MATAGORDA AVE H (0913-21-055)

Items: 71

County: MATAGORDA
Length: 0.1500 MILES
Highway: AVE H
District: YOAKUM
Control Number: 0913-21-055
DBE Goal: 5.0%
Project: BR 2024(086)
Guaranty: $76,000.00
Time: 267 WORKING DAYS
Engineer's Estimate: $3,775,698.75
Date: 02/06/2025 (1 year ago)
Contract Number: 2253033
Type: BRIDGE REPLACEMENT
Project ID: A00194183
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
RYAN SIMPER
PAUL RODRIGUEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (9)
E
Engineer's Estimate
$3,775,698.75
$3,170,843.64
Over/Under Est: -16.02% -$604,855.11
Over/Under Est: -7.38% -$278,765.05
Amt Left: 10.28% $326,090.06
$3,508,812.90
Over/Under Est: -7.07% -$266,885.85
Amt Left: 10.66% $337,969.26
Delta: -0.34% -$11,879.20
$3,652,466.15
Over/Under Est: -3.26% -$123,232.60
Amt Left: 15.19% $481,622.51
Delta: -4.09% -$143,653.25
Over/Under Est: -1.16% -$43,647.55
Amt Left: 17.7% $561,207.56
Delta: -2.18% -$79,585.05
$3,762,209.49
Over/Under Est: -0.36% -$13,489.26
Amt Left: 18.65% $591,365.85
Delta: -0.81% -$30,158.29
Over/Under Est: 12.06% $455,173.35
Amt Left: 33.43% $1,060,028.46
Delta: -12.46% -$468,662.61
$4,422,581.61
Over/Under Est: 17.13% $646,882.86
Amt Left: 39.48% $1,251,737.97
Delta: -4.53% -$191,709.51
$5,878,554.00
Over/Under Est: 55.69% $2,102,855.25
Amt Left: 85.39% $2,707,710.36
Delta: -32.92% -$1,455,972.39
Subcontractor Percentage Amount
M & D FOUNDATION DRILLING INDUSTRIES, INC. 11.77% $373,208.30
VIZION CRANE & INDUSTRIAL SUPPORT, LLC 1.73% $54,855.59
MATAGORDA CONSTRUCTION & MATERIALS 0.77% $24,415.50
MESA ROD BUSTERS INC 0.23% $7,292.94
Total: 14.50% $459,772.33

Bid Items & Bid Tabulations

71 Total 0 of 71
MATAGORDA  |  AVE H  |  YOAKUM  |  0913-21-055  |  02/06/2025  |  $3,775,698.75  |  BR 2024(086)  |  BRIDGE REPL  |  267 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SCOUT 5 CONSTRUCTION LLC
JOHN REED AND COMPANY, LLC
TREVWAY, INC.
STX CIVIL
E-Z BEL CONSTRUCTION, LLC
C. E. BARKER, LTD.
R CONSTRUCTION CIVIL, LLC
TALBERT COMPANIES LLC
CK NEWBERRY, LLC
PREPARING ROW
STA 10.400 $5,000.000 $0.010 $15,000.000 $1,828.190 $8,500.000 $5,200.000 $39,500.000 $4,000.000 $22,000.000 $2,500.000
REMOV CONC (PAV)
SY 1,384.000 $40.000 $24.810 $10.000 $20.000 $55.000 $10.000 $14.610 $15.000 $13.900 $20.000
REMOV CONC (DRIVEWAYS)
SY 67.000 $25.000 $28.190 $12.000 $66.300 $40.000 $50.000 $18.010 $20.000 $19.290 $25.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 39.000 $35.000 $36.830 $10.000 $10.000 $25.000 $15.000 $26.840 $20.000 $19.930 $20.000
EXCAV (ROADWAY)
CY 536.000 $22.000 $34.540 $30.000 $23.680 $17.000 $35.000 $19.190 $24.000 $23.560 $30.000
EXCAV (CHANNEL)
CY 1,420.000 $30.000 $51.760 $40.000 $19.000 $17.000 $38.000 $37.370 $21.000 $20.770 $25.000
EMBANK (FNL)(OC)(TY C)
CY 769.000 $60.000 $63.980 $20.000 $33.000 $30.000 $28.000 $19.190 $35.000 $35.640 $45.000
