Show Job Controls
Bid Cobra

MADISON SH 75 (0166-07-068)

Items: 64

County: MADISON
Length: 0.0000 MILES
Highway: SH 75
District: BRYAN
Control Number: 0166-07-068
DBE Goal: 0.0%
Project: STP 2025(888)HES
Guaranty: $16,000.00
Time: 79 WORKING DAYS
Engineer's Estimate: $822,327.07
Date: 07/01/2025 (11 months ago)
Contract Number: 7253031
Type: RECONSTRUCT EXISTING ROADWAY
Project ID: A00184431
Contract Type: Federal
Project Description: LOWER VERTICAL CURVE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DELMY REYES
MATT HENSARLING
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$822,327.07
Over/Under Est: -0.19% -$1,586.51
Over/Under Est: 8.75% $71,980.68
Amt Left: 8.96% $73,567.19
Over/Under Est: 11.51% $94,659.18
Amt Left: 11.73% $96,245.69
Delta: -2.54% -$22,678.50
Over/Under Est: 15.15% $124,581.42
Amt Left: 15.37% $126,167.93
Delta: -3.26% -$29,922.24
$1,098,304.75
Over/Under Est: 33.56% $275,977.68
Amt Left: 33.82% $277,564.19
Delta: -15.99% -$151,396.26
Subcontractor Percentage Amount
J & M CONTRACTING, COMPANY 19.89% $166,527.15
TRP CONSTRUCTION GROUP, LLC 7.33% $61,369.73
CEN TEX HYDROSEED, INC. 1.46% $12,223.71
LONESTAR TRAFFIC SAFETY, LLC 0.86% $7,200.27
Total: 29.54% $247,320.86

