MARION US 59 (0062-05-062)

Items: 60

County: MARION
Length: N/A
Highway: US 59
District: ATLANTA
Control Number: 0062-05-062
DBE Goal: N/A
Project: NH 2021(317)
Guaranty: N/A
Time: 150 WORKING DAYS
Engineer's Estimate: $4,561,815.63
Date: 01/07/2021 (5 years ago)
Contract Number: N/A
Type: RESURFACE EXISTING 4 LANE DIVIDED HIGHWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (3)
E
Engineer's Estimate
$4,561,815.63
$2,827,413.51
Over/Under Est: -38.02% -$1,734,402.12
Over/Under Est: -32.35% -$1,475,967.13
Amt Left: 9.14% $258,434.99
Over/Under Est: -28.34% -$1,292,676.76
Amt Left: 15.62% $441,725.36
Delta: -5.94% -$183,290.37

Bid Items & Bid Tabulations

60 Total 0 of 60
MARION  |  US 59  |  ATLANTA  |  0062-05-062  |  01/07/2021  |  $4,561,815.63  |  NH 2021(317)  |  RESURF EXIST 4 LANE DIVIDED HWY  |  150 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MADDEN CONTRACTING COMPANY, LLC.
SILVER CREEK CONSTRUCTION, INC.
EAST TEXAS BRIDGE, INC.
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 12.000 $25.000 $50.000 $100.000 $75.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 2,316.000 $0.250 $0.250 $0.750 $0.250
BROADCAST SEED (TEMP) (WARM)
SY 1,158.000 $0.250 $0.450 $0.750 $0.250
BROADCAST SEED (TEMP) (COOL)
SY 1,158.000 $0.250 $0.450 $0.750 $0.250
VEGETATIVE WATERING
MG 37.000 $10.000 $10.000 $50.000 $1.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 5,768.000 $120.000 $130.000 $145.000 $142.000
TACK COAT
GAL 6,294.000 $2.880 $2.500 $2.500 $2.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 250.000 $100.000 $80.000 $120.000 $55.000
PLANE ASPH CONC PAV(0" TO 3")
SY 31,652.000 $5.000 $2.650 $2.500 $2.250
PLANE CONC PAV(0" TO 1")
SY 25,474.000 $3.000 $2.250 $2.500 $2.250
PLANE ASPH CONC PAV (2")
SY 52,445.000 $2.000 $1.250 $2.500 $2.250
FULL - DEPTH REPAIR CPCD (13")
SY 4,168.000 $350.000 $160.000 $200.000 $275.000
CL A CONC (CURB OUTLET)(TY II)
EA 1.000 $2,550.000 $2,400.000 $3,000.000 $2,000.000
RIPRAP (MOW STRIP)(4 IN)
CY 40.000 $450.000 $495.000 $550.000 $500.000
CLEANING AND SEALING EXISTING JOINTS
LF 32,930.000 $30.000 $10.170 $6.000 $8.000
MOBILIZATION
LS 1.000 $428,000.000 $250,000.000 $200,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $6,500.000 $2,000.000 $10,000.000 $5,000.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 11,332.000 $0.500 $0.270 $0.250 $0.750
MTL W-BEAM GD FEN (TIM POST)
LF 600.000 $22.000 $18.500 $20.000 $20.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,600.000 $1,325.000 $1,200.000 $1,600.000
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 4.000 $600.000 $630.000 $1,000.000 $700.000
REMOVE METAL BEAM GUARD FENCE
LF 450.000 $4.500 $2.500 $2.000 $3.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,700.000 $2,425.000 $2,000.000 $2,600.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $500.000 $200.000 $500.000 $250.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 18.000 $25.000 $15.000 $15.000 $25.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 24.000 $34.000 $20.000 $20.000 $25.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 18.000 $30.000 $15.000 $15.000 $25.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 11,332.000 $0.500 $0.800 $0.800 $0.880
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 11,332.000 $0.500 $0.800 $0.800 $0.880
WK ZN PAV MRK SHT TERM RMV (W)(4")
LF 3,325.000 $1.100 $1.400 $1.000 $1.500
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 6,650.000 $1.300 $1.400 $1.000 $1.500
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 75.000 $1.650 $1.000 $1.000 $1.200
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 820.000 $1.650 $1.000 $1.000 $1.200
REFL PAV MRK TY II (W) 24" (SLD)
LF 180.000 $3.300 $5.500 $5.500 $6.000
PAVEMENT SEALER 6"
LF 4,080.000 $0.270 $0.150 $0.150 $0.170
PAVEMENT SEALER 8"
LF 420.000 $0.270 $0.500 $0.500 $0.550
PAVEMENT SEALER 10"
LF 480.000 $0.500 $0.500 $0.500 $0.550
PAVEMENT SEALER (ARROW)
EA 2.000 $49.180 $55.000 $55.000 $60.000
PAVEMENT SEALER (WORD)
EA 2.000 $54.000 $75.000 $75.000 $85.000
PREFAB PAV MRK TY B (W)(6")(BRK)CNTST
LF 480.000 $10.000 $12.500 $12.500 $14.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 430.000 $13.230 $14.500 $14.500 $16.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 8.000 $207.130 $185.000 $185.000 $200.000
PREFAB PAV MRK TY C (W) (WORD)
EA 12.000 $214.910 $265.000 $265.000 $300.000
REFL PAV MRKR TY I-C
EA 313.000 $3.400 $4.000 $4.000 $5.000
REFL PAV MRKR TY II-A-A
EA 680.000 $2.930 $3.500 $3.500 $5.000
ELIM EXT PAV MRK & MRKS (6")
LF 4,110.000 $0.500 $0.700 $0.700 $0.770
ELIM EXT PAV MRK & MRKS (8")
LF 390.000 $0.900 $1.000 $1.000 $1.100
ELIM EXT PAV MRK & MRKS (10")
LF 480.000 $0.500 $1.000 $1.000 $1.100
ELIM EXT PAV MRK & MRKS (ARROW)
EA 3.000 $70.000 $55.000 $55.000 $60.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 2.000 $77.060 $55.000 $55.000 $60.000
SP MIXES SP-D SAC-A PG76-22
TON 3,131.000 $110.000 $110.000 $125.000 $120.000
TACK COAT
GAL 3,790.000 $2.880 $2.500 $2.500 $2.000
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 300.000 $2.820 $10.000 $10.000 $11.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 11,332.000 $3.500 $3.400 $3.400 $3.700
REFL PAV MRK AWT (W) 6" (SLD) (100MIL)
LF 13,102.000 $0.500 $0.620 $0.620 $0.700
REFL PAV MRK AWT (W) 6" (BRK) (100MIL)
LF 2,510.000 $0.550 $0.700 $0.700 $0.770
REFL PAV MRK AWT (Y) 6" (SLD) (100MIL)
LF 27,498.000 $0.490 $0.620 $0.620 $0.700
REFL PAV MRK AWT (Y) 6" (BRK) (100MIL)
LF 4,570.000 $0.500 $0.700 $0.700 $0.770
TMA (STATIONARY)
DAY 150.000 $170.000 $150.000 $150.000 $200.000
TMA (MOBILE OPERATION)
DAY 2.000 $200.000 $0.010 $350.000 $200.000
Totals: $4,561,815.630 $2,827,413.510 $3,085,848.500 $3,269,138.870