MCLENNAN FM 938 (1187-02-018)

Items: 48

County: MCLENNAN
Length: N/A
Highway: FM 938
District: WACO
Control Number: 1187-02-018
DBE Goal: N/A
Project: BR 2020(397)
Guaranty: N/A
Time: 90 WORKING DAYS
Engineer's Estimate: $671,088.40
Date: 12/04/2019 (6 years ago)
Contract Number: N/A
Type: REPL BR & APPRS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$671,088.40
$663,129.76
Over/Under Est: -1.19% -$7,958.64
Over/Under Est: 0.57% $3,818.20
Amt Left: 1.78% $11,776.84
Over/Under Est: 3.62% $24,271.76
Amt Left: 4.86% $32,230.40
Delta: -3.03% -$20,453.56
Over/Under Est: 28.09% $188,535.60
Amt Left: 29.63% $196,494.24
Delta: -23.62% -$164,263.84
Over/Under Est: 62.26% $417,835.60
Amt Left: 64.21% $425,794.24
Delta: -26.67% -$229,300.00
Over/Under Est: 83.52% $560,488.22
Amt Left: 85.72% $568,446.86
Delta: -13.10% -$142,652.62

Bid Items & Bid Tabulations

48 Total 0 of 48
MCLENNAN  |  FM 938  |  WACO  |  1187-02-018  |  12/04/2019  |  $671,088.40  |  BR 2020(397)  |  REPL BR & APPRS  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
ELLIS-MCGINNIS CONSTRUCTION CO.
JAMES CONSTRUCTION GROUP, L.L.C.
ENCINO LANDSCAPE, INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
FUQUA CONSTRUCTION CO., INC.
PREPARING ROW
STA 5.900 $2,000.000 $2,100.000 $720.000 $10,000.000 $5,000.000 $5,000.000 $2,394.000
REMOVING CONC (RIPRAP)
SY 207.000 $10.000 $14.000 $7.000 $14.640 $20.000 $40.000 $10.201
RMV TRT BASE & ASPH PAV(0-7.5")
SY 1,303.000 $1.000 $2.000 $6.000 $2.110 $20.000 $25.000 $8.446
EXCAVATION (ROADWAY)
CY 380.000 $15.000 $12.000 $12.000 $10.000 $20.000 $40.000 $50.008
EXCAVATION (CHANNEL)
CY 262.000 $15.000 $8.000 $12.000 $5.260 $20.000 $40.000 $40.006
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 880.000 $15.000 $12.000 $14.000 $8.220 $20.000 $40.000 $19.950
FURNISHING AND PLACING TOPSOIL (4")
SY 1,782.000 $2.000 $1.000 $2.100 $0.630 $4.000 $5.000 $2.660
ROLL SODDING
SY 1,782.000 $4.000 $6.000 $4.400 $3.910 $5.000 $10.000 $7.980
BROADCAST SEED (TEMP) (WARM)
SY 891.000 $0.700 $1.950 $0.800 $4.300 $0.500 $4.000 $2.660
BROADCAST SEED (TEMP) (COOL)
SY 891.000 $0.700 $0.010 $0.800 $4.300 $0.500 $4.000 $2.660
VEGETATIVE WATERING
MG 29.000 $15.000 $40.000 $30.000 $14.030 $10.000 $1.000 $15.960
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 100.000 $2.500 $7.500 $5.000 $8.880 $2.000 $6.000 $10.640
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 597.000 $50.000 $45.000 $60.000 $50.550 $50.000 $60.000 $101.030
PRIME COAT(MC-30 OR AE-P)
GAL 290.000 $5.000 $6.400 $6.000 $6.710 $5.000 $15.000 $7.980
AGGR (TY-PD GR-4 OR TY-PL GR-4)(SAC-B)
CY 21.000 $250.000 $340.000 $740.000 $827.870 $150.000 $800.000 $1,117.200
ASPH(AC-15P,AC-20XP,AC10-2TR,AC-12-5TR)
GAL 1,331.000 $7.000 $4.300 $6.000 $6.710 $5.000 $10.000 $8.884
CEM STABIL BKFL
CY 78.000 $130.000 $139.000 $200.000 $134.710 $120.000 $220.000 $170.905
DRILL SHAFT (24 IN)
LF 174.000 $175.000 $230.000 $310.000 $195.410 $545.000 $225.000 $977.550
CL C CONC (ABUT)
CY 21.600 $1,200.000 $1,020.000 $1,130.000 $849.280 $800.000 $1,800.000 $2,526.668
CL C CONC (CAP)
CY 16.000 $1,200.000 $1,420.000 $1,230.000 $1,090.640 $1,250.000 $2,000.000 $2,526.668
