Show Job Controls
Bid Cobra

MIDLAND LAMESA RD (0906-32-052)

Items: 78

County: MIDLAND
Length: 0.0000 MILES
Highway: LAMESA RD
District: ODESSA
Control Number: 0906-32-052
DBE Goal: 2.0%
Project: BR 2025(147)
Guaranty: $42,000.00
Time: 84 WORKING DAYS
Engineer's Estimate: $2,090,078.70
Date: 10/02/2024 (1 year ago)
Contract Number: 10243226
Type: BRIDGE REPLACEMENT
Project ID: A00099634
Project Description: NBI 06-165-0-B052-00-001 BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
ODA-PRELETTINGQUESTIONS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$2,090,078.70
$1,912,116.95
Over/Under Est: -8.51% -$177,961.75
Over/Under Est: 18.54% $387,409.95
Amt Left: 29.57% $565,371.70
$2,661,755.00
Over/Under Est: 27.35% $571,676.30
Amt Left: 39.2% $749,638.05
Delta: -7.44% -$184,266.35
$3,353,703.23
Over/Under Est: 60.46% $1,263,624.53
Amt Left: 75.39% $1,441,586.28
Delta: -26.00% -$691,948.23
Subcontractor Percentage Amount
WILLIS ELECTRIC CO., LP 28.95% $572,596.97
1 PRIORITY ENVIRONMENTAL SERVICES, LLC 0.71% $14,042.97
PMI PAVEMENT MARKING, LLC 0.56% $11,076.14
Total: 30.22% $597,716.08

