MCCULLOCH US 87 (0071-01-060)

Items: 23

County: MCCULLOCH
Length: 31.3280 MILES
Highway: US 87
District: BROWNWOOD
Control Number: 0071-01-060
DBE Goal: 0.0%
Project: C 71-1-60
Guaranty: $65,000.00
Time: 53 WORKING DAYS
Engineer's Estimate: $3,270,391.50
Date: 11/07/2024 (1 year ago)
Contract Number: 11243218
Type: PREVENTIVE MAINTENANCE
Project ID: A00178028
Project Description: MILL AND SEAL COAT
Mail/Deliver Bids To: N/A
BLAKE STEMBRIDGE
CASEY MCGEE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$3,270,391.50
$3,936,577.18
Over/Under Est: 20.37% $666,185.68
$4,516,277.48
Over/Under Est: 38.1% $1,245,885.98
Amt Left: 14.73% $579,700.30
Over/Under Est: 40.53% $1,325,590.53
Amt Left: 16.75% $659,404.85
Delta: -1.76% -$79,704.55
Subcontractor Percentage Amount
TEXOP CONSTRUCTION 21.47% $845,183.12
FLAT LINE, INC. 3.11% $122,427.55
TEXAS TRAFFIC AND BARRICADE, LLC 1.14% $44,876.98
BARRICADES PLUS, LLC 1.10% $43,302.35
RED SIXTEEN CONSTRUCTION, INC 0.00% $0.00
Total: 26.82% $1,055,790.00

Bid Items & Bid Tabulations

23 Total 0 of 23
MCCULLOCH  |  US 87  |  BROWNWOOD  |  0071-01-060  |  11/07/2024  |  $3,270,391.50  |  C 71-1-60  |  PREVENT MAINT  |  53 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RONALD R. WAGNER & CO., LP
ALLEN KELLER COMPANY
CLARK CONSTRUCTION OF TEXAS, INC.
ASPH (AC-20-5TR)
TON 1,524.000 $800.000 $870.000 $1,150.590 $906.050
ASPH (RC-250)
TON 36.000 $500.000 $1,290.000 $1,455.340 $850.000
AGGR (TY-PB, GR-3)(SAC-B)
CY 9,266.000 $115.000 $93.540 $147.680 $114.080
AGGR (TY-B, GR-4)
CY 238.000 $130.000 $150.000 $283.340 $70.000
PLANE ASPH CONC PAV(0" TO 1")
SY 650,116.000 $0.700 $1.340 $1.090 $1.000
MOBILIZATION
LS 1.000 $243,000.000 $633,994.600 $195,000.000 $1,271,800.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
EA 3.000 $3,000.000 $0.010 $47,884.400 $12,500.000
TMA (MOBILE OPERATION)
DAY 40.000 $200.000 $0.010 $937.930 $0.010
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,288.000 $0.100 $1.500 $1.650 $0.010
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 21,547.000 $0.100 $1.500 $1.650 $0.010
RE PM TY II (W) 6" (BRK)
LF 17,175.000 $0.250 $0.170 $0.220 $0.200
RE PM TY II (W) 6" (SLD)
LF 303,534.000 $0.400 $0.170 $0.220 $0.200
RE PM TY II (W) 8" (DOT)
LF 148.000 $2.000 $1.000 $0.520 $0.400
RE PM TY II (W) 8" (SLD)
LF 536.000 $0.600 $1.000 $0.360 $0.400
RE PM TY II (W) 24" (SLD)
LF 782.000 $4.500 $3.000 $3.940 $7.000
RE PM TY II (W) (ARROW)
EA 6.000 $100.000 $65.000 $77.890 $200.000
RE PM TY II (W) (LN REDUCT ARW)
EA 20.000 $150.000 $100.000 $207.690 $300.000
RE PM TY II (W) (WORD)
EA 2.000 $120.000 $75.000 $83.080 $250.000
RE PM TY II (Y) 6" (BRK)
LF 28,997.000 $0.300 $0.170 $0.220 $0.200
RE PM TY II (Y) 6" (SLD)
LF 193,715.000 $0.250 $0.170 $0.220 $0.200
RE PM TY II (Y) 24" (SLD)
LF 230.000 $4.500 $5.000 $3.940 $7.000
REFL PAV MRKR TY I-C
EA 215.000 $6.000 $5.000 $4.310 $6.000
REFL PAV MRKR TY II-A-A
EA 5,232.000 $5.000 $4.250 $4.310 $5.000
Totals: $3,270,391.500 $3,936,577.180 $4,516,277.480 $4,595,982.030