MCLENNAN SL 340 (2311-01-042)

Items: 62

County: MCLENNAN
Length: N/A
Highway: SL 340
District: WACO
Control Number: 2311-01-042
DBE Goal: N/A
Project: F 2024(330)
Guaranty: N/A
Time: 75 WORKING DAYS
Engineer's Estimate: $3,840,522.55
Date: 11/02/2023 (2 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$3,840,522.55
$3,759,444.64
Over/Under Est: -2.11% -$81,077.91
Over/Under Est: 10.22% $392,316.91
Amt Left: 12.59% $473,394.82
Over/Under Est: 11.99% $460,407.15
Amt Left: 14.4% $541,485.06
Delta: -1.61% -$68,090.24
Subcontractor Percentage Amount
DIIBS SPECIALISTS, LLC 5.69% $216,982.39
WILKO INDUSTRIAL, L.L.C. 3.42% $130,418.24
PAVEMENT MARKINGS INC. 3.06% $116,690.00
J & M CONTRACTING, COMPANY 2.43% $92,665.59
CHEROKEE SERVICES 0.80% $30,507.19
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC 0.53% $20,211.01
MURRAY CONSTRUCTION 0.23% $8,770.82
Total: 16.16% $616,245.24

Bid Items & Bid Tabulations

62 Total 0 of 62
MCLENNAN  |  SL 340  |  WACO  |  2311-01-042  |  11/02/2023  |  $3,840,522.55  |  F 2024(330)  |  SURF/ROADWAY RESTOR  |  75 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
TEXAS MATERIALS GROUP, INC.
BIG CREEK CONSTRUCTION, LTD.
REMOVING CONC (RIPRAP)
SY 1,285.000 $20.000 $20.000 $45.000 $16.000
OBLITERATING ABANDONED ROAD
SY 85.000 $6.000 $22.000 $78.000 $70.000
EXCAVATION (CHANNEL)
CY 25.000 $20.000 $80.000 $170.000 $75.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 30.000 $45.000 $80.000 $180.000 $75.000
BACKFILL (TY B)
STA 76.000 $235.000 $340.000 $320.000 $275.000
BLOCK SODDING
SY 120.000 $5.500 $20.000 $15.000 $10.000
BROADCAST SEED (TEMP) (WARM)
SY 60.000 $0.600 $10.000 $3.000 $0.500
BROADCAST SEED (TEMP) (COOL)
SY 60.000 $0.450 $10.000 $3.000 $0.500
VEGETATIVE WATERING
MG 2.000 $20.000 $150.000 $330.000 $100.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 1,100.000 $65.000 $114.000 $115.000 $100.000
PLANE ASPH CONC PAV(0" TO 2")
SY 34,177.000 $2.850 $2.650 $4.300 $3.000
PLANE ASPH CONC PAV (2")
SY 22,184.000 $2.500 $2.650 $4.400 $3.000
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 2,127.000 $5.000 $5.750 $6.000 $3.000
CONC STR REPAIR (STANDARD)
SF 3.000 $160.000 $3,000.000 $2,300.000 $1,300.000
RIPRAP (CONC)(5 IN)
CY 15.000 $600.000 $1,100.000 $750.000 $650.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 52.000 $185.000 $365.000 $250.000 $225.000
RIPRAP (MOW STRIP)(4 IN)
CY 262.000 $550.000 $620.000 $600.000 $650.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 899.000 $33.000 $36.000 $28.000 $50.000
WINGWALL (FW - 0) (HW=4 FT)
EA 2.000 $6,800.000 $18,000.000 $24,500.000 $9,500.000
REMOV STR (WINGWALL)
EA 2.000 $1,225.000 $3,000.000 $1,100.000 $2,850.000
MOBILIZATION
LS 1.000 $280,000.000 $358,000.000 $313,500.000 $429,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $6,600.000 $20,000.000 $5,078.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 170.000 $40.000 $40.000 $37.000 $35.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 55.000 $55.000 $75.000 $110.000 $80.000
ROCK FILTER DAMS (REMOVE)
LF 225.000 $9.500 $15.000 $8.000 $11.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 305.000 $3.500 $12.000 $6.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 305.000 $0.750 $5.000 $3.000 $1.250
MTL W-BEAM GD FEN (STEEL POST)
LF 5,000.000 $35.000 $30.000 $27.500 $33.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $2,850.000 $2,950.000 $3,200.000 $3,000.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,475.000 $1,500.000 $1,100.000 $1,650.000
REMOVE METAL BEAM GUARD FENCE
LF 4,675.000 $2.550 $2.750 $3.000 $6.500
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $340.000 $300.000 $125.000 $670.000
GUARDRAIL END TREATMENT (INSTALL)
EA 13.000 $3,450.000 $3,100.000 $2,775.000 $3,700.000
GUARDRAIL END TREATMENT (REMOVE)
EA 9.000 $330.000 $300.000 $275.000 $525.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 6.000 $670.000 $1,400.000 $1,300.000 $730.000
REMOVE SM RD SN SUP&AM
EA 5.000 $140.000 $105.000 $100.000 $115.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 13.000 $20.000 $37.000 $35.000 $8.500
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 70.000 $46.000 $47.000 $45.000 $20.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 920.000 $1.030 $1.400 $0.990 $1.500
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,504.000 $1.050 $1.400 $0.990 $1.500
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 1,440.000 $1.750 $2.530 $0.800 $2.650
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 7,369.000 $1.200 $1.260 $0.810 $1.300
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 1,015.000 $2.750 $3.370 $2.780 $3.500
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 1,580.000 $8.000 $10.320 $6.400 $11.000
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 80.000 $0.850 $4.000 $1.500 $4.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 600.000 $8.000 $10.320 $6.500 $11.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 7,270.000 $0.750 $0.720 $0.710 $0.750
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 26,760.000 $0.770 $0.680 $0.690 $0.750
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 4,420.000 $0.700 $0.790 $0.710 $0.850
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 26,625.000 $0.840 $0.680 $0.690 $0.750
PREFAB PAV MRK TY C (W) (ARROW)
EA 51.000 $235.000 $275.000 $226.000 $285.000
PREFAB PAV MRK TY C (W) (UTURN ARROW)
EA 3.000 $380.000 $400.000 $340.000 $420.000
PREFAB PAV MRK TY C (W) (WORD)
EA 33.000 $300.000 $275.000 $339.000 $285.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 78.000 $40.000 $34.000 $39.000 $35.000
REFL PAV MRKR TY I-C
EA 820.000 $4.500 $3.790 $3.510 $4.000
REFL PAV MRKR TY II-A-A
EA 602.000 $4.500 $5.050 $3.510 $5.250
REFL PAV MRKR TY II-C-R
EA 117.000 $3.850 $5.690 $3.510 $6.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 16,824.000 $147.000 $135.000 $165.000 $155.000
UNDERSEAL COURSE
GAL 39,297.000 $3.300 $0.010 $0.010 $4.500
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 56.000 $120.000 $150.000 $35.000 $100.000
TMA (STATIONARY)
DAY 72.000 $250.000 $50.000 $185.000 $200.000
TMA (MOBILE OPERATION)
HR 152.000 $65.000 $20.000 $20.000 $90.000
Totals: $3,840,522.550 $3,759,444.640 $4,232,839.460 $4,300,929.700