Bid Items & Bid Tabulations

78 Total 0 of 78
MIDLAND  |  LAMESA RD  |  ODESSA  |  0906-32-052  |  10/02/2024  |  $2,090,078.70  |  BR 2025(147)  |  BRIDGE REPL  |  84 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DAN WILLIAMS COMPANY
RAGLE CONSTRUCTION, INC.
FNH CONSTRUCTION, LLC
ALTUS CONSTRUCTION LLC
REMOV CONC (RIPRAP)
SY 121.000 $50.000 $25.000 $50.000 $200.000 $68.300
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 80.000 $100.000 $35.000 $50.000 $100.000 $136.610
REMOV CONC (CURB & GUTTER)
LF 122.000 $35.000 $15.000 $20.000 $100.000 $34.150
REMOV CONC (APPR SLAB)
SY 115.000 $57.000 $80.000 $48.000 $500.000 $157.100
RMV (7"-11") TRT/UNTRT BASE & ASPH PAV
SY 36.000 $150.000 $80.000 $100.000 $100.000 $273.210
D-GR HMA TY-D PG70-22
TON 6.000 $1,500.000 $1,135.000 $700.000 $1,000.000 $1,366.070
TACK COAT
GAL 15.000 $30.000 $95.000 $58.000 $20.000 $34.150
CEM STABIL BKFL
CY 12.000 $500.000 $550.000 $225.000 $500.000 $409.820
TRENCH EXCAVATION PROTECTION
LF 200.000 $30.000 $1.500 $41.000 $10.000 $10.250
DRILL SHAFT (24 IN)
LF 30.000 $550.000 $500.000 $400.000 $385.000 $273.210
DRILL SHAFT (30 IN)
LF 24.000 $900.000 $550.000 $480.000 $450.000 $409.820
DRILL SHAFT (36 IN)
LF 56.000 $1,250.000 $750.000 $600.000 $650.000 $409.820
CL C CONC (MISC)
CY 200.000 $2,100.000 $1,850.000 $1,130.000 $2,000.000 $1,366.070
CL S CONC (CULV)
CY 89.000 $2,100.000 $2,400.000 $3,500.000 $2,000.000 $5,464.270
BRIDGE SIDEWALK
SF 552.000 $32.000 $35.000 $26.700 $500.000 $683.030
APPROACH SLAB
CY 39.000 $1,250.000 $1,250.000 $759.000 $2,000.000 $2,049.100
RETAINING WALL (CAST-IN-PLACE)
SF 536.000 $130.000 $50.000 $114.000 $120.000 $341.520
RIPRAP (CONC)(4 IN)
CY 39.000 $900.000 $1,100.000 $820.000 $650.000 $1,366.070
RAIL (TY C223)
LF 214.000 $260.000 $300.000 $216.000 $250.000 $1,366.070
WINGWALL (SW - 0) (HW=6 FT)
EA 4.000 $30,000.000 $15,250.000 $50,000.000 $50,000.000 $20,491.020
REMOV STR (WINGWALL)
EA 4.000 $4,000.000 $2,500.000 $25,000.000 $5,000.000 $6,830.340
REMOV STR (BOX CULVERT)
LF 285.000 $150.000 $90.000 $500.000 $100.000 $273.210
REMOVE STR (RAIL)
LF 163.000 $50.000 $25.000 $25.000 $100.000 $136.610
MOBILIZATION
LS 1.000 $189,913.700 $190,000.000 $285,000.000 $260,000.000 $333,827.170
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $12,000.000 $35,000.000 $72,800.000 $8,500.000 $102,455.110
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 84.000 $200.000 $175.000 $133.000 $150.000 $409.820
TMA (STATIONARY)
DAY 84.000 $500.000 $200.000 $542.000 $250.000 $683.300
TMA (MOBILE OPERATION)
DAY 5.000 $500.000 $650.000 $1,034.000 $550.000 $1,366.070
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 50.000 $100.000 $161.000 $100.000 $30.000 $40.980
ROCK FILTER DAMS (REMOVE)
LF 50.000 $20.000 $38.000 $25.000 $15.000 $12.290
CONC CURB & GUTTER (TY II)
LF 84.000 $100.000 $75.000 $36.000 $75.000 $683.030
CURB RAMPS (TY 10)
EA 4.000 $4,000.000 $2,400.000 $2,900.000 $3,250.000 $6,830.340
CONDT (PVC) (SCH 40) (2")
LF 71.000 $20.000 $25.000 $25.000 $40.000 $17.980
CONDT (PVC) (SCH 40) (3")
LF 110.000 $30.000 $45.000 $45.000 $50.000 $23.460
CONDT (PVC) (SCH 40) (4") (BORE)
LF 753.000 $200.000 $65.000 $65.000 $80.000 $45.060
ELEC CONDR (NO.12) INSULATED
LF 1,671.000 $1.500 $1.250 $1.250 $4.000 $1.540
ELEC CONDR (NO.6) BARE
LF 759.000 $3.000 $2.500 $2.500 $4.000 $2.200
ELEC CONDR (NO.6) INSULATED
LF 20.000 $3.250 $2.750 $2.750 $4.000 $2.550
TRAY CABLE (4 CONDR) (12 AWG)
LF 532.000 $4.000 $5.000 $5.000 $4.000 $2.550
GROUND BOX TY D (162922)W/APRON
