MCLENNAN FM1860 (6393-25-001)

Items: 21

County: MCLENNAN
Length: N/A
Highway: FM1860
District: WACO
Control Number: 6393-25-001
DBE Goal: N/A
Project: RMC - 639325001
Guaranty: N/A
Time: 35 CALENDAR DAYS
Engineer's Estimate: $73,887.00
Date: 01/04/2022 (4 years ago)
Contract Number: N/A
Type: CULVERT REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (4)
E
Engineer's Estimate
$73,887.00
$69,447.00
Over/Under Est: -6.01% -$4,440.00
Over/Under Est: 28.25% $20,873.70
Amt Left: 36.45% $25,313.70
Over/Under Est: 52.18% $38,553.00
Amt Left: 61.91% $42,993.00
Delta: -18.66% -$17,679.30
Over/Under Est: 82.93% $61,273.00
Amt Left: 94.62% $65,713.00
Delta: -20.21% -$22,720.00

Bid Items & Bid Tabulations

21 Total 0 of 21
MCLENNAN  |  FM1860  |  WACO  |  6393-25-001  |  01/04/2022  |  $73,887.00  |  RMC - 639325001  |  CULVERT REPAIR  |  35 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FULL FORCE DRILLING, LLC
TCB CONSTRUCTION, INC
BEAR CREEK CONTRACTING, LLC
CROSS PLUS CONSTRUCTION, LLC
PREPARING ROW
STA 1.000 $1,000.000 $500.000 $5,500.000 $200.000 $5,000.000
EXCAVATION (ROADWAY)
CY 394.000 $20.000 $12.000 $25.000 $8.000 $35.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 167.000 $20.000 $15.000 $55.000 $40.000 $35.000
BLADING
STA 1.000 $100.000 $2,209.000 $500.000 $100.000 $1,200.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 2,200.000 $0.500 $2.100 $0.350 $0.600 $1.000
VEGETATIVE WATERING
MG 66.000 $40.000 $18.500 $22.000 $10.000 $1.000
D-GR HMA(SQ) TY-B PG64-22
TON 6.000 $100.000 $500.000 $450.000 $491.000 $800.000
CEM STABIL BKFL
CY 98.000 $150.000 $34.000 $75.000 $250.000 $250.000
FLOWABLE BACKFILL
CY 43.000 $150.000 $34.000 $199.000 $175.000 $250.000
TRENCH EXCAVATION PROTECTION
LF 85.000 $20.000 $90.000 $22.000 $6.000 $45.000
RC PIPE (CL III)(18 IN)
LF 88.000 $100.000 $35.000 $125.000 $85.000 $98.000
HEADWALL (CH - PW - S) (DIA= 18 IN)
EA 2.000 $4,500.000 $9,080.000 $6,900.000 $17,000.000 $12,000.000
REMOV STR (PIPE)
LF 88.000 $30.000 $10.000 $20.000 $5.000 $20.000
MOBILIZATION
LS 1.000 $6,717.000 $800.000 $7,000.000 $10,008.000 $10,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 1.000 $3,000.000 $5,000.000 $5,500.000 $7,709.000 $2,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 40.000 $30.000 $50.000 $45.000 $30.000 $20.000
ROCK FILTER DAMS (REMOVE)
LF 40.000 $8.000 $45.000 $10.000 $3.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 100.000 $3.000 $5.000 $9.000 $5.000 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 100.000 $2.000 $5.000 $4.000 $2.000 $1.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 10.000 $60.000 $150.000 $165.000 $119.000 $250.000
TMA (STATIONARY)
DAY 10.000 $160.000 $400.000 $281.670 $200.000 $1,200.000
Totals: $73,887.000 $69,447.000 $94,760.700 $112,440.000 $135,160.000