Show Job Controls
Bid Cobra

MARTIN FM 1208 (1823-01-011)

Items: 65

County: MARTIN
Length: 0.0000 MILES
Highway: FM 1208
District: ODESSA
Control Number: 1823-01-011
DBE Goal: 0.0%
Project: C 1823-1-11
Guaranty: $100,000.00
Time: 251 WORKING DAYS
Engineer's Estimate: $9,927,435.20
Date: 04/08/2026 (2 months ago)
Contract Number: 4263210
Type: HIGHWAY IMPROVEMENT
Project ID: A00187842
Project Description: ROADWAY REHABILITATION
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ODA-PRELETTINGQUESTIONS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$9,927,435.20
Over/Under Est: -5.58% -$553,642.86
$10,238,363.76
Over/Under Est: 3.13% $310,928.56
Amt Left: 9.22% $864,571.42
$11,381,090.50
Over/Under Est: 14.64% $1,453,655.30
Amt Left: 21.41% $2,007,298.16
Delta: -11.16% -$1,142,726.74
Over/Under Est: 26.71% $2,651,350.05
Amt Left: 34.19% $3,204,992.91
Delta: -10.52% -$1,197,694.75
$13,757,544.67
Over/Under Est: 38.58% $3,830,109.47
Amt Left: 46.77% $4,383,752.33
Delta: -9.37% -$1,178,759.42

