Show Job Controls
Bid Cobra

MCLENNAN FM 2114 (2061-02-034)

Items: 29

County: MCLENNAN
Length: 0.0000 MILES
Highway: FM 2114
District: WACO
Control Number: 2061-02-034
DBE Goal: 0.0%
Project: STP 2025(694)FRS
Guaranty: $10,000.00
Time: 105 WORKING DAYS
Engineer's Estimate: $494,421.60
Date: 04/03/2025 (1 year ago)
Contract Number: 4253023
Type: RAILROAD CROSSING IMPROVEMENTS
Project ID: A00213071
Contract Type: Federal
Project Description: INSTALL NECESSARY RAILROAD STRIPING AT ALL ON-SYSTEM RAILROAD CROSSINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
CLAYTON ZACHA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$494,421.60
$378,726.35
Over/Under Est: -23.4% -$115,695.25
Over/Under Est: 3.95% $19,533.71
Amt Left: 35.71% $135,228.96
Over/Under Est: 29.32% $144,945.45
Amt Left: 68.82% $260,640.70
Delta: -24.40% -$125,411.74
Over/Under Est: 73.44% $363,079.50
Amt Left: 126.42% $478,774.75
Delta: -34.12% -$218,134.05
Over/Under Est: 95.59% $472,601.40
Amt Left: 155.34% $588,296.65
Delta: -12.77% -$109,521.90

Bid Items & Bid Tabulations

29 Total 0 of 29
MCLENNAN  |  FM 2114  |  WACO  |  2061-02-034  |  04/03/2025  |  $494,421.60  |  STP 2025(694)FRS  |  RAILROAD CROSSING IMPRVS  |  105 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CENTERLINE TECHNOLOGIES, LLC
D. I. J. CONSTRUCTION, INC.
THE CONFIDENCE GROUP, INC
TRP INFRASTRUCTURE SERVICES, LLC
TRAFFIC HIGHWAY MAINTENANCE, LLC
MOBILIZATION
LS 1.000 $20,000.000 $1.000 $25,000.000 $80,000.000 $10,000.000 $87,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $10,000.000 $1.000 $100.000 $1,800.000 $5,000.000 $12,000.000
TMA (STATIONARY)
DAY 105.000 $225.560 $1.000 $1.000 $200.000 $150.000 $100.000
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 398.000 $60.000 $45.000 $25.500 $40.330 $75.000 $55.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 60.000 $950.000 $800.000 $715.000 $1,000.000 $1,500.000 $1,175.000
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
EA 6.000 $740.000 $800.000 $780.000 $2,000.000 $1,500.000 $1,200.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 6.000 $1,120.000 $1,200.000 $1,110.000 $2,250.000 $1,900.000 $1,800.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 14.000 $1,000.000 $1,400.000 $1,240.000 $1,488.000 $2,200.000 $1,922.000
IN SM RD SN SUP&AM TYS80(1)SB(U-1EXT)
EA 2.000 $800.000 $1,500.000 $1,305.000 $1,566.000 $2,200.000 $1,945.000
REMOVE SM RD SN SUP&AM
EA 97.000 $158.000 $150.000 $105.000 $187.880 $250.000 $200.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 3,405.000 $2.240 $0.900 $1.250 $1.780 $2.000 $2.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 4,393.000 $9.000 $7.000 $13.500 $5.750 $10.000 $12.000
PAVEMENT SLER 8"
LF 3,405.000 $0.800 $0.250 $0.500 $1.740 $1.000 $1.000
PAVEMENT SLER 24"
LF 4,393.000 $3.000 $1.000 $4.000 $3.110 $6.000 $5.000
PAVEMENT SLER (RR XING)
EA 114.000 $120.000 $50.000 $135.000 $126.510 $275.000 $250.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 50.000 $0.600 $0.600 $1.100 $2.000 $1.600 $3.500
REFL PAV MRK TY I (W)6"(SLD)(060MIL)
LF 50,893.000 $0.360 $0.600 $1.060 $1.000 $1.600 $2.500
REFL PAV MRK TY I (Y)6"(SLD)(060MIL)
LF 47,911.000 $0.370 $0.600 $1.060 $2.250 $1.600 $2.500
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 5,222.000 $2.000 $0.600 $1.060 $0.350 $1.600 $3.000
PREFAB PM TY C (W)(RR XING)
EA 114.000 $600.000 $700.000 $985.000 $651.000 $1,000.000 $1,100.000
REFL PAV MRKR TY I-C
EA 96.000 $8.000 $6.000 $6.250 $6.000 $10.000 $15.000
REFL PAV MRKR TY II-A-A
EA 942.000 $8.000 $6.000 $7.000 $6.250 $10.000 $15.000
REFL PAV MRKR TY II-C-R
EA 194.000 $9.000 $6.000 $6.250 $5.000 $10.000 $15.000
ELIM EXT PM & MRKS (6")
LF 2,888.000 $1.250 $3.000 $3.000 $1.110 $5.000 $1.000
ELIM EXT PM & MRKS (8")
LF 3,455.000 $1.650 $3.000 $4.000 $1.400 $8.000 $2.000
ELIM EXT PM & MRKS (24")
LF 4,273.000 $5.000 $5.000 $5.000 $5.250 $17.500 $7.000
ELIM EXT PM & MRKS (RR XING)
EA 110.000 $192.000 $250.000 $175.000 $173.000 $600.000 $400.000
PAV SURF PREP FOR MRK (RPM)
EA 1,233.000 $1.100 $1.000 $1.000 $3.750 $3.000 $3.000
MAINTENANCE SPEED LIMIT SIGNING
EA 29.000 $100.000 $1.000 $1.000 $700.000 $200.000 $600.000
Totals: $494,421.600 $378,726.350 $513,955.310 $639,367.050 $857,501.100 $967,023.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (PART) $10,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
ENVIRONMENTAL: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,500.00
Total: $28,500.00