MCLENNAN VARIOUS (0909-22-214)
Items: 69
County: MCLENNAN
Length: 0.0000 MILES
Highway: VARIOUS
District: WACO
Control Number: 0909-22-214
DBE Goal: 300.0%
Project: STP 2025(296)TAPS
Guaranty: $21,000.00
Time: 66 WORKING DAYS
Engineer's Estimate: $1,067,720.00
Date: 09/04/2025 (9 months ago)
Contract Number: 9253032
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Project ID: A00206363
Contract Type: Federal
Project Description: WILL CONSTRUCT 6FT WIDE SIDEWALKS ON SOUTH SIDE OF S. CARPENTER ST FROM SH 164 TO E. BOWIE ST AND DOWN E. BOWIE ST TO S. LUMPKIN ST IN MART. PROJECT WILL INCLUDE THREE CROSSWALKS, ADA RAMPS AND NEW SIGNAGE.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
CLAYTON ZACHA
MCLENNAN VARIOUS (0909-22-214)
Project Name: N/A
Project: STP 2025(296)TAPS
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: CARPENTER STREET FROM SH 164 TO BOWIE
Limits To: BOWIE ST FROM CARPENTER TO LUMPKIN
Project Description: WILL CONSTRUCT 6FT WIDE SIDEWALKS ON SOUTH SIDE OF S. CARPENTER ST FROM SH 164 TO E. BOWIE ST AND DOWN E. BOWIE ST TO S. LUMPKIN ST IN MART. PROJECT WILL INCLUDE THREE CROSSWALKS, ADA RAMPS AND NEW SIGNAGE.
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,067,720.00 | |||
| $995,057.79 |
-6.81%
-$72,662.21
|
|||
| $1,096,957.02 |
2.74%
$29,237.02
|
10.24%
$101,899.23
|
||
| $1,168,001.00 |
9.39%
$100,281.00
|
17.38%
$172,943.21
|
-6.48%
-$71,043.98
|
|
| $1,224,684.00 |
14.7%
$156,964.00
|
23.08%
$229,626.21
|
-4.85%
-$56,683.00
|
|
| $1,275,505.70 |
19.46%
$207,785.70
|
28.18%
$280,447.91
|
-4.15%
-$50,821.70
|
|
| $1,478,413.00 |
38.46%
$410,693.00
|
48.58%
$483,355.21
|
-15.91%
-$202,907.30
|
E
Engineer's Estimate
$1,067,720.00
1
Awarded
$995,057.79
Over/Under Est:
-6.81%
-$72,662.21
$1,096,957.02
Over/Under Est:
2.74%
$29,237.02
Amt Left:
10.24%
$101,899.23
$1,168,001.00
Over/Under Est:
9.39%
$100,281.00
Amt Left:
17.38%
$172,943.21
Delta:
-6.48%
-$71,043.98
$1,224,684.00
Over/Under Est:
14.7%
$156,964.00
Amt Left:
23.08%
$229,626.21
Delta:
-4.85%
-$56,683.00
$1,275,505.70
Over/Under Est:
19.46%
$207,785.70
Amt Left:
28.18%
$280,447.91
Delta:
-4.15%
-$50,821.70
$1,478,413.00
Over/Under Est:
38.46%
$410,693.00
Amt Left:
48.58%
$483,355.21
Delta:
-15.91%
-$202,907.30
| Subcontractor | Percentage | Amount |
|---|---|---|
| 4E TREE WORX LLC | 2.44% | $24,279.41 |
| ROBIN STEEL LLC | 2.32% | $23,085.34 |
| HIGHWAY TRAFFIC CONTROL & SERVICES, LLC | 1.01% | $10,050.08 |
| D. I. J. CONSTRUCTION, INC. | 0.80% | $7,960.46 |
| Total: | 6.57% | $65,375.29 |
Bid Items & Bid Tabulations
69
Total
0 of 69
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,000.00 |
| Total: | $4,000.00 |