BLADING
HR 48.000 $120.000 $0.010 $30.000 $75.000 $165.000 $60.000 $66.040 $125.000 $106.100 $225.000
BLOCK SODDING
SY 1,254.000 $7.500 $10.460 $5.000 $6.000 $8.000 $7.000 $6.570 $6.000 $6.050 $10.000
BROADCAST SEED (PERM_RURAL_CLAY)
SY 2,227.000 $1.000 $0.010 $0.500 $1.260 $3.250 $1.000 $0.610 $0.300 $0.280 $1.000
BROADCAST SEED (TEMP_WARM)
SY 872.000 $1.000 $0.010 $0.500 $1.260 $2.250 $0.250 $0.250 $0.300 $0.280 $1.000
BROADCAST SEED (TEMP_COOL)
SY 872.000 $1.000 $0.010 $0.500 $1.260 $1.500 $0.250 $0.250 $0.300 $0.280 $1.000
VEGETATIVE WATERING
TGL 44.100 $90.000 $0.010 $40.000 $200.000 $150.000 $90.000 $47.980 $250.000 $35.200 $85.000
FL BS (CMP IN PLC)(TY E GR 5) (6")
SY 104.000 $27.500 $100.000 $80.000 $116.000 $240.000 $35.000 $160.080 $31.000 $159.500 $175.000
FL BS (CMP IN PLC)(TY E GR 5)(FNAL POS)
CY 279.000 $150.000 $105.000 $230.000 $292.000 $105.000 $130.000 $176.350 $150.000 $115.500 $195.000
LIME (COM OR QK)(SLURRY) OR QK(DRY)
TON 26.000 $430.000 $393.330 $330.000 $350.000 $500.000 $500.000 $353.500 $600.000 $330.000 $450.000
LIME TRT (EXIST MATL)(8")
SY 1,551.000 $8.250 $10.980 $10.000 $27.000 $10.000 $8.000 $7.150 $17.000 $3.300 $20.000
ASPH (RC-250)
GAL 234.000 $15.000 $13.990 $30.000 $21.470 $23.000 $17.000 $8.080 $10.000 $27.500 $10.000
AGGR (TY-E, GR-5)(SAC-B)
CY 8.400 $1,000.000 $650.000 $600.000 $1,515.790 $1,500.000 $1,186.000 $1,010.000 $1,200.000 $550.000 $2,000.000
AGGR (TY-PE, GR-4)(SAC-B)
CY 9.100 $1,000.000 $500.000 $600.000 $1,538.530 $1,300.000 $1,218.000 $1,010.000 $1,200.000 $440.000 $2,000.000
ASPH (AC 20-5TR OR AC-20XP OR CRS-2P)
GAL 398.000 $15.000 $50.000 $25.000 $17.680 $17.000 $14.000 $10.860 $9.000 $16.500 $10.000
D-GR HMA TY-B PG64-22
TON 344.000 $170.000 $250.000 $240.000 $328.000 $130.000 $150.000 $232.300 $270.000 $192.500 $275.000
CONC PVMT (CPCD) (7")
SY 1,403.000 $180.000 $100.000 $115.000 $75.000 $150.000 $90.000 $93.230 $115.000 $275.000 $200.000
CEM STABIL BKFL
CY 121.000 $270.000 $241.140 $130.000 $229.610 $235.000 $255.000 $118.680 $60.000 $184.890 $300.000
DRILL SHAFT (24 IN)
LF 2,132.000 $265.000 $240.000 $280.000 $266.000 $250.000 $210.000 $281.630 $445.000 $292.600 $600.000
CL C CONC (ABUT)
CY 88.100 $1,700.000 $1,350.000 $1,600.000 $700.000 $1,300.000 $1,750.000 $1,828.060 $2,700.000 $1,485.000 $3,000.000
CL C CONC (CAP)
CY 37.200 $1,800.000 $250.000 $1,600.000 $1,127.000 $1,710.000 $1,850.000 $1,865.380 $3,000.000 $1,595.000 $3,500.000
CL C CONC (COLUMN)
CY 17.800 $2,000.000 $250.000 $1,600.000 $1,594.000 $2,500.000 $1,850.000 $1,879.910 $3,800.000 $1,732.500 $3,000.000
REINF CONC SLAB (SLAB BEAM)
SF 10,273.000 $30.000 $28.020 $25.000 $22.000 $26.000 $25.000 $26.360 $34.000 $23.100 $35.000
BRIDGE SIDEWALK
SF 2,997.000 $25.000 $47.900 $20.000 $16.000 $45.000 $12.000 $12.530 $15.000 $52.690 $75.000
