Show Job Controls
Bid Cobra

MCLENNAN SH0006 (6365-05-001)

Items: 39

County: MCLENNAN
Length: N/A
Highway: SH0006
District: WACO
Control Number: 6365-05-001
DBE Goal: N/A
Project: RMC - 636505001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $1,026,194.00
Date: 09/04/2020 (5 years ago)
Contract Number: N/A
Type: MBGF,BRIDGE RAIL,CABLE BARRIER REPR&INST
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$1,026,194.00
$887,302.00
Over/Under Est: -13.53% -$138,892.00
$892,690.00
Over/Under Est: -13.01% -$133,504.00
Amt Left: 0.61% $5,388.00
Over/Under Est: -12.46% -$127,844.00
Amt Left: 1.25% $11,048.00
Delta: -0.63% -$5,660.00
$1,023,590.00
Over/Under Est: -0.25% -$2,604.00
Amt Left: 15.36% $136,288.00
Delta: -13.94% -$125,240.00

Bid Items & Bid Tabulations

39 Total 0 of 39
MCLENNAN  |  SH0006  |  WACO  |  6365-05-001  |  09/04/2020  |  $1,026,194.00  |  RMC - 636505001  |  MBGF,BRIDGE RAIL,CABLE BARRIER REPR&...  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
T&L CLEANING SERVICES LLC
VANN/ELLI, INC.
BK FIELD OPERATIONS LLC
SJ&J CONSTRUCTION, LLC
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 50.000 $150.000 $50.000 $150.000 $10.000 $250.000
RAIL (HANDRAIL)(DECORATIVE)
LF 30.000 $100.000 $100.000 $290.000 $200.000 $200.000
MOBILIZATION (CALLOUT)
EA 12.000 $6,220.000 $100.000 $100.000 $600.000 $2,000.000
MOBILIZATION (EMERGENCY)
EA 8.000 $2,333.000 $100.000 $500.000 $1,200.000 $3,000.000
MTL W-BEAM GD FEN (STEEL POST)
LF 300.000 $30.000 $30.000 $22.200 $28.000 $30.000
TERMINAL ANCHOR SECTION
EA 5.000 $100.000 $50.000 $300.000 $100.000 $22.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 5.000 $1,500.000 $1,500.000 $2,293.000 $1,800.000 $1,700.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 5.000 $1,200.000 $1,200.000 $1,175.000 $1,100.000 $1,300.000
REMOVE METAL BEAM GUARD FENCE
LF 600.000 $2.000 $2.000 $2.000 $2.000 $4.000
REMOVE TERMINAL ANCHOR SECTION
EA 10.000 $250.000 $100.000 $100.000 $250.000 $500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 10.000 $300.000 $100.000 $100.000 $400.000 $300.000
GDRAIL END TRT(INSTALL)(HBA POST)
EA 40.000 $3,000.000 $2,500.000 $2,750.000 $2,600.000 $2,900.000
CRASH CUSH ATTEN (DES SOURCE)
EA 5.000 $2,500.000 $2,500.000 $3,666.000 $1,000.000 $2,500.000
CRASH CUSH ATTEN (REMOVE)
EA 5.000 $800.000 $1.000 $1,800.000 $500.000 $300.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 50.000 $30.000 $30.000 $32.500 $50.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 10.000 $30.000 $30.000 $32.500 $40.000 $30.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 4,500.000 $20.000 $24.000 $9.750 $21.000 $22.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 25.000 $20.000 $20.000 $55.000 $80.000 $26.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 12.000 $20.000 $20.000 $55.000 $50.000 $35.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 200.000 $50.000 $50.000 $70.000 $60.000 $55.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 100.000 $55.000 $60.000 $75.000 $65.000 $60.000
REALIGN POSTS
EA 100.000 $10.000 $10.000 $15.000 $10.000 $15.000
REMOVE & REPLACE BLOCKOUT
EA 1,000.000 $20.000 $10.000 $20.000 $5.000 $35.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 125.000 $3,300.000 $3,350.000 $2,800.000 $2,900.000 $3,100.000
REPAIR RAIL ELEMENT(W - BEAM FURNISHED)
LF 2,000.000 $20.000 $12.000 $13.000 $15.000 $22.000
REPAIR SINGLE GUARDRAIL TERMINAL
EA 5.000 $1,500.000 $1.000 $2,000.000 $700.000 $2,000.000
REPLACE POSTS (TL-4)
EA 200.000 $150.000 $160.000 $150.000 $140.000 $165.000
CABLE SPLICE / TURNBUCKLE (TL-4)
EA 2.000 $150.000 $1.000 $300.000 $200.000 $130.000
REPR OR REPLC CABLE BARR TERM SEC(TL-4)
EA 5.000 $1,500.000 $1,500.000 $2,000.000 $2,500.000 $1,550.000
REPLACE CABLE (TL-4)
LF 7,000.000 $1.000 $0.500 $3.000 $2.000 $4.500
POST AND CABLE FENCE (NEW INSTALLATION)
LF 200.000 $10.000 $10.000 $10.500 $10.000 $26.000
POST AND CABLE FENCE (NEW CONC ANCHOR)
EA 5.000 $10.000 $10.000 $200.000 $100.000 $130.000
POST AND CABLE FENCE(REMV / REPL POSTS)
EA 20.000 $100.000 $200.000 $100.000 $100.000 $80.000
POST AND CABLE FENCE (REMV/ REPL CABLE)
LF 700.000 $4.000 $5.000 $5.000 $4.000 $20.000
REMOVE AND REPLACE (TRACC)
EA 5.000 $12,000.000 $15,000.000 $15,500.000 $20,000.000 $11,000.000
RMV/REPL(VIA-SAND FILL PLASTIC BARRELS)
EA 20.000 $400.000 $300.000 $660.000 $600.000 $300.000
REPAIR(STEEL POST W/ CHANNEL IRON RAIL)
LF 150.000 $100.000 $100.000 $125.000 $140.000 $110.000
REPAIR (W-BEAM - T101 RAIL)
LF 250.000 $10.000 $10.000 $75.000 $27.000 $33.000
TMA (STATIONARY)
DAY 100.000 $300.000 $100.000 $300.000 $100.000 $150.000
Totals: $1,026,194.000 $887,302.000 $892,690.000 $898,350.000 $1,023,590.000