $300.000 $670.000 $750.000
CONC CURB (TY II)
LF 273.000 $40.000 $40.000 $59.530 $31.250 $45.000 $60.000 $31.250 $60.000
CONC CURB & GUTTER (TY II)
LF 360.000 $70.000 $50.000 $59.530 $43.750 $45.000 $60.000 $156.600 $60.000
DRIVEWAYS (CONC)
SY 151.000 $160.000 $100.000 $203.070 $131.250 $125.000 $150.000 $250.000 $300.000
CONC SIDEWALKS (4")
SY 822.000 $155.000 $100.000 $168.460 $93.750 $110.000 $195.000 $160.000 $350.000
CONC SIDEWALK (STEPS)
SY 8.000 $265.000 $300.000 $424.800 $143.750 $500.000 $2,000.000 $4,960.000 $1,500.000
CURB RAMPS (TY 1)
SY 188.000 $175.000 $500.000 $253.560 $118.750 $850.000 $200.000 $284.500 $500.000
CURB RAMPS (TY 5)
SY 13.000 $215.000 $300.000 $253.560 $118.750 $1,200.000 $200.000 $264.000 $500.000
CURB RAMPS (TY 10)
SY 112.000 $170.000 $500.000 $253.560 $118.750 $999.000 $200.000 $180.000 $500.000
CONC SIDEWALKS (SPECIAL)
SY 33.000 $725.000 $150.000 $453.150 $187.500 $250.000 $1,000.000 $550.000 $500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 4.000 $825.000 $1,000.000 $715.000 $312.500 $900.000 $1,000.000 $933.000 $1,200.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 5.000 $670.000 $500.000 $715.000 $393.750 $400.000 $1,000.000 $725.000 $750.000
RELOCATE SM RD SN SUP&AM TY S80
EA 3.000 $620.000 $500.000 $715.000 $393.750 $400.000 $1,000.000 $810.000 $750.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 327.000 $12.000 $23.000 $22.000 $15.000 $12.000 $15.000 $24.390 $20.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 8.000 $250.000 $410.000 $385.000 $375.000 $300.000 $500.000 $427.000 $1,000.000
REFL PAV MRK TY I (W)(SYMBOL)(100MIL)
EA 4.000 $280.000 $600.000 $550.000 $562.500 $450.000 $500.000 $600.000 $1,000.000
RE PM TY II (W) 4" (SLD)
LF 258.000 $1.000 $1.750 $1.650 $3.750 $3.000 $10.000 $1.830 $5.000
RE PM TY II (W) 24" (SLD)
LF 484.000 $7.000 $4.750 $4.400 $7.500 $6.000 $10.000 $4.900 $10.000
RE PM TY II (W) (WORD)
EA 8.000 $155.000 $42.000 $38.500 $125.000 $100.000 $150.000 $43.000 $500.000
RE PM TY II (W) (SYMBOL)
EA 4.000 $140.000 $53.000 $49.500 $62.500 $50.000 $100.000 $55.000 $500.000
RE PM TY II (Y)(CURB)
LF 357.000 $3.000 $5.000 $4.400 $6.250 $5.000 $8.000 $5.000 $10.000
REFL PAV MRK TY I (W)4"(SLD)(100MIL)
LF 143.000 $2.000 $6.000 $5.500 $3.750 $3.000 $8.000 $6.100 $5.000
ELIM EXT PM & MRKS (4")
LF 36.000 $2.000 $2.500 $2.200 $12.500 $10.000 $15.000 $3.000 $5.000
ELIM EXT PM & MRKS (12")
LF 139.000 $2.000 $4.000 $3.300 $12.500 $10.000 $15.000 $4.000 $7.000
ELIM EXT PM & MRKS (24")
LF 22.000 $5.000 $6.000 $5.500 $18.750 $15.000 $15.000 $6.100 $10.000
ELIM EXT PM & MRKS (SYMBOL)
EA 1.000 $50.000 $200.000 $181.500 $250.000 $200.000 $300.000 $400.000 $500.000
Totals: $934,783.200 $714,788.500 $730,136.270 $859,936.802 $909,834.600 $1,063,840.000 $1,168,437.970 $1,223,968.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $5,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $10,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $5,000.00
Total: $20,000.00