MCLENNAN SL 2 (0209-01-070)

Items: 26

County: MCLENNAN
Length: N/A
Highway: SL 2
District: WACO
Control Number: 0209-01-070
DBE Goal: N/A
Project: BR 2023(714)
Guaranty: N/A
Time: 135 WORKING DAYS
Engineer's Estimate: $1,790,447.00
Date: 05/04/2023 (3 years ago)
Contract Number: N/A
Type: REHABILITATE BRIDGE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,790,447.00
$1,279,088.35
Over/Under Est: -28.56% -$511,358.65
Over/Under Est: 4.64% $83,017.00
Amt Left: 46.47% $594,375.65
Over/Under Est: 31.91% $571,304.90
Amt Left: 84.64% $1,082,663.55
Delta: -26.06% -$488,287.90
$2,494,467.00
Over/Under Est: 39.32% $704,020.00
Amt Left: 95.02% $1,215,378.65
Delta: -5.62% -$132,715.10
Subcontractor Percentage Amount
1 PRIORITY ENVIRONMENTAL SERVICES, LLC 15.73% $227,576.39
BECK-REIT & SONS, LTD. 5.64% $81,597.64
BARRICADES UNLIMITED 0.76% $10,995.43
LINEAR TRAFFIC MARKINGS LLC 0.53% $7,667.86
NELSON INDUSTRIAL SERVICES, INC. 0.48% $6,944.48
KING GEORGE TRAFFIC SOLUTIONS LLC 0.28% $4,050.95
Total: 23.42% $338,832.75

Bid Items & Bid Tabulations

26 Total 0 of 26
MCLENNAN  |  SL 2  |  WACO  |  0209-01-070  |  05/04/2023  |  $1,790,447.00  |  BR 2023(714)  |  REHAB BRIDGE  |  135 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SCR CIVIL CONSTRUCTION, LLC
MB WESTERN INDUSTRIAL CONTRACTING COMPANY
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
AAD CONTRACTING INC.
PREPARING ROW
STA 9.600 $2,000.000 $1,900.000 $1,000.000 $3,500.000 $1,500.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 3,055.000 $15.000 $10.750 $14.000 $13.000 $14.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 20.000 $500.000 $150.000 $200.000 $300.000 $300.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 105.000 $200.000 $550.000 $347.000 $300.000 $250.000
CONC STR REPAIR (STANDARD)
SF 20.000 $150.000 $446.000 $324.000 $500.000 $200.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 370.000 $220.000 $218.900 $250.000 $325.000 $220.000
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 1,941.000 $40.000 $46.500 $45.000 $50.000 $55.000
MULTI-LAYER POLYMER OVERLAY
SY 3,812.000 $80.000 $48.000 $100.000 $100.000 $72.500
STR STEEL (PEDESTAL)
LB 5,040.000 $40.000 $18.000 $75.000 $50.000 $20.000
CLEAN & PAINT EXIST STR (SYSTEM I-A)
LS 1.000 $250,000.000 $217,554.700 $283,000.000 $250,000.000 $340,000.000
RETROFIT RAIL (CONC PARAPET)
LF 31.340 $1,500.000 $1,150.000 $2,000.000 $175.000 $350.000
SHOT BLASTING
SY 3,812.000 $4.000 $4.000 $8.000 $7.000 $36.000
RAISING EXIST STRUCT
LS 1.000 $400,000.000 $174,000.000 $100,000.000 $400,000.000 $850,000.000
MOBILIZATION
LS 1.000 $210,000.000 $101,000.000 $275,000.000 $200,000.000 $340,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $5,000.000 $2,250.000 $2,000.000 $4,000.000 $7,000.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,000.000 $1,500.000 $2,000.000 $26,000.000 $1,500.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 60.000 $1.000 $10.000 $10.000 $1.000 $5.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 440.000 $3.000 $3.300 $4.000 $3.300 $4.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 858.000 $3.000 $3.300 $4.000 $3.300 $4.000
REFL PAV MRKR TY II-C-R
EA 13.000 $10.000 $16.500 $142.000 $25.000 $13.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 20.000 $100.000 $200.000 $178.000 $50.000 $80.000
CONC CRCK REPR(DISCRETE)(ROUT AND SEAL)
LF 72.000 $90.000 $100.000 $205.000 $50.000 $80.000
ULTRA-HIGH PERFORMANCE CONCRETE (UPHC)
CY 0.500 $10,000.000 $250,000.000 $20,000.000 $600,000.000 $10,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 20.000 $100.000 $150.000 $300.000 $300.000 $300.000
TMA (STATIONARY)
DAY 50.000 $200.000 $10.000 $250.000 $300.000 $150.000
TMA (MOBILE OPERATION)
HR 300.000 $90.000 $5.000 $25.000 $300.000 $200.000
Totals: $1,790,447.000 $1,279,088.350 $1,873,464.000 $2,361,751.900 $2,494,467.000