MILAM FM 908 (0858-02-021)
Items: 85
County: MILAM
Length: N/A
Highway: FM 908
District: BRYAN
Control Number: 0858-02-021
DBE Goal: N/A
Project: STP 2018(029)
Guaranty: N/A
Time: 87 WORKING DAYS
Engineer's Estimate: $1,577,873.86
Date: 09/07/2017 (8 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROAD
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (12)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,577,873.86 | |||
| $1,428,673.97 |
-9.46%
-$149,199.89
|
|||
| $1,460,312.87 |
-7.45%
-$117,560.99
|
2.21%
$31,638.90
|
||
| $1,486,815.04 |
-5.77%
-$91,058.82
|
4.07%
$58,141.07
|
-1.81%
-$26,502.17
|
|
| $1,581,360.70 |
0.22%
$3,486.84
|
10.69%
$152,686.73
|
-6.36%
-$94,545.66
|
|
| $1,588,102.18 |
0.65%
$10,228.32
|
11.16%
$159,428.21
|
-0.43%
-$6,741.48
|
|
| $1,678,533.30 |
6.38%
$100,659.44
|
17.49%
$249,859.33
|
-5.69%
-$90,431.12
|
|
| $1,736,839.00 |
10.07%
$158,965.14
|
21.57%
$308,165.03
|
-3.47%
-$58,305.70
|
|
| $1,757,176.36 |
11.36%
$179,302.50
|
22.99%
$328,502.39
|
-1.17%
-$20,337.36
|
|
| $1,942,616.15 |
23.12%
$364,742.29
|
35.97%
$513,942.18
|
-10.55%
-$185,439.79
|
|
| $1,945,457.00 |
23.3%
$367,583.14
|
36.17%
$516,783.03
|
-0.15%
-$2,840.85
|
|
| $2,299,462.20 |
45.73%
$721,588.34
|
60.95%
$870,788.23
|
-18.20%
-$354,005.20
|
|
| $2,852,426.20 |
80.78%
$1,274,552.34
|
99.66%
$1,423,752.23
|
-24.05%
-$552,964.00
|
E
Engineer's Estimate
$1,577,873.86
$1,428,673.97
Over/Under Est:
-9.46%
-$149,199.89
$1,460,312.87
Over/Under Est:
-7.45%
-$117,560.99
Amt Left:
2.21%
$31,638.90
$1,486,815.04
Over/Under Est:
-5.77%
-$91,058.82
Amt Left:
4.07%
$58,141.07
Delta:
-1.81%
-$26,502.17
$1,581,360.70
Over/Under Est:
0.22%
$3,486.84
Amt Left:
10.69%
$152,686.73
Delta:
-6.36%
-$94,545.66
$1,588,102.18
Over/Under Est:
0.65%
$10,228.32
Amt Left:
11.16%
$159,428.21
Delta:
-0.43%
-$6,741.48
$1,678,533.30
Over/Under Est:
6.38%
$100,659.44
Amt Left:
17.49%
$249,859.33
Delta:
-5.69%
-$90,431.12
$1,736,839.00
Over/Under Est:
10.07%
$158,965.14
Amt Left:
21.57%
$308,165.03
Delta:
-3.47%
-$58,305.70
$1,757,176.36
Over/Under Est:
11.36%
$179,302.50
Amt Left:
22.99%
$328,502.39
Delta:
-1.17%
-$20,337.36
$1,942,616.15
Over/Under Est:
23.12%
$364,742.29
Amt Left:
35.97%
$513,942.18
Delta:
-10.55%
-$185,439.79
$1,945,457.00
Over/Under Est:
23.3%
$367,583.14
Amt Left:
36.17%
$516,783.03
Delta:
-0.15%
-$2,840.85
$2,299,462.20
Over/Under Est:
45.73%
$721,588.34
Amt Left:
60.95%
$870,788.23
Delta:
-18.20%
-$354,005.20
$2,852,426.20
Over/Under Est:
80.78%
$1,274,552.34
Amt Left:
99.66%
$1,423,752.23
Delta:
-24.05%
-$552,964.00
Bid Items & Bid Tabulations
85
Total
0 of 85