PRESTR CONC SLAB BEAM (5SB15)
LF 1,969.060 $250.000 $240.000 $270.000 $263.000 $250.000 $350.000 $220.640 $230.000 $215.030 $325.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,895.000 $210.000 $300.000 $100.000 $225.000 $240.000 $250.000 $154.670 $255.000 $255.040 $350.000
STR STEEL (MISC NON-BRIDGE)
LB 896.000 $27.500 $50.000 $25.000 $26.000 $22.000 $30.000 $21.840 $35.000 $27.500 $35.000
RAIL (TY T223)
LF 264.000 $165.000 $50.000 $130.000 $120.000 $170.000 $193.000 $145.440 $225.000 $172.700 $150.000
RAIL (TY C223)
LF 358.000 $260.000 $50.000 $160.000 $179.000 $195.000 $342.000 $221.580 $300.000 $214.500 $175.000
ARMOR JOINT (SEALED)
LF 146.000 $150.000 $250.000 $90.000 $180.000 $215.000 $208.000 $119.520 $100.000 $282.700 $225.000
RC PIPE (CL III)(18 IN)
LF 103.000 $165.000 $107.920 $110.000 $80.730 $110.000 $140.000 $158.570 $150.000 $110.000 $175.000
RC PIPE (CL III)(42 IN)
LF 156.000 $365.000 $190.000 $250.000 $299.000 $250.000 $220.000 $315.790 $400.000 $330.000 $400.000
MANH (COMPL)(PRM)(48IN)
EA 1.000 $8,500.000 $12,000.000 $6,000.000 $11,300.000 $7,600.000 $15,500.000 $4,292.500 $2,500.000 $11,550.000 $10,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (C)
EA 2.000 $2,500.000 $10,000.000 $3,000.000 $5,032.000 $3,200.000 $3,700.000 $3,633.980 $1,600.000 $2,090.000 $5,000.000
SET (TY II) (42 IN) (RCP) (3: 1) (C)
EA 2.000 $6,500.000 $10,000.000 $6,000.000 $11,917.000 $7,500.000 $12,000.000 $8,145.650 $5,400.000 $3,960.000 $10,000.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 3.000 $35,000.000 $1,000.000 $50,000.000 $70,000.000 $27,000.000 $70,333.000 $50,165.080 $30,000.000 $44,000.000 $50,000.000
REMOV STR (SMALL)
EA 4.000 $1,500.000 $1,000.000 $2,000.000 $2,000.000 $1,000.000 $400.000 $8,585.000 $1,000.000 $2,200.000 $5,000.000
MOBILIZATION
LS 1.000 $340,000.000 $100,000.000 $330,000.000 $350,000.000 $286,137.900 $300,000.000 $360,000.000 $350,000.000 $585,000.000 $575,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 19.000 $3,500.000 $0.010 $2,000.000 $1,100.000 $2,000.000 $1,400.000 $858.500 $4,500.000 $11,000.000 $15,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
CY 18.000 $320.000 $26.000 $50.000 $200.000 $25.000 $200.000 $202.000 $45.000 $44.000 $50.000
ROCK FILTER DAMS (REMOVE)
CY 18.000 $70.000 $0.010 $15.000 $100.000 $20.000 $30.000 $30.300 $22.000 $22.000 $20.000
SANDBAGS FOR EROSION CONTROL
EA 90.000 $25.000 $19.000 $10.000 $10.000 $18.000 $18.000 $18.180 $2.000 $2.200 $2.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,146.000 $4.500 $5.540 $4.000 $3.000 $4.250 $3.000 $2.930 $4.000 $3.850 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,146.000 $1.500 $1.870 $1.000 $1.000 $1.000 $1.000 $1.210 $1.000 $1.100 $1.000
CONC CURB (MONO) (TY II)
LF 110.000 $60.000 $19.000 $75.000 $22.000 $35.000 $12.000 $24.240 $16.000 $17.050 $20.000
