MADISON SH 75 (0166-07-068)
Items: 64
County: MADISON
Length: 0.0000 MILES
Highway: SH 75
District: BRYAN
Control Number: 0166-07-068
DBE Goal: 0.0%
Project: STP 2025(888)HES
Guaranty: $16,000.00
Time: 79 WORKING DAYS
Engineer's Estimate: $822,327.07
Date: 07/01/2025 (11 months ago)
Contract Number: 7253031
Type: RECONSTRUCT EXISTING ROADWAY
Project ID: A00184431
Contract Type: Federal
Project Description: LOWER VERTICAL CURVE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DELMY REYES
MATT HENSARLING
MADISON SH 75 (0166-07-068)
Project Name: N/A
Project: STP 2025(888)HES
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: IH 45
Limits To: 0.2 MI S OF IH 45
Project Description: LOWER VERTICAL CURVE
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$822,327.07 | |||
| $820,740.56 |
-0.19%
-$1,586.51
|
|||
| $894,307.75 |
8.75%
$71,980.68
|
8.96%
$73,567.19
|
||
| $916,986.25 |
11.51%
$94,659.18
|
11.73%
$96,245.69
|
-2.54%
-$22,678.50
|
|
| $946,908.49 |
15.15%
$124,581.42
|
15.37%
$126,167.93
|
-3.26%
-$29,922.24
|
|
| $1,098,304.75 |
33.56%
$275,977.68
|
33.82%
$277,564.19
|
-15.99%
-$151,396.26
|
E
Engineer's Estimate
$822,327.07
$820,740.56
Over/Under Est:
-0.19%
-$1,586.51
$894,307.75
Over/Under Est:
8.75%
$71,980.68
Amt Left:
8.96%
$73,567.19
$916,986.25
Over/Under Est:
11.51%
$94,659.18
Amt Left:
11.73%
$96,245.69
Delta:
-2.54%
-$22,678.50
$946,908.49
Over/Under Est:
15.15%
$124,581.42
Amt Left:
15.37%
$126,167.93
Delta:
-3.26%
-$29,922.24
$1,098,304.75
Over/Under Est:
33.56%
$275,977.68
Amt Left:
33.82%
$277,564.19
Delta:
-15.99%
-$151,396.26
| Subcontractor | Percentage | Amount |
|---|---|---|
| J & M CONTRACTING, COMPANY | 19.89% | $166,527.15 |
| TRP CONSTRUCTION GROUP, LLC | 7.33% | $61,369.73 |
| CEN TEX HYDROSEED, INC. | 1.46% | $12,223.71 |
| LONESTAR TRAFFIC SAFETY, LLC | 0.86% | $7,200.27 |
| Total: | 29.54% | $247,320.86 |
Bid Items & Bid Tabulations
64
Total
0 of 64
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $22,500.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| Total: | $27,500.00 |