Bid Items & Bid Tabulations

64 Total 0 of 64
MADISON  |  SH 75  |  BRYAN  |  0166-07-068  |  07/01/2025  |  $822,327.07  |  STP 2025(888)HES  |  RECON EXIST ROADWAY  |  79 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
LARRY YOUNG PAVING, INC.
BIG CREEK CONSTRUCTION, LTD.
KNIFE RIVER CORPORATION - SOUTH
BRAZOS PAVING, INC.
PREPARING ROW
STA 9.500 $500.000 $350.000 $1,000.000 $1,000.000 $1,920.000 $1,200.000
REMOV CONC (PAV)
SY 556.000 $25.000 $40.000 $15.000 $12.000 $29.000 $33.000
REMOV CONC (DRIVEWAYS)
SY 323.000 $25.000 $50.000 $14.000 $20.000 $26.800 $33.000
RMV (8"-19") TRT/UNTRT BASE & ASPH PAV
SY 2,111.000 $15.000 $16.500 $17.000 $10.000 $16.000 $22.500
EXCAV (ROADWAY)
CY 1,005.000 $15.000 $28.000 $51.000 $22.000 $35.200 $56.250
BACKFILL (TY A OR B)
STA 9.500 $100.000 $400.000 $520.000 $800.000 $285.000 $1,300.000
FURN & PLACE TOPSOIL (4")
SY 5,320.000 $2.750 $1.250 $1.750 $1.500 $0.320 $1.500
BROADCAST SEED (PERM_RURAL_SAND)
SY 5,320.000 $2.500 $0.750 $1.000 $0.850 $0.830 $1.000
BROADCAST SEED (TEMP_WARM)
SY 2,660.000 $3.000 $0.650 $0.750 $0.750 $0.720 $0.850
BROADCAST SEED (TEMP_COOL)
SY 2,660.000 $2.250 $0.650 $0.750 $0.750 $0.720 $0.850
VEGETATIVE WATERING
TGL 1,064.000 $12.000 $5.000 $3.500 $20.000 $33.250 $36.500
CEM TRT(PLNT MX)(CL L)(TYA)(GR1-2)(10")
SY 2,956.000 $55.000 $50.000 $62.000 $60.000 $50.280 $42.650
PRIME COAT(MC-30 OR AE-P)
GAL 592.000 $11.000 $13.000 $10.000 $4.500 $10.900 $12.850
SP MIXES SP-B SAC-B PG64-22
TON 326.000 $120.000 $140.350 $210.000 $235.000 $150.000 $227.000
SP MIXES SP-C SAC-A PG70-22
TON 497.000 $135.000 $148.350 $150.000 $200.000 $152.000 $178.250
TACK COAT
GAL 747.000 $6.000 $3.500 $7.500 $5.000 $4.200 $13.500
PLANE & TEXT ASPH CONC PAV(0" TO 4")
SY 1,334.000 $5.000 $8.760 $7.000 $7.500 $7.000 $11.000
PLANE & TEXT ASPH CONC PAV(4" TO 6")
SY 889.000 $5.500 $12.750 $12.000 $9.000 $11.000 $14.000
PLANE & TEXT ASPH CONC PAV(6" TO 8")
SY 556.000 $5.750 $12.750 $18.000 $14.000 $17.000 $20.150
PLANE ASPH CONC PAV(4")
SY 2,889.000 $5.000 $8.500 $5.000 $4.000 $3.000 $11.000
RC PIPE (CL III)(18 IN)
LF 78.000 $114.000 $65.000 $94.000 $95.000 $88.000 $84.000
RC PIPE (CL III)(24 IN)
LF 242.000 $135.000 $140.000 $88.000 $95.000 $100.000 $106.300
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $1,730.010 $900.000 $1,100.000 $1,750.000 $1,238.000 $2,435.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 8.000 $2,200.000 $2,000.000 $1,500.000 $2,200.000 $1,300.000 $3,840.000
REMOV STR (INLET)
EA 1.000 $875.000 $750.000 $1,300.000 $800.000 $500.000 $2,610.000
REMOV STR (SET)
EA 8.000 $850.000 $850.000 $650.000 $625.000 $600.000 $1,600.000
REMOV STR (WINGWALL)
EA 4.000 $2,425.000 $1,200.000 $720.000 $1,200.000 $2,700.000 $630.000
REMOV STR (PIPE)
LF 406.000 $35.000 $40.000 $25.000 $15.000 $22.000 $57.750
MOBILIZATION
LS 1.000 $75,000.000 $42,000.000 $98,000.000 $75,000.000 $100,000.000 $116,410.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $7,250.000 $2,500.000 $6,400.000 $2,000.000 $8,100.000 $11,515.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $5,000.000 $1,800.000 $15,000.000 $6,600.000 $13,000.000
TMA (STATIONARY)
DAY 89.000 $275.000 $100.000 $250.000 $200.000 $500.000 $325.000
TMA (MOBILE OPERATION)
DAY 6.000 $325.000 $100.000 $1,400.000 $1,000.000 $900.000 $850.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 80.000 $60.000 $35.000 $44.000 $40.000 $39.000 $45.500
ROCK FILTER DAMS (REMOVE)
LF 80.000 $20.000 $10.000 $13.000 $12.000 $10.000 $13.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 200.000 $5.500 $5.000 $6.250 $5.500 $5.560 $6.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 200.000 $2.000 $1.000 $1.250 $1.250 $1.100 $1.300
CONSTRUCTING DETOURS
SY 178.000 $124.250 $254.000 $120.000 $200.000 $218.000 $125.000
INTERSECTIONS (ACP)
SY 418.000 $56.000 $105.500 $17.000 $65.000 $105.000 $54.600
DRIVEWAYS (ACP)
SY 449.000 $45.000 $98.500 $74.000 $65.000 $68.500 $53.150
RELOCATE EXISTING MAILBOX
EA 1.000 $400.000 $250.000 $340.000 $525.000 $330.000 $624.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 8.000 $825.000 $770.000 $910.000 $950.000 $850.000 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $1,070.000 $1,225.000 $1,000.000 $1,150.000 $1,361.000 $1,600.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $1,150.000 $1,200.000 $1,400.000 $1,150.000 $1,314.000 $1,540.000
REMOVE SM RD SN SUP&AM
EA 15.000 $160.000 $130.000 $170.000 $120.000 $145.000 $170.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 7,644.000 $0.450 $1.050 $1.250 $1.750 $1.170 $1.350
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 9,788.000 $0.700 $1.050 $1.250 $1.750 $1.170 $1.350
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 255.000 $5.250 $7.000 $8.750 $9.750 $7.800 $9.100
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 3,090.000 $1.700 $0.550 $0.750 $1.000 $0.610 $0.700
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 572.000 $2.700 $1.100 $1.500 $1.250 $1.220 $1.450
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 3,488.000 $1.500 $0.550 $0.750 $1.000 $0.600 $0.700
REFL PAV MRK TY I (W)8"(BRK)(090MIL)
LF 150.000 $1.350 $2.000 $2.500 $4.000 $2.500 $2.600
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 422.000 $1.350 $2.000 $2.500 $4.000 $2.500 $2.600
RE PROFILE PM TY I(W)6"(SLD)(090MIL)
LF 160.000 $1.000 $5.750 $7.250 $3.500 $6.400 $7.500
RE PROFILE PM TY I(Y)6"(SLD)(090MIL)
LF 160.000 $1.000 $5.750 $7.250 $3.500 $6.400 $7.500
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 2,930.000 $0.850 $1.350 $1.750 $3.000 $1.500 $1.750
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 3,328.000 $0.850 $1.350 $1.750 $3.000 $1.500 $1.750
PREFAB PM TY C (W)(24")(SLD)
LF 22.000 $18.000 $20.100 $25.000 $25.000 $25.000 $26.100
PREFAB PM TY C (W)(ARROW)
EA 5.000 $235.000 $309.000 $390.000 $450.000 $344.000 $400.000
PREFAB PM TY C (W)(WORD)
EA 4.000 $290.000 $377.000 $470.000 $550.000 $420.000 $490.000
PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)
LF 587.000 $4.000 $11.240 $14.000 $18.000 $12.490 $14.600
REFL PAV MRKR TY I-C
EA 34.000 $5.500 $7.000 $8.750 $10.000 $8.000 $9.100
REFL PAV MRKR TY II-A-A
EA 164.000 $7.000 $7.000 $8.750 $9.000 $8.000 $9.100
ELIM EXT PM & MRKS (6")
LF 2,242.000 $1.000 $0.520 $0.750 $4.000 $0.600 $0.700
Totals: $822,327.070 $820,740.560 $894,307.750 $916,986.250 $946,908.490 $1,098,304.750
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $22,500.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
Total: $27,500.00