EA 11.000 $4,500.000 $2,850.000 $2,850.000 $1,500.000 $1,484.570
ELC SRV TY D 120/240 100(NS)AL(E)SP(O)
EA 1.000 $10,000.000 $11,500.000 $11,500.000 $12,500.000 $12,653.210
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 4.000 $1,100.000 $2,000.000 $900.000 $1,500.000 $776.970
REMOVE SM RD SN SUP&AM
EA 4.000 $250.000 $225.000 $200.000 $500.000 $117.820
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
LF 946.000 $5.000 $1.450 $5.000 $10.000 $2.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 44.000 $17.000 $9.000 $25.000 $20.000 $9.020
PAVEMENT SLER 4"
LF 386.000 $4.000 $0.750 $6.000 $1.000 $0.400
PAVEMENT SLER 24"
LF 44.000 $7.000 $3.250 $13.000 $20.000 $2.050
REFL PAV MRK TY I (W)4"(BRK)(100MIL)
LF 209.000 $6.000 $2.000 $10.000 $1.000 $0.320
REFL PAV MRK TY I (W)4"(SLD)(100MIL)
LF 177.000 $6.000 $2.000 $10.000 $1.000 $0.320
REFL PAV MRK TY I (Y)4"(SLD)(100MIL)
LF 90.000 $6.000 $2.000 $10.000 $1.000 $0.320
ELIM EXT PM & MRKS (4")
LF 725.000 $2.500 $2.000 $6.000 $1.000 $0.770
PAV SURF PREP FOR MRK (4")
LF 386.000 $4.000 $0.750 $6.000 $1.000 $0.150
PAV SURF PREP FOR MRK (24")
LF 44.000 $6.000 $3.500 $13.000 $20.000 $0.820
INSTALL HWY TRF SIG (ISOLATED)
EA 1.000 $60,000.000 $50,000.000 $50,000.000 $50,000.000 $28,876.970
REMOVING TRAFFIC SIGNALS
EA 2.000 $4,500.000 $10,000.000 $10,000.000 $8,500.000 $5,669.870
VEH SIG SEC (12")LED(GRN)
EA 18.000 $350.000 $400.000 $400.000 $325.000 $307.370
VEH SIG SEC (12")LED(GRN ARW)
EA 2.000 $350.000 $400.000 $400.000 $325.000 $307.370
VEH SIG SEC (12")LED(YEL)
EA 18.000 $350.000 $400.000 $400.000 $325.000 $317.610
VEH SIG SEC (12")LED(YEL ARW)
EA 1.000 $350.000 $400.000 $400.000 $325.000 $307.370
VEH SIG SEC (12")LED(RED)
EA 18.000 $350.000 $400.000 $400.000 $325.000 $312.160
VEH SIG SEC (12")LED(RED ARW)
EA 1.000 $350.000 $400.000 $400.000 $325.000 $307.370
PED SIG SEC (LED)(COUNTDOWN)
EA 12.000 $1,000.000 $885.000 $885.000 $8,500.000 $768.410
BACKPLATE W/REF BRDR(3 SEC)(VENT)ALUM
EA 18.000 $150.000 $200.000 $200.000 $150.000 $201.750
BACKPLATE W/REF BRDR(4 SEC)(VENT)ALUM
EA 1.000 $200.000 $300.000 $300.000 $200.000 $223.250
TRF SIG CBL (TY A)(12 AWG)(2 CONDR)
LF 1,851.000 $3.000 $2.500 $2.500 $4.000 $2.050
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
LF 510.000 $5.000 $3.250 $3.250 $4.000 $3.070
TRF SIG CBL (TY A)(14 AWG)(20 CONDR)
LF 920.000 $9.000 $9.000 $9.000 $4.000 $8.020
INS TRF SIG PL AM(S)1 ARM(32')
EA 1.000 $15,000.000 $20,000.000 $16,000.000 $20,000.000 $5,832.250
INS TRF SIG PL AM(S)1 ARM(32')ILSN
EA 1.000 $15,000.000 $22,000.000 $18,000.000 $22,500.000 $5,832.250
INS TRF SIG PL AM(S)1 ARM(36')
EA 1.000 $20,000.000 $22,500.000 $17,500.000 $20,000.000 $6,132.910
INS TRF SIG PL AM(S)1 ARM(36')LUM&ILSN
EA 1.000 $20,000.000 $26,000.000 $23,000.000 $26,500.000 $6,132.910
INS TRF SIG PL AM(S)1 ARM(48')ILSN
EA 1.000 $25,000.000 $27,000.000 $24,000.000 $28,000.000 $7,313.240
INS TRF SIG PL AM(S)1 ARM(48')LUM&ILSN
EA 1.000 $25,000.000 $32,000.000 $28,000.000 $32,000.000 $7,313.240
PED POLE ASSEMBLY
EA 5.000 $3,500.000 $2,500.000 $2,500.000 $6,500.000 $2,890.390
PED DETECT PUSH BUTTON (APS)
EA 12.000 $950.000 $950.000 $950.000 $1,850.000 $999.960
INSTALL RADAR VEHICLE DETECTION SYSTEM
EA 4.000 $10,000.000 $13,500.000 $13,500.000 $30,000.000 $2,031.380
ILSN (8S)
EA 4.000 $3,000.000 $6,000.000 $6,000.000 $30,000.000 $5,031.000
RADAR PRESENCE DETECTOR COMM CABLE
LF 920.000 $6.000 $2.500 $2.500 $4.000 $2.580
Totals: $2,090,078.700 $1,912,116.950 $2,477,488.650 $2,661,755.000 $3,353,703.230