Show Job Controls
Bid Cobra

MENARD RM1773 (6337-64-001)

Items: 33

County: MENARD
Length: N/A
Highway: RM1773
District: SAN ANGELO
Control Number: 6337-64-001
DBE Goal: N/A
Project: RMC - 633764001
Guaranty: N/A
Time: 100 W
Engineer's Estimate: $1,553,200.00
Date: 01/09/2019 (7 years ago)
Contract Number: N/A
Type: WIDENING OF ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (1)
E
Engineer's Estimate
$1,553,200.00
$2,258,272.55
Over/Under Est: 45.39% $705,072.55

Bid Items & Bid Tabulations

33 Total 0 of 33
MENARD  |  RM1773  |  SAN ANGELO  |  6337-64-001  |  01/09/2019  |  $1,553,200.00  |  RMC - 633764001  |  WIDENING OF ROADWAY  |  100 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALLEN KELLER COMPANY
REMOVING CONC (RIPRAP)
SY 433.000 $10.000 $200.000
SUBGRADE WIDENING (ORD COMP)
STA 589.300 $320.000 $500.000
BLADING
HR 26.000 $100.000 $100.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 70,626.000 $0.150 $0.170
BROADCAST SEED (TEMP) (WARM)
SY 35,313.000 $0.080 $0.130
BROADCAST SEED (TEMP) (COOL)
SY 35,313.000 $0.080 $0.130
PROOF ROLLING
HR 19.000 $100.000 $100.000
FL BS (CMP IN PLC)(TY A GR 5)(8")
SY 48,084.000 $10.000 $15.000
ASPH (TIER I)
GAL 88,560.000 $3.200 $3.650
ASPH (RC-250)
GAL 20,230.000 $4.250 $4.300
AGGR(TY-B GR-5 SAC-B)
CY 580.000 $80.000 $110.000
AGGR(TY-PD GR-3 SAC-B)
CY 578.000 $80.000 $125.000
AGGR(TY-PD GR-4 SAC-B)
CY 1,571.000 $90.000 $130.000
CMP AR (GAL STL DES 3)
LF 21.000 $100.000 $83.000
SET (TY II) (DES 3) (CMP) (6: 1) (P)
EA 2.000 $1,500.000 $3,240.000
REMOV STR (PIPE)
LF 21.000 $20.000 $20.000
MOBILIZATION
LS 1.000 $112,896.970 $150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $16,850.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 78.000 $25.000 $32.000
CONSTRUCTION EXITS (REMOVE)
SY 78.000 $10.000 $13.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 200.000 $5.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 200.000 $2.000 $0.800
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,555.000 $0.750 $1.880
REFL PAV MRK TY II (W) 4" (SLD)
LF 118,390.000 $0.120 $0.110
REFL PAV MRK TY II (Y) 4" (BRK)
LF 12,900.000 $0.120 $0.120
REFL PAV MRK TY II (Y) 4" (SLD)
LF 49,875.000 $0.120 $0.120
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 118,390.000 $0.300 $0.360
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 12,900.000 $0.300 $0.400
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 49,875.000 $0.300 $0.370
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 25.000 $12.000 $22.280
REFL PAV MRKR TY II-A-A
EA 1,336.000 $3.000 $5.350
TMA (STATIONARY)
DAY 90.000 $180.000 $184.630
TMA (MOBILE OPERATION)
HR 100.000 $50.000 $11.140
Totals: $1,553,200.000 $2,258,272.550