Show Job Controls
Bid Cobra

MARION FM 248 (0138-11-032)

Items: 25

County: MARION
Length: N/A
Highway: FM 248
District: ATLANTA
Control Number: 0138-11-032
DBE Goal: N/A
Project: STP 2021(148)
Guaranty: N/A
Time: 200 WORKING DAYS
Engineer's Estimate: $1,288,999.00
Date: 12/02/2020 (5 years ago)
Contract Number: N/A
Type: INSTALLING SAFETY LIGHTING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$1,288,999.00
Over/Under Est: -11.64% -$150,078.06
Over/Under Est: -7.49% -$96,552.03
Amt Left: 4.7% $53,526.03
Over/Under Est: -1.16% -$15,010.57
Amt Left: 11.86% $135,067.49
Delta: -6.84% -$81,541.46
Over/Under Est: 3.14% $40,512.00
Amt Left: 16.73% $190,590.06
Delta: -4.36% -$55,522.57

Bid Items & Bid Tabulations

25 Total 0 of 25
MARION  |  FM 248  |  ATLANTA  |  0138-11-032  |  12/02/2020  |  $1,288,999.00  |  STP 2021(148)  |  INSTLING SAFETY LIGHTING  |  200 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SOUTH TEXAS ILLUMINATION, LLC
AMERICAN LIGHTING AND SIGNALIZATION, LLC
STRIPING TECHNOLOGY, L.P.
PREPARING ROW
AC 0.500 $12,000.000 $10,650.000 $7,868.700 $8,800.000 $30,000.000
DRILL SHAFT (HIGH MAST POLE) (60 IN)
LF 150.000 $670.000 $569.380 $427.480 $627.530 $925.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 380.000 $200.000 $186.420 $200.670 $155.110 $145.000
RIPRAP (CONC)(CL B)
CY 41.000 $650.000 $705.000 $404.440 $925.240 $410.000
MOBILIZATION
LS 1.000 $80,075.000 $114,266.930 $116,630.500 $129,533.200 $50,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $5,000.000 $3,380.820 $5,444.900 $6,177.730 $3,000.000
REMOVE RD IL ASM (TRANS-BASE)
EA 21.000 $790.000 $426.000 $451.590 $776.600 $400.000
REPLACE LUMINAIRE W/LED (250W EQ)
EA 3.000 $750.000 $833.800 $773.010 $619.290 $800.000
IN RD IL (TY AL) 50T-10 (400W EQ) LED
EA 38.000 $3,500.000 $3,187.400 $3,450.530 $3,225.880 $4,900.000
HI MST IL POLE (150 FT)( 80 MPH)
EA 6.000 $34,000.000 $25,795.200 $30,632.340 $29,087.220 $46,200.000
CONDT (PVC) (SCH 40) (2")
LF 12,975.000 $8.500 $8.710 $6.660 $11.700 $7.000
CONDT (PVC) (SCH 40) (2") (BORE)
LF 2,661.000 $22.000 $20.210 $23.760 $21.230 $21.000
ELEC CONDR (NO.6) BARE
LF 15,636.000 $1.400 $1.100 $1.220 $1.280 $1.500
ELEC CONDR (NO.6) INSULATED
LF 34,654.000 $1.650 $1.210 $1.320 $1.450 $1.500
GROUND BOX TY A (122311)
EA 6.000 $700.000 $733.750 $693.080 $942.000 $400.000
GROUND BOX TY A (122311)W/APRON
EA 48.000 $820.000 $903.500 $704.880 $1,125.430 $700.000
GROUND BOX TY D (162922)W/APRON
EA 3.000 $985.000 $1,044.500 $716.680 $1,211.850 $800.000
REMOVE GROUND BOX
EA 3.000 $280.000 $319.500 $244.100 $338.360 $100.000
REMOVE ELECTRICAL SERVICES
EA 4.000 $500.000 $639.000 $732.300 $884.080 $200.000
ELC SRV TY A 120/240 060(NS)AL(E)SP(O)
EA 6.000 $5,500.000 $5,201.000 $6,178.700 $5,950.290 $5,500.000
ELC SRV TY A 240/480 060(NS)AL(E)SP(O)
EA 3.000 $6,200.000 $5,402.250 $6,391.100 $5,950.290 $7,050.000
ELC SRV TY A 240/480 060(SS)SS(E)SP(O)
EA 2.000 $6,500.000 $5,701.250 $6,550.400 $6,157.070 $7,050.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 16.000 $130.000 $169.400 $94.400 $118.660 $110.000
LED HI MST IL ASM (6 FIXT)(ASYM)(TY A)
EA 6.000 $32,000.000 $23,361.800 $23,517.360 $21,510.260 $33,000.000
TMA (STATIONARY)
DAY 100.000 $230.000 $208.500 $472.000 $102.160 $110.000
Totals: $1,288,999.000 $1,138,920.940 $1,192,446.970 $1,273,988.430 $1,329,511.000