Items: 38

County: MADISON
Length: N/A
Highway: CS
District: BRYAN
Control Number: 0917-31-031
DBE Goal: N/A
Project: BR 2022(281)
Guaranty: N/A
Time: 61 WORKING DAYS
Engineer's Estimate: $777,206.00
Date: 06/01/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
DELMY REYES
MATT HENSARLING
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$777,206.00
$649,993.90
Over/Under Est: -16.37% -$127,212.10
Over/Under Est: 4.18% $32,509.35
Amt Left: 24.57% $159,721.45
Over/Under Est: 7.31% $56,784.00
Amt Left: 28.31% $183,996.10
Delta: -3.00% -$24,274.65
Over/Under Est: 11.62% $90,339.60
Amt Left: 33.47% $217,551.70
Delta: -4.02% -$33,555.60
Over/Under Est: 72.27% $561,652.00
Amt Left: 105.98% $688,864.10
Delta: -54.33% -$471,312.40
Subcontractor Percentage Amount
LARRY YOUNG PAVING, INC. 4.11% $32,078.72
HIGHWAY 1 LLC 1.42% $11,083.16
WILLOW CITY SIGN & RAIL, INC. 0.85% $6,634.29
Total: 6.38% $49,796.17

Bid Items & Bid Tabulations

38 Total 0 of 38
MADISON  |  CS  |  BRYAN  |  0917-31-031  |  06/01/2023  |  $777,206.00  |  BR 2022(281)  |  BRIDGE REPL  |  61 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
R CONSTRUCTION CIVIL, LLC
SEFBO PIPELINE BRIDGE, INCORPORATED
CROSS PLUS CONSTRUCTION, LLC
TEXAS MATERIALS GROUP, INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
PREPARING ROW
STA 3.300 $6,000.000 $3,500.000 $10,071.670 $1,100.000 $6,000.000 $12,000.000
EXCAVATION (ROADWAY)
CY 307.000 $35.000 $15.000 $10.550 $44.000 $50.000 $40.000
EXCAVATION (CHANNEL)
CY 1,050.000 $30.000 $15.000 $7.770 $44.000 $35.000 $40.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 7.000 $94.000 $500.000 $1,016.730 $165.000 $700.000 $100.000
FL BS (CMP IN PLACE)(TY A GR 1-2)(10")
SY 870.000 $45.000 $40.000 $38.800 $33.000 $46.000 $50.000
ASPH (RC-250)
GAL 195.000 $45.000 $15.000 $37.310 $11.000 $18.000 $20.000
AGGR (TY-B GR-5 OR TY-L GR-5)
CY 6.000 $1,700.000 $480.000 $581.510 $550.000 $1,800.000 $4,000.000
TRENCH EXCAVATION PROTECTION
LF 26.000 $20.000 $2.000 $92.310 $330.000 $100.000 $10.000
TEMPORARY SPL SHORING
SF 755.000 $80.000 $10.000 $64.840 $61.000 $75.000 $80.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 413.000 $225.000 $200.000 $113.980 $165.000 $194.000 $200.000
RAIL (TY T223)
LF 186.000 $150.000 $127.000 $117.660 $275.000 $200.000 $200.000
CONC BOX CULV (10 FT X 8 FT)
LF 108.000 $1,500.000 $2,100.000 $2,566.290 $2,090.000 $2,000.000 $4,500.000
WINGWALL (PW - 1) (HW=11 FT)
EA 2.000 $72,000.000 $52,000.000 $57,801.580 $55,000.000 $75,000.000 $65,000.000
SET (TY II) (24 IN) (CMP) (3: 1) (C)
EA 1.000 $1,800.000 $2,400.000 $2,691.000 $3,850.000 $2,400.000 $2,500.000
SET (TY II) (42 IN) (CMP) (3: 1) (C)
EA 1.000 $6,000.000 $7,055.000 $6,295.200 $8,250.000 $3,200.000 $5,000.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $15,000.000 $12,000.000 $63,600.000 $33,000.000 $30,000.000 $75,000.000
MOBILIZATION
LS 1.000 $69,000.000 $60,000.000 $60,000.000 $82,500.000 $80,000.000 $160,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $2,000.000 $700.000 $1,400.000 $5,500.000 $3,700.000 $20,000.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 71.000 $40.000 $95.000 $97.350 $55.000 $120.000 $1.000
ROCK FILTER DAMS (REMOVE)
LF 71.000 $12.000 $1.500 $13.520 $6.000 $60.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 543.000 $5.000 $3.800 $7.250 $17.000 $5.500 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 543.000 $2.000 $1.000 $0.880 $1.000 $1.500 $1.000
DRIVEWAYS (ACP)
SY 77.000 $70.000 $20.000 $195.530 $165.000 $72.000 $95.000
MTL W-BEAM GD FEN (TIM POST)
LF 13.000 $35.000 $34.000 $50.520 $44.000 $30.000 $50.000
MTL BEAM GD FEN TRANS (TL2)
EA 1.000 $1,300.000 $1,200.000 $1,920.000 $2,310.000 $1,800.000 $2,500.000
SHORT RADIUS
LF 25.000 $50.000 $60.000 $79.500 $44.000 $65.000 $80.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $1,000.000 $1,200.000 $1,200.000 $1,430.000 $1,500.000 $4,000.000
REMOVE SM RD SN SUP&AM
EA 2.000 $120.000 $110.000 $360.000 $110.000 $150.000 $50.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 3.000 $50.000 $15.000 $38.000 $55.000 $25.000 $500.000
INSTL OM ASSM (OM-3L)(TWT)GND
EA 2.000 $420.000 $150.000 $98.000 $55.000 $250.000 $500.000
INSTL OM ASSM (OM-3R)(TWT)GND
EA 2.000 $420.000 $150.000 $192.000 $55.000 $250.000 $500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $45.000 $25.000 $192.000 $55.000 $35.000 $50.000
PAVEMENT SEALER 6"
LF 400.000 $0.400 $3.000 $3.000 $6.000 $4.000 $25.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 200.000 $1.000 $6.000 $20.000 $11.000 $4.000 $25.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 200.000 $1.000 $6.000 $20.000 $11.000 $4.000 $25.000
REFL PAV MRKR TY II-A-A
EA 3.000 $15.000 $50.000 $35.000 $55.000 $6.200 $25.000
SP MIXES SP-C PG64-22
TON 125.000 $400.000 $200.000 $145.000 $330.000 $273.000 $250.000
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 2.000 $500.000 $350.000 $240.000 $110.000 $400.000 $500.000
Totals: $777,206.000 $649,993.900 $809,715.351 $833,990.000 $867,545.600 $1,338,858.000