MCLENNAN FM 308 (0834-04-024)
Items: 79
County: MCLENNAN
Length: N/A
Highway: FM 308
District: WACO
Control Number: 0834-04-024
DBE Goal: N/A
Project: STP 2017(896)HES
Guaranty: N/A
Time: 192 WORKING DAYS
Engineer's Estimate: $1,332,902.38
Date: 02/02/2018 (8 years ago)
Contract Number: N/A
Type: SFTY TR FX OBJS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,332,902.38 | |||
| $1,258,844.00 |
-5.56%
-$74,058.38
|
|||
| $1,281,284.00 |
-3.87%
-$51,618.38
|
1.78%
$22,440.00
|
||
| $1,342,695.06 |
0.73%
$9,792.68
|
6.66%
$83,851.06
|
-4.79%
-$61,411.06
|
|
| $1,384,460.00 |
3.87%
$51,557.62
|
9.98%
$125,616.00
|
-3.11%
-$41,764.94
|
|
| $1,432,331.43 |
7.46%
$99,429.05
|
13.78%
$173,487.43
|
-3.46%
-$47,871.43
|
|
| $1,447,000.00 |
8.56%
$114,097.62
|
14.95%
$188,156.00
|
-1.02%
-$14,668.57
|
|
| $1,452,495.00 |
8.97%
$119,592.62
|
15.38%
$193,651.00
|
-0.38%
-$5,495.00
|
|
| $1,778,935.68 |
33.46%
$446,033.30
|
41.32%
$520,091.68
|
-22.47%
-$326,440.68
|
E
Engineer's Estimate
$1,332,902.38
1
Awarded
$1,258,844.00
Over/Under Est:
-5.56%
-$74,058.38
$1,281,284.00
Over/Under Est:
-3.87%
-$51,618.38
Amt Left:
1.78%
$22,440.00
$1,342,695.06
Over/Under Est:
0.73%
$9,792.68
Amt Left:
6.66%
$83,851.06
Delta:
-4.79%
-$61,411.06
$1,384,460.00
Over/Under Est:
3.87%
$51,557.62
Amt Left:
9.98%
$125,616.00
Delta:
-3.11%
-$41,764.94
$1,432,331.43
Over/Under Est:
7.46%
$99,429.05
Amt Left:
13.78%
$173,487.43
Delta:
-3.46%
-$47,871.43
$1,447,000.00
Over/Under Est:
8.56%
$114,097.62
Amt Left:
14.95%
$188,156.00
Delta:
-1.02%
-$14,668.57
$1,452,495.00
Over/Under Est:
8.97%
$119,592.62
Amt Left:
15.38%
$193,651.00
Delta:
-0.38%
-$5,495.00
$1,778,935.68
Over/Under Est:
33.46%
$446,033.30
Amt Left:
41.32%
$520,091.68
Delta:
-22.47%
-$326,440.68
Bid Items & Bid Tabulations
79
Total
0 of 79