MCLENNAN SL 396 (0258-10-050)
Items: 71
County: MCLENNAN
Length: 0.0000 MILES
Highway: SL 396
District: WACO
Control Number: 0258-10-050
DBE Goal: 6.0%
Project: F 2025(771)
Guaranty: $59,000.00
Time: 180 WORKING DAYS
Engineer's Estimate: $2,956,391.00
Date: 05/01/2025 (1 year ago)
Contract Number: 5253015
Type: CONSTRUCT SIDEWALKS & CURB RAMPS
Project ID: A00194279
Contract Type: Federal
Project Description: ADA REMEDIATION INCLUDING UPGRADING ADA CURB RAMPS, PED BUTTONS, AND INSTALLING SIDEWALK
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
CLAYTON ZACHA
MCLENNAN SL 396 (0258-10-050)
Project Name: N/A
Project: F 2025(771)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: US 84
Limits To: BAGBY AVENUE
Project Description: ADA REMEDIATION INCLUDING UPGRADING ADA CURB RAMPS, PED BUTTONS, AND INSTALLING SIDEWALK
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,956,391.00 | |||
| $2,695,683.72 |
-8.82%
-$260,707.28
|
|||
| $2,716,165.32 |
-8.13%
-$240,225.68
|
0.76%
$20,481.60
|
||
| $2,793,095.10 |
-5.52%
-$163,295.90
|
3.61%
$97,411.38
|
-2.83%
-$76,929.78
|
|
| $2,837,523.86 |
-4.02%
-$118,867.14
|
5.26%
$141,840.14
|
-1.59%
-$44,428.76
|
|
| $2,862,894.88 |
-3.16%
-$93,496.12
|
6.2%
$167,211.16
|
-0.89%
-$25,371.02
|
|
| $3,534,472.00 |
19.55%
$578,081.00
|
31.12%
$838,788.28
|
-23.46%
-$671,577.12
|
E
Engineer's Estimate
$2,956,391.00
1
Awarded
$2,695,683.72
Over/Under Est:
-8.82%
-$260,707.28
$2,716,165.32
Over/Under Est:
-8.13%
-$240,225.68
Amt Left:
0.76%
$20,481.60
$2,793,095.10
Over/Under Est:
-5.52%
-$163,295.90
Amt Left:
3.61%
$97,411.38
Delta:
-2.83%
-$76,929.78
$2,837,523.86
Over/Under Est:
-4.02%
-$118,867.14
Amt Left:
5.26%
$141,840.14
Delta:
-1.59%
-$44,428.76
$2,862,894.88
Over/Under Est:
-3.16%
-$93,496.12
Amt Left:
6.2%
$167,211.16
Delta:
-0.89%
-$25,371.02
$3,534,472.00
Over/Under Est:
19.55%
$578,081.00
Amt Left:
31.12%
$838,788.28
Delta:
-23.46%
-$671,577.12
| Subcontractor | Percentage | Amount |
|---|---|---|
| D&G ENERGY CORPORATION | 3.49% | $95,155.39 |
| JR WEST TEXAS CONCRETE LLC | 1.60% | $43,624.25 |
| LINEAR TRAFFIC MARKINGS LLC | 0.91% | $24,811.29 |
| ROBIN STEEL LLC | 0.55% | $14,995.83 |
| DIAMOND ELITE BARRICADES, LLC | 0.53% | $14,450.53 |
| Total: | 7.08% | $193,037.29 |
Bid Items & Bid Tabulations
71
Total
0 of 71
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $261,404.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $25,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $25,000.00 |
| Total: | $311,404.00 |