CL C CONC (COLUMN)
CY 6.700 $1,200.000 $1,800.000 $1,180.000 $1,602.850 $1,500.000 $2,000.000 $2,526.668
REINF CONC SLAB (SLAB BEAM)
SF 3,213.000 $18.000 $17.500 $12.000 $11.830 $20.000 $24.000 $36.243
APPROACH SLAB
CY 48.400 $500.000 $439.000 $430.000 $530.960 $500.000 $600.000 $1,067.857
PRESTR CONC SLAB BEAM (4SB12)
LF 788.000 $150.000 $146.500 $123.000 $135.530 $150.000 $200.000 $173.499
RIPRAP (CONC)(5 IN)
CY 8.000 $500.000 $565.000 $650.000 $497.480 $400.000 $850.000 $520.496
RIPRAP (STONE PROTECTION)(18 IN)
CY 782.000 $85.000 $92.000 $100.000 $73.230 $125.000 $200.000 $170.130
RIPRAP (MOW STRIP)(4 IN)
CY 34.000 $500.000 $439.000 $660.000 $632.350 $400.000 $550.000 $523.289
RAIL (TY T1W)
LF 224.000 $250.000 $192.000 $230.000 $125.290 $250.000 $200.000 $199.567
ARMOR JOINT (SEALED)
LF 28.000 $95.000 $98.000 $90.000 $121.710 $165.000 $85.000 $85.572
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $10,000.000 $15,000.000 $13,100.000 $57,129.920 $20,000.000 $50,000.000 $26,600.000
MOBILIZATION
LS 1.000 $58,000.000 $63,000.000 $60,000.000 $55,749.630 $50,000.000 $80,000.000 $121,030.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $3,000.000 $1,000.000 $1,600.000 $1,183.330 $8,000.000 $5,000.000 $2,871.962
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 100.000 $30.000 $33.000 $25.000 $29.840 $50.000 $5.000 $66.500
ROCK FILTER DAMS (REMOVE)
LF 100.000 $8.000 $8.000 $8.000 $9.840 $10.000 $1.000 $13.300
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,100.000 $3.000 $4.000 $3.000 $3.180 $5.000 $1.000 $5.320
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,100.000 $1.000 $0.900 $1.000 $0.880 $1.000 $1.000 $1.330
MTL W-BEAM GD FEN (STEEL POST)
LF 225.000 $25.000 $23.000 $22.000 $22.000 $30.000 $26.000 $33.250
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,800.000 $2,100.000 $1,550.000 $1,550.000 $2,000.000 $2,000.000 $2,427.250
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,500.000 $2,500.000 $2,430.000 $2,430.000 $3,000.000 $2,700.000 $3,391.500
WIRE FENCE (TY C)
LF 500.000 $20.000 $8.000 $11.000 $8.190 $7.000 $25.000 $13.899
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 4.000 $500.000 $525.000 $375.000 $725.000 $400.000 $800.000 $415.758
REMOVE SM RD SN SUP&AM
EA 6.000 $100.000 $35.000 $30.000 $100.000 $50.000 $100.000 $115.843
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 4.000 $25.000 $21.000 $20.000 $24.000 $100.000 $50.000 $37.240
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $35.000 $23.000 $22.000 $39.000 $100.000 $50.000 $59.850
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,180.000 $0.300 $3.000 $3.000 $2.250 $4.000 $5.000 $2.993
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 1,220.000 $0.300 $3.000 $3.000 $2.250 $4.000 $5.000 $2.993
REFL PAV MRKR TY II-A-A
EA 15.000 $3.000 $25.000 $25.000 $7.000 $4.000 $30.000 $9.310
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 28.000 $135.000 $50.000 $70.000 $150.000 $150.000 $100.000 $135.660
Totals: $671,088.400 $663,129.760 $674,906.600 $695,360.177 $859,624.000 $1,088,924.000 $1,231,576.723