Show Job Controls
Bid Cobra

MCLENNAN VA (0909-00-089)

Items: 15

County: MCLENNAN
Length: N/A
Highway: VA
District: WACO
Control Number: 0909-00-089
DBE Goal: N/A
Project: F 2B23(177)
Guaranty: N/A
Time: 30 WORKING DAYS
Engineer's Estimate: $3,582,438.70
Date: 08/03/2023 (2 years ago)
Contract Number: N/A
Type: MAINTENANCE & OPERATIONS PROJECT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$3,582,438.70
$2,409,825.67
Over/Under Est: -32.73% -$1,172,613.03
$2,571,923.24
Over/Under Est: -28.21% -$1,010,515.46
Amt Left: 6.73% $162,097.57
$2,619,278.03
Over/Under Est: -26.89% -$963,160.67
Amt Left: 8.69% $209,452.36
Delta: -1.84% -$47,354.79
$2,721,620.90
Over/Under Est: -24.03% -$860,817.80
Amt Left: 12.94% $311,795.23
Delta: -3.91% -$102,342.87
$3,179,039.82
Over/Under Est: -11.26% -$403,398.88
Amt Left: 31.92% $769,214.15
Delta: -16.81% -$457,418.92
Over/Under Est: -8.64% -$309,586.30
Amt Left: 35.81% $863,026.73
Delta: -2.95% -$93,812.58
Over/Under Est: -6.53% -$233,938.90
Amt Left: 38.95% $938,674.13
Delta: -2.31% -$75,647.40
Over/Under Est: 10.64% $381,285.80
Amt Left: 64.48% $1,553,898.83
Delta: -18.37% -$615,224.70

Bid Items & Bid Tabulations

15 Total 0 of 15
MCLENNAN  |  VA  |  WACO  |  0909-00-089  |  08/03/2023  |  $3,582,438.70  |  F 2B23(177)  |  MAINT & OPERATIONS PROJECT  |  30 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
D. I. J. CONSTRUCTION, INC.
VIZCAINO, L.P.
STRIPE-A-ZONE, LLC
STRIPE LINES, INC.
PAVEMENT MARKINGS INC.
INTERSTATE BARRICADES & MARKINGS, INC.
TRP CONSTRUCTION GROUP, LLC
TRAFFIC HIGHWAY MAINTENANCE, LLC
MOBILIZATION
LS 1.000 $326,000.000 $70,000.000 $200,000.000 $75,000.000 $50,000.000 $3,500.000 $190,000.000 $50,000.000 $175,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $2,500.000 $6,500.000 $2,500.000 $3,500.000 $2,000.000 $100.000 $2,500.000 $5,000.000 $50,000.000
REFL PAV MRK TY I (W)6"(LNDP)(100MIL)
LF 690.000 $1.000 $2.000 $1.000 $1.500 $1.250 $2.800 $0.750 $1.250 $2.000
REFL PAV MRK TY I (W)8"(LNDP)(100MIL)
LF 4,488.000 $1.800 $2.000 $0.200 $1.250 $1.250 $3.200 $0.850 $1.500 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 14,226.000 $1.150 $1.250 $0.600 $0.980 $0.900 $1.200 $0.850 $1.000 $1.250
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 5,097.000 $7.500 $8.000 $5.000 $13.500 $7.000 $12.800 $6.000 $10.000 $9.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 34,340.000 $0.700 $0.460 $0.480 $0.580 $0.550 $0.650 $0.720 $0.700 $0.770
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 8,517.000 $0.750 $0.600 $0.480 $0.570 $0.550 $0.750 $0.720 $0.650 $0.700
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 54,950.000 $0.700 $0.560 $0.480 $0.580 $0.550 $0.800 $0.720 $0.700 $0.770
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 516,683.000 $0.700 $0.450 $0.480 $0.570 $0.550 $0.650 $0.720 $0.650 $0.700
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 1,588,118.000 $0.900 $0.690 $0.770 $0.700 $0.750 $0.920 $0.850 $0.900 $1.100
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
LF 110,910.000 $0.900 $0.700 $0.770 $0.720 $0.750 $1.100 $0.850 $1.000 $1.200
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 916,364.000 $0.900 $0.700 $0.770 $0.700 $0.750 $0.940 $0.850 $0.900 $1.100
PREFORMED CENTERLINE RUMBLE STRIP
LF 55,455.000 $6.750 $2.000 $0.400 $4.750 $5.500 $3.800 $6.000 $7.500 $4.500
TMA (MOBILE OPERATION)
HR 326.000 $90.000 $147.000 $1.000 $1.000 $25.000 $40.000 $100.000 $95.000 $125.000
Totals: $3,582,438.700 $2,409,825.670 $2,571,923.240 $2,619,278.030 $2,721,620.900 $3,179,039.820 $3,272,852.400 $3,348,499.800 $3,963,724.500