LUBBOCK VARIOUS (0905-00-142)
Items: 63
County: LUBBOCK
Length: 0.0000 MILES
Highway: VARIOUS
District: LUBBOCK
Control Number: 0905-00-142
DBE Goal: 7.0%
Project: F 2025(866)
Guaranty: $70,000.00
Time: 316 WORKING DAYS
Engineer's Estimate: $3,454,533.29
Date: 07/02/2025 (11 months ago)
Contract Number: 7253224
Type: CONSTRUCT RAMPS
Project ID: A00195963
Contract Type: Federal
Project Description: FY 2025 ADA RAMPS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
HEATH BOZEMAN
LUBBOCK VARIOUS (0905-00-142)
Project Name: N/A
Project: F 2025(866)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: VARIOUS LOCATIONS IN
Limits To: THE LUBBOCK DISTRICT
Project Description: FY 2025 ADA RAMPS
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,454,533.29 | |||
| $2,978,480.50 |
-13.78%
-$476,052.79
|
|||
| $3,063,718.43 |
-11.31%
-$390,814.86
|
2.86%
$85,237.93
|
||
| $4,276,263.00 |
23.79%
$821,729.71
|
43.57%
$1,297,782.50
|
-39.58%
-$1,212,544.57
|
E
Engineer's Estimate
$3,454,533.29
1
Awarded
$2,978,480.50
Over/Under Est:
-13.78%
-$476,052.79
$3,063,718.43
Over/Under Est:
-11.31%
-$390,814.86
Amt Left:
2.86%
$85,237.93
$4,276,263.00
Over/Under Est:
23.79%
$821,729.71
Amt Left:
43.57%
$1,297,782.50
Delta:
-39.58%
-$1,212,544.57
| Subcontractor | Percentage | Amount |
|---|---|---|
| ONE WAY CONCRETE CONSTRUCTION, LLC | 44.57% | $1,550,358.76 |
| FC TRAFFIC CONTROL, INC. | 0.58% | $20,175.19 |
| Total: | 45.15% | $1,570,533.95 |
Bid Items & Bid Tabulations
63
Total
0 of 63
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $20,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,000.00 |
| RAILROAD FORCE ACCOUNT WORK (PART) | $5,000.00 |
| Total: | $27,000.00 |