Bid Items & Bid Tabulations

65 Total 0 of 65
MARTIN  |  FM 1208  |  ODESSA  |  1823-01-011  |  04/08/2026  |  $9,927,435.20  |  C 1823-1-11  |  HWY IMPRV  |  251 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
RK HALL, LLC
REECE ALBERT, INC.
RAGLE CONSTRUCTION, INC.
GILVIN-TERRILL, LTD.
REMOV CONC (DRIVEWAYS)
SY 799.000 $25.000 $35.000 $46.120 $46.100 $14.000 $55.000
RMV (4") TRT/UNTRT BASE & ASPH PAV
SY 66,758.000 $8.000 $3.850 $4.030 $6.960 $3.000 $3.000
SUBGR WIDEN (OC)
STA 246.000 $500.000 $1,073.000 $1,149.910 $839.450 $1,620.000 $3,000.000
BACKFILL (TY B)
STA 266.000 $215.000 $188.000 $119.120 $272.090 $264.000 $500.000
BLADING
HR 175.000 $200.000 $375.000 $175.040 $193.730 $10.000 $500.000
PROOF ROLLING
HR 200.000 $150.000 $150.000 $151.180 $179.870 $10.000 $500.000
FL BS (CMP IN PLC)(TY A GR 4) (6")
SY 60,114.000 $15.000 $9.230 $14.600 $14.160 $10.250 $8.500
PRIME COAT (AE-P)
GAL 25,720.000 $4.500 $4.650 $6.290 $4.230 $6.000 $0.720
ASPH (AC-20-5TR)
GAL 48,495.000 $5.000 $3.500 $4.290 $4.790 $5.000 $5.050
AGGR (TY-PB, GR-4)(SAC-A)
CY 1,164.000 $180.000 $72.000 $186.590 $254.060 $150.000 $250.000
D-GR HMA TY-C SAC-B PG64-22
TON 216.000 $110.000 $204.000 $179.000 $187.870 $190.000 $378.000
TACK COAT
GAL 10,211.000 $4.750 $3.590 $8.040 $3.960 $6.100 $8.000
SP MIXES SP-B SAC-B PG70-22
TON 35,092.000 $100.000 $112.000 $108.800 $130.280 $140.000 $140.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 2,516.000 $100.000 $101.000 $57.880 $69.290 $85.000 $90.000
PLANE & TEXT ASPH CONC PAV (0” TO 5.5”)
SY 2,070.000 $6.000 $13.210 $5.960 $8.450 $6.000 $15.000
CEM STABIL BKFL
CY 166.000 $190.000 $236.500 $270.090 $217.760 $152.000 $250.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 120.000 $450.000 $412.500 $397.500 $445.190 $375.000 $315.000
RIPRAP (CONC)(4 IN)
CY 9.000 $560.000 $1,045.000 $2,640.560 $818.130 $1,005.500 $950.000
RC PIPE (CL III)(18 IN)
LF 463.000 $150.000 $143.400 $125.470 $110.910 $91.000 $65.000
RC PIPE (CL III)(24 IN)
LF 19.000 $160.000 $240.320 $190.730 $229.980 $142.000 $155.000
RC PIPE (CL III)(30 IN)
LF 112.000 $150.000 $205.050 $165.710 $253.550 $166.000 $200.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 20.000 $2,600.000 $2,079.760 $1,456.170 $1,973.410 $1,421.000 $1,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $2,310.000 $2,334.030 $1,729.990 $2,601.290 $2,023.100 $2,500.000
SET (TY II) (30 IN) (RCP) (6: 1) (C)
EA 4.000 $4,600.000 $4,517.390 $3,910.880 $4,720.850 $5,175.000 $3,500.000
CLEAN EXIST CULVERTS
EA 1.000 $2,700.000 $5,500.000 $4,372.800 $2,389.520 $1,783.000 $2,480.000
REMOV STR (PIPE)
LF 538.000 $27.000 $38.110 $30.780 $36.060 $25.000 $90.210
MOBILIZATION
LS 1.000 $556,884.130 $310,000.000 $596,974.290 $450,619.390 $1,200,000.000 $1,300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $23,000.000 $15,000.000 $25,000.000 $8,001.510 $62,250.000 $10,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $19,250.000 $14,000.000 $10,610.460 $9,000.000 $18,500.000
TMA (STATIONARY)
DAY 183.000 $200.000 $137.500 $236.700 $298.310 $286.500 $400.000
TMA (MOBILE OPERATION)
DAY 56.000 $300.000 $935.000 $396.780 $643.260 $625.000 $400.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 720.000 $10.000 $14.500 $7.390 $7.160 $10.000 $13.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 720.000 $2.000 $5.500 $1.790 $1.760 $3.000 $2.000
CONC CURB (TY I)
LF 280.000 $45.000 $55.000 $76.610 $43.090 $24.000 $85.000
DRIVEWAYS (CONC)
SY 1,057.000 $115.000 $150.000 $181.710 $158.450 $116.000 $235.000
DRIVEWAYS (ACP)
SY 7,439.000 $75.000 $52.500 $44.430 $69.890 $50.000 $100.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 52,552.000 $0.250 $0.200 $0.250 $0.150 $0.080 $0.150
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 26,276.000 $0.250 $0.250 $0.280 $0.150 $0.100 $0.150
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 2.000 $200.000 $468.600 $233.200 $505.740 $426.000 $220.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 2.000 $320.000 $511.500 $254.400 $552.040 $465.000 $240.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 12.000 $620.000 $1,094.500 $699.600 $1,181.250 $995.000 $660.000
IN RD IL (TY SA) 50T-10 (400W EQ) LED
EA 12.000 $9,400.000 $8,250.000 $7,950.000 $8,903.880 $7,500.000 $5,770.000
CONDT (PVC) (SCH 40) (2")
LF 3,071.000 $10.000 $11.000 $10.600 $11.870 $10.000 $26.080
ELEC CONDR (NO.6) BARE
LF 3,296.000 $2.500 $2.750 $2.650 $2.970 $2.500 $1.710
ELEC CONDR (NO.6) INSULATED
LF 6,592.000 $2.750 $2.750 $2.650 $2.970 $2.500 $2.430
GROUND BOX TY A (122311)W/APRON
EA 2.000 $2,100.000 $1,925.000 $1,855.000 $2,077.570 $1,750.000 $1,280.000
ELC SRV TY A 240/480 060(NS)SS(E)SP(O)
EA 2.000 $13,500.000 $11,000.000 $10,600.000 $11,871.840 $10,000.000 $5,850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 31.000 $795.000 $754.600 $980.500 $814.410 $686.000 $925.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 7.000 $1,400.000 $1,123.100 $1,272.000 $1,212.120 $1,021.000 $1,200.000
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 1.000 $1,048.000 $1,425.600 $1,272.000 $1,538.580 $1,296.000 $1,200.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 5.000 $700.000 $726.000 $503.500 $783.540 $660.000 $475.000
REMOVE SM RD SN SUP&AM
EA 23.000 $130.000 $175.000 $106.000 $178.540 $140.000 $100.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 26.000 $90.000 $89.100 $90.100 $96.160 $81.000 $85.000
INSTL OM SM RD SIGN (1-OM-PW)R
EA 5.000 $6.000 $14.300 $21.200 $15.430 $13.000 $20.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 24,045.000 $0.500 $1.500 $3.000 $2.960 $1.000 $2.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 53,152.000 $0.400 $0.610 $0.710 $0.800 $0.670 $0.670
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 5,966.000 $0.420 $0.640 $0.740 $0.830 $0.700 $0.700
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 8,022.000 $0.450 $0.640 $0.740 $0.830 $0.700 $0.700
PREFAB PM TY C (W)(24")(SLD)
LF 116.000 $8.000 $13.200 $16.960 $18.990 $16.000 $16.000
REFL PAV MRKR TY II-A-A
EA 398.000 $5.000 $4.400 $8.480 $9.500 $8.000 $8.000
ELIM EXT PM & MRKS (4")
LF 59,400.000 $0.800 $0.720 $0.880 $1.060 $0.600 $1.210
DITCH CLEANING AND RESHAPING (FOOT)
LF 250.000 $15.000 $44.000 $21.740 $55.580 $11.000 $50.000
BONDING COURSE
GAL 10,211.000 $4.900 $2.610 $5.540 $3.820 $5.750 $5.500
1
STONE-MTRX-ASPH SMAR-F SAC-A
TON 0.000 $140.000 $0.000 $0.000 $0.000 $0.000 $0.000
1A
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 10,528.000 $140.000 $144.000 $155.680 $191.540 $210.000 $257.000
Totals: $9,927,435.200 $9,373,792.340 $10,238,363.760 $11,381,090.500 $12,578,785.250 $13,757,544.670
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
PUBLIC UTILITY FORCE ACCT WORK (NON- PART) $15,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $2,500.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $100,000.00
Total: $117,500.00