MADISON SH 21 (0117-05-063)
Items: 92
County: MADISON
Length: 0.0000 MILES
Highway: SH 21
District: BRYAN
Control Number: 0117-05-063
DBE Goal: 0.0%
Project: STP 2026(122)HES
Guaranty: $47,000.00
Time: 89 WORKING DAYS
Engineer's Estimate: $2,371,533.25
Date: 11/06/2025 (7 months ago)
Contract Number: 11253221
Type: EXTENDING/ADDING A TWLTL
Project ID: A00192965
Contract Type: Federal
Project Description: EXTEND/ADD TWLTL
Mail/Deliver Bids To: N/A
DELMY REYES
MATT HENSARLING
MADISON SH 21 (0117-05-063)
Project Name: N/A
Project: STP 2026(122)HES
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: 0.14 MI E OF IH 45
Limits To: 1.17 MI E OF IH 45
Project Description: EXTEND/ADD TWLTL
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,371,533.25 | |||
| $2,014,433.07 |
-15.06%
-$357,100.18
|
|||
| $2,378,581.84 |
0.3%
$7,048.59
|
18.08%
$364,148.77
|
||
| $2,399,583.94 |
1.18%
$28,050.69
|
19.12%
$385,150.87
|
-0.88%
-$21,002.10
|
|
| $2,434,664.17 |
2.66%
$63,130.92
|
20.86%
$420,231.10
|
-1.46%
-$35,080.23
|
|
| $2,638,161.15 |
11.24%
$266,627.90
|
30.96%
$623,728.08
|
-8.36%
-$203,496.98
|
|
| $2,795,415.18 |
17.87%
$423,881.93
|
38.77%
$780,982.11
|
-5.96%
-$157,254.03
|
|
| $3,269,229.77 |
37.85%
$897,696.52
|
62.29%
$1,254,796.70
|
-16.95%
-$473,814.59
|
|
| $3,989,171.38 |
68.21%
$1,617,638.13
|
98.03%
$1,974,738.31
|
-22.02%
-$719,941.61
|
E
Engineer's Estimate
$2,371,533.25
1
Awarded
$2,014,433.07
Over/Under Est:
-15.06%
-$357,100.18
$2,378,581.84
Over/Under Est:
0.3%
$7,048.59
Amt Left:
18.08%
$364,148.77
$2,399,583.94
Over/Under Est:
1.18%
$28,050.69
Amt Left:
19.12%
$385,150.87
Delta:
-0.88%
-$21,002.10
$2,434,664.17
Over/Under Est:
2.66%
$63,130.92
Amt Left:
20.86%
$420,231.10
Delta:
-1.46%
-$35,080.23
$2,638,161.15
Over/Under Est:
11.24%
$266,627.90
Amt Left:
30.96%
$623,728.08
Delta:
-8.36%
-$203,496.98
$2,795,415.18
Over/Under Est:
17.87%
$423,881.93
Amt Left:
38.77%
$780,982.11
Delta:
-5.96%
-$157,254.03
$3,269,229.77
Over/Under Est:
37.85%
$897,696.52
Amt Left:
62.29%
$1,254,796.70
Delta:
-16.95%
-$473,814.59
$3,989,171.38
Over/Under Est:
68.21%
$1,617,638.13
Amt Left:
98.03%
$1,974,738.31
Delta:
-22.02%
-$719,941.61
| Subcontractor | Percentage | Amount |
|---|---|---|
| STRIPE LINES, INC. | 3.67% | $73,929.69 |
| WILLOW CITY SIGN & RAIL, INC. | 1.58% | $31,828.04 |
| SURFACE PREPARATION TECHNOLOGIES, LLC | 0.53% | $10,676.50 |
| J. H. ODEN CONTRACTING COMPANY | 0.25% | $5,036.08 |
| Total: | 6.03% | $121,470.31 |