MCLENNAN US 84 (0055-08-122)

Items: 15

County: MCLENNAN
Length: N/A
Highway: US 84
District: WACO
Control Number: 0055-08-122
DBE Goal: N/A
Project: STP 1902(127)HES
Guaranty: N/A
Time: 60 WORKING DAYS
Engineer's Estimate: $1,177,268.00
Date: 08/06/2019 (6 years ago)
Contract Number: N/A
Type: INSTALL CABLE MEDIAN BARRIER
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$1,177,268.00
$986,493.00
Over/Under Est: -16.2% -$190,775.00
$1,093,959.00
Over/Under Est: -7.08% -$83,309.00
Amt Left: 10.89% $107,466.00
Over/Under Est: -4.59% -$54,019.30
Amt Left: 13.86% $136,755.70
Delta: -2.68% -$29,289.70
Over/Under Est: -1.34% -$15,799.00
Amt Left: 17.74% $174,976.00
Delta: -3.40% -$38,220.30
$1,234,040.05
Over/Under Est: 4.82% $56,772.05
Amt Left: 25.09% $247,547.05
Delta: -6.25% -$72,571.05

Bid Items & Bid Tabulations

15 Total 0 of 15
MCLENNAN  |  US 84  |  WACO  |  0055-08-122  |  08/06/2019  |  $1,177,268.00  |  STP 1902(127)HES  |  INSTL CABLE MEDIAN BARRIER  |  60 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MASSANA CONSTRUCTION INC.
DBI SERVICES, LLC
SCR CIVIL CONSTRUCTION, LLC
CROSS PLUS CONSTRUCTION, LLC
VANN/ELLI, INC.
PREPARING ROW
STA 32.000 $1,000.000 $900.000 $250.000 $150.000 $1,200.000 $3,000.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 40.000 $40.000 $95.000 $70.000 $97.000 $56.000 $55.000
ROLL SODDING
SY 17,887.000 $4.000 $5.000 $4.000 $4.350 $5.000 $5.850
VEGETATIVE WATERING
MG 824.000 $30.000 $12.500 $45.000 $29.000 $40.000 $65.000
RIPRAP (MOW STRIP)(4 IN)
CY 998.000 $425.000 $340.000 $400.000 $430.000 $400.000 $470.000
MOBILIZATION
LS 1.000 $103,275.000 $89,598.000 $95,000.000 $90,000.000 $123,456.000 $75,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $5,000.000 $9,500.000 $4,400.000 $7,700.000 $5,677.000 $5,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 500.000 $2.500 $7.000 $4.000 $1.600 $2.000 $6.640
TEMP SEDMT CONT FENCE (REMOVE)
LF 500.000 $0.500 $2.000 $1.000 $0.600 $2.000 $3.620
CABLE BARRIER SYSTEM (TL-4)
LF 26,045.000 $15.000 $12.000 $11.800 $11.650 $14.000 $9.580
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 16.000 $3,000.000 $2,500.000 $2,360.000 $3,400.000 $2,100.000 $3,000.000
FULL - WIDTH MOWING
CYC 1.000 $5,000.000 $6,000.000 $9,700.000 $28,000.000 $7,000.000 $9,500.000
POST AND CABLE FENCE (REMOVAL)
LF 520.000 $5.000 $5.000 $2.000 $10.000 $21.000 $2.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 120.000 $75.000 $30.000 $270.000 $110.000 $45.000 $220.000
TMA (STATIONARY)
DAY 240.000 $180.000 $75.000 $300.000 $240.000 $123.000 $300.000
Totals: $1,177,268.000 $986,493.000 $1,093,959.000 $1,123,248.700 $1,161,469.000 $1,234,040.050