MADISON IH0045 (6477-39-001)

Items: 30

County: MADISON
Length: 0.0100 MILES
Highway: IH0045
District: BRYAN
Control Number: 6477-39-001
DBE Goal: N/A
Project: RMC - A00213018
Guaranty: $81,000.00
Time: 26 WORKING DAYS
Engineer's Estimate: $4,066,898.90
Date: 06/04/2025 (1 year ago)
Contract Number: 6254005
Type: MILL AND INLAY
Project ID: A00213018
Project Description: MILL AND INLAY ON THE NORTHBOUND MAIN LANES OF IH 45 IN MADISON COUNTY FROM SH 21 TO SH OSR.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DELMY REYES
MATT HENSARLING
RYAN GOERLITZ
MICHAEL ESTILLETTE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$4,066,898.90
$3,461,709.75
Over/Under Est: -14.88% -$605,189.15
Over/Under Est: -13.12% -$533,393.85
Amt Left: 2.07% $71,795.30
Over/Under Est: 4.26% $173,198.60
Amt Left: 22.49% $778,387.75
Delta: -20.00% -$706,592.45
Over/Under Est: 6.42% $261,084.62
Amt Left: 25.02% $866,273.77
Delta: -2.07% -$87,886.02
Over/Under Est: 19.63% $798,341.26
Amt Left: 40.54% $1,403,530.41
Delta: -12.41% -$537,256.64

Bid Items & Bid Tabulations

30 Total 0 of 30
MADISON  |  IH0045  |  BRYAN  |  6477-39-001  |  06/04/2025  |  $4,066,898.90  |  RMC - A00213018  |  MILL AND INLAY  |  26 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
KNIFE RIVER CORPORATION - SOUTH
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
TEXAS MATERIALS GROUP, INC.
BACKFILL (TY B)
STA 29.000 $200.000 $500.000 $175.000 $450.000 $292.540 $645.000
PFC-C PG76-22 SAC-A
TON 10,222.000 $180.000 $170.000 $161.750 $184.500 $173.830 $211.000
TACK COAT
GAL 17,587.000 $6.000 $3.000 $4.000 $3.500 $4.180 $4.000
TOM-C PG76-22 SAC-B
TON 7,254.000 $160.000 $140.000 $151.000 $191.000 $184.170 $226.000
TACK COAT
GAL 17,587.000 $6.000 $3.000 $4.000 $3.500 $4.350 $4.000
PLANE ASPH CONC PAV(2")
SY 175,849.000 $2.500 $1.250 $1.170 $1.600 $2.100 $2.200
PAV JT UNDERSEAL (24")
LF 224.000 $45.000 $65.000 $38.000 $38.000 $38.000 $41.000
CLEANING AND SEALING EXIST JOINTS (CL3)
LF 224.000 $50.000 $50.000 $55.000 $23.000 $22.680 $25.000
MOBILIZATION
LS 1.000 $50,000.000 $55,000.000 $104,000.000 $280,000.000 $398,210.370 $241,446.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $5,000.000 $5,000.000 $8,369.000 $3,000.000 $16,685.380 $3,700.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 52.000 $150.000 $150.000 $180.000 $150.000 $56.000 $99.000
TMA (STATIONARY)
DAY 20.000 $400.000 $300.000 $500.000 $125.000 $257.680 $395.000
TMA (MOBILE OPERATION)
DAY 24.000 $400.000 $500.000 $800.000 $125.000 $76.000 $395.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 104,842.000 $0.200 $0.200 $0.070 $0.150 $0.070 $0.070
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 27,680.000 $0.500 $0.500 $0.390 $0.500 $0.350 $0.550
WK ZN PAV MRK NON-REMOV (W)6"(DOT)
LF 848.000 $0.500 $1.000 $0.390 $1.000 $0.920 $1.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 109,358.000 $0.500 $0.350 $0.390 $0.350 $0.350 $0.380
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 4,400.000 $1.000 $1.000 $0.690 $1.000 $0.600 $1.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 109,366.000 $0.500 $0.350 $0.390 $0.350 $0.350 $0.380
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 9,904.000 $2.000 $1.500 $1.500 $1.000 $0.880 $1.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 424.000 $2.000 $2.000 $1.260 $2.000 $2.500 $2.150
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,200.000 $2.500 $1.500 $1.580 $1.300 $1.100 $1.400
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 300.000 $3.000 $5.000 $4.200 $5.000 $3.750 $2.850
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 13,840.000 $0.750 $0.800 $0.740 $0.800 $0.660 $0.850
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 58,608.000 $0.750 $0.700 $0.760 $0.650 $0.660 $0.700
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 58,608.000 $0.750 $0.700 $0.760 $0.650 $0.660 $0.700
PREFAB PM TY C (W)(NUMBER)
EA 6.000 $300.000 $150.000 $300.000 $150.000 $250.000 $161.000
REFL PAV MRKR TY II-C-R
EA 832.000 $5.000 $6.000 $7.000 $5.500 $7.000 $6.000
ELIM EXT PM & MRKS (4")
LF 7,850.000 $1.000 $0.750 $1.000 $0.500 $1.000 $0.550
TMSP RADAR SPEED CONTROL MONITOR
EA 1.000 $10,000.000 $5,000.000 $3,000.000 $12,000.000 $3,600.000 $3,100.000
Totals: $4,066,898.900 $3,461,709.750 $3,533,505.050 $4,240,097.500 $4,327,983.520 $4,865,240.160