MCLENNAN SL 484 (0049-01-101)

Items: 21

County: MCLENNAN
Length: N/A
Highway: SL 484
District: WACO
Control Number: 0049-01-101
DBE Goal: N/A
Project: F 2024(113)
Guaranty: N/A
Time: 60 WORKING DAYS
Engineer's Estimate: $950,704.52
Date: 10/05/2023 (2 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$950,704.52
$850,998.10
Over/Under Est: -10.49% -$99,706.42
$911,627.00
Over/Under Est: -4.11% -$39,077.52
Amt Left: 7.12% $60,628.90
$956,047.80
Over/Under Est: 0.56% $5,343.28
Amt Left: 12.34% $105,049.70
Delta: -4.87% -$44,420.80
Over/Under Est: 4.64% $44,151.38
Amt Left: 16.9% $143,857.80
Delta: -4.06% -$38,808.10
Over/Under Est: 29.32% $278,775.21
Amt Left: 44.48% $378,481.63
Delta: -23.58% -$234,623.83
Subcontractor Percentage Amount
TJT CONSTRUCTION, INC. 4.00% $34,039.92
A-1 DOT SOLUTIONS LLC 3.52% $29,955.13
LIQUID LAWNS HYDROMULCH CORPORATION 0.20% $1,702.00
Total: 7.72% $65,697.05

Bid Items & Bid Tabulations

21 Total 0 of 21
MCLENNAN  |  SL 484  |  WACO  |  0049-01-101  |  10/05/2023  |  $950,704.52  |  F 2024(113)  |  HWY IMPRV  |  60 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SCOUT 5 CONSTRUCTION LLC
3LW CIVIL LLC
HJC FARMS, INC.
MB WESTERN INDUSTRIAL CONTRACTING COMPANY
ROADWAY SPECIALTIES, INC.
REMOVING CONCRETE(MOW STRIP)
LF 5,490.000 $13.000 $8.750 $6.000 $10.000 $10.000 $2.330
ROLL SODDING
SY 22,676.000 $6.000 $6.000 $0.100 $6.000 $6.670 $7.490
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 22,676.000 $0.370 $0.350 $0.400 $0.550 $0.610 $0.680
VEGETATIVE WATERING
MG 368.000 $16.000 $85.000 $0.010 $50.000 $136.750 $95.670
RIPRAP (MOW STRIP)(4 IN)
CY 598.000 $556.000 $350.000 $500.000 $600.000 $550.000 $600.000
MOBILIZATION
LS 1.000 $50,000.000 $112,000.000 $80,000.000 $100,000.000 $100,000.000 $335,790.010
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $5,000.000 $500.000 $30,324.500 $2,925.000 $1,000.000 $3,612.090
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,656.000 $3.800 $12.000 $0.100 $6.250 $6.990 $2.560
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,656.000 $1.100 $1.000 $0.010 $2.750 $3.040 $1.000
MTL W-BEAM GD FEN (STEEL POST)
LF 4,700.000 $34.500 $21.000 $38.000 $28.750 $31.770 $28.180
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 16.000 $2,725.000 $2,100.000 $3,500.000 $2,466.000 $2,753.000 $3,026.720
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 10.000 $1,400.000 $1,500.000 $3,000.000 $1,373.000 $1,853.000 $1,347.240
REMOVE METAL BEAM GUARD FENCE
LF 4,600.000 $4.500 $6.000 $6.000 $1.500 $2.430 $3.040
REMOVE TERMINAL ANCHOR SECTION
EA 6.000 $385.000 $2,500.000 $600.000 $200.000 $212.630 $399.920
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 12.000 $275.000 $600.000 $500.000 $200.000 $243.000 $202.910
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $3,540.000 $3,500.000 $4,000.000 $3,209.000 $3,353.400 $3,192.760
GUARDRAIL END TREATMENT (REMOVE)
EA 10.000 $290.000 $1,500.000 $250.000 $200.000 $243.000 $304.370
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 45.000 $43.000 $80.000 $58.350 $25.000 $30.380 $42.080
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 27.000 $49.000 $80.000 $71.830 $25.000 $30.380 $42.080
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 60.000 $83.000 $300.000 $100.000 $35.250 $38.880 $42.750
TMA (STATIONARY)
DAY 120.000 $215.000 $100.000 $100.000 $100.000 $60.750 $229.620
Totals: $950,704.520 $850,998.100 $911,627.000 $956,047.800 $994,855.900 $1,229,479.730