CONC CURB (SLOTTED)
LF 705.000 $30.000 $35.000 $75.000 $35.000 $70.000 $70.000 $40.000 $32.000 $34.210 $40.000
DRIVEWAYS (CONC)
SY 110.000 $120.000 $115.000 $160.000 $121.000 $130.000 $118.000 $204.190 $100.000 $105.510 $120.000
CONC SIDEWALKS (5")
SY 748.000 $105.000 $80.000 $105.000 $70.000 $105.000 $100.000 $75.930 $70.000 $73.350 $80.000
CURB RAMPS (TY 1)
SY 24.000 $220.000 $150.000 $800.000 $120.000 $90.000 $275.000 $146.720 $140.000 $150.450 $175.000
MTL W-BEAM GD FEN (TIM POST)
LF 50.000 $30.000 $31.000 $40.000 $121.000 $45.000 $35.000 $39.880 $35.000 $38.500 $105.000
MTL BEAM GD FEN TRANS (TL2)
EA 3.000 $2,500.000 $2,100.000 $1,433.000 $2,670.000 $1,700.000 $1,675.000 $1,447.330 $1,700.000 $1,842.500 $2,500.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,750.000 $1,500.000 $1,552.000 $2,821.000 $1,800.000 $1,350.000 $1,567.520 $1,400.000 $1,485.000 $5,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,500.000 $3,500.000 $3,497.000 $4,520.000 $3,800.000 $3,330.000 $3,531.970 $3,400.000 $3,663.000 $5,000.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL2)
EA 1.000 $30,000.000 $30,000.000 $28,925.000 $33,000.000 $35,000.000 $30,600.000 $29,214.250 $31,000.000 $33,660.000 $30,000.000
WIRE FENCE (TY A)
LF 58.000 $45.000 $26.920 $35.000 $50.000 $25.000 $42.000 $101.000 $42.000 $46.200 $40.000
GATE (TY 2)
EA 1.000 $1,500.000 $500.000 $4,000.000 $1,200.000 $1,900.000 $800.000 $202.000 $800.000 $880.000 $1,500.000
IN SM RD SN SUP&AM TYTWT(1)UA(T)
EA 1.000 $775.000 $1,400.000 $713.000 $928.420 $850.000 $735.000 $720.130 $740.000 $808.500 $1,500.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 9.000 $600.000 $1,100.000 $597.000 $682.000 $700.000 $540.000 $602.970 $550.000 $594.000 $1,200.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
EA 24.000 $60.000 $150.000 $95.000 $99.000 $100.000 $67.000 $95.950 $70.000 $73.700 $120.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 18.000 $30.000 $100.000 $16.000 $6.000 $20.000 $23.000 $16.160 $23.000 $24.750 $60.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 9.000 $30.000 $150.000 $25.000 $13.000 $30.000 $29.000 $25.250 $29.000 $31.350 $90.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 2.000 $75.000 $200.000 $305.000 $50.000 $360.000 $58.000 $308.050 $60.000 $63.800 $175.000
INSTL OM ASSM (OM-3L)(TWT)GND
EA 4.000 $375.000 $750.000 $305.000 $195.000 $360.000 $270.000 $308.050 $270.000 $297.000 $750.000
INSTL OM ASSM (OM-3R)(TWT)GND
EA 4.000 $375.000 $750.000 $305.000 $195.000 $360.000 $238.000 $308.050 $240.000 $261.800 $800.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 8.000 $25.000 $50.000 $25.000 $200.000 $30.000 $18.000 $25.250 $19.000 $19.800 $65.000
Totals: $3,775,698.750 $3,170,843.645 $3,496,933.700 $3,508,812.895 $3,652,466.150 $3,732,051.200 $3,762,209.476 $4,230,872.100 $4,422,581.612 $5,878,554.000