MCLENNAN VARIOUS (0909-00-098)
Items: 16
County: MCLENNAN
Length: 0.0000 MILES
Highway: VARIOUS
District: WACO
Control Number: 0909-00-098
DBE Goal: 0.0%
Project: C 909-00-98
Guaranty: $50,000.00
Time: 60 WORKING DAYS
Engineer's Estimate: $2,495,773.13
Date: 05/02/2025 (1 year ago)
Contract Number: 5253213
Type: MAINTENANCE & OPERATIONS PROJECT
Project ID: A00210581
Project Description: DISTRICTWIDE STRIPING PROJECT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
CLAYTON ZACHA
MCLENNAN VARIOUS (0909-00-098)
Project Name: N/A
Project: C 909-00-98
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: VARIOUS
Limits To: VARIOUS
Project Description: DISTRICTWIDE STRIPING PROJECT
Bidders (11)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,495,773.13 | |||
| $2,298,505.22 |
-7.9%
-$197,267.91
|
|||
| $2,370,208.61 |
-5.03%
-$125,564.52
|
3.12%
$71,703.39
|
||
| $2,399,857.23 |
-3.84%
-$95,915.90
|
4.41%
$101,352.01
|
-1.25%
-$29,648.62
|
|
| $2,495,718.80 |
0%
-$54.33
|
8.58%
$197,213.58
|
-3.99%
-$95,861.57
|
|
| $2,512,101.05 |
0.65%
$16,327.92
|
9.29%
$213,595.83
|
-0.66%
-$16,382.25
|
|
| $2,548,006.78 |
2.09%
$52,233.65
|
10.85%
$249,501.56
|
-1.43%
-$35,905.73
|
|
| $2,736,719.62 |
9.65%
$240,946.49
|
19.07%
$438,214.40
|
-7.41%
-$188,712.84
|
|
| $2,859,148.13 |
14.56%
$363,375.00
|
24.39%
$560,642.91
|
-4.47%
-$122,428.51
|
|
| $2,898,701.60 |
16.14%
$402,928.47
|
26.11%
$600,196.38
|
-1.38%
-$39,553.47
|
|
| $3,139,667.70 |
25.8%
$643,894.57
|
36.6%
$841,162.48
|
-8.31%
-$240,966.10
|
|
| $3,199,779.14 |
28.21%
$704,006.01
|
39.21%
$901,273.92
|
-1.91%
-$60,111.44
|
E
Engineer's Estimate
$2,495,773.13
1
Awarded
$2,298,505.22
Over/Under Est:
-7.9%
-$197,267.91
$2,370,208.61
Over/Under Est:
-5.03%
-$125,564.52
Amt Left:
3.12%
$71,703.39
$2,399,857.23
Over/Under Est:
-3.84%
-$95,915.90
Amt Left:
4.41%
$101,352.01
Delta:
-1.25%
-$29,648.62
$2,495,718.80
Over/Under Est:
0%
-$54.33
Amt Left:
8.58%
$197,213.58
Delta:
-3.99%
-$95,861.57
$2,512,101.05
Over/Under Est:
0.65%
$16,327.92
Amt Left:
9.29%
$213,595.83
Delta:
-0.66%
-$16,382.25
$2,548,006.78
Over/Under Est:
2.09%
$52,233.65
Amt Left:
10.85%
$249,501.56
Delta:
-1.43%
-$35,905.73
$2,736,719.62
Over/Under Est:
9.65%
$240,946.49
Amt Left:
19.07%
$438,214.40
Delta:
-7.41%
-$188,712.84
$2,859,148.13
Over/Under Est:
14.56%
$363,375.00
Amt Left:
24.39%
$560,642.91
Delta:
-4.47%
-$122,428.51
$2,898,701.60
Over/Under Est:
16.14%
$402,928.47
Amt Left:
26.11%
$600,196.38
Delta:
-1.38%
-$39,553.47
$3,139,667.70
Over/Under Est:
25.8%
$643,894.57
Amt Left:
36.6%
$841,162.48
Delta:
-8.31%
-$240,966.10
$3,199,779.14
Over/Under Est:
28.21%
$704,006.01
Amt Left:
39.21%
$901,273.92
Delta:
-1.91%
-$60,111.44
Bid Items & Bid Tabulations
16
Total
0 of 16
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (NON-PART) | $10,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| Total: | $20,000.00 |