LUBBOCK VA (0905-00-134)

Items: 27

County: LUBBOCK
Length: N/A
Highway: VA
District: LUBBOCK
Control Number: 0905-00-134
DBE Goal: N/A
Project: BR 2024(179)
Guaranty: N/A
Time: 284 WORKING DAYS
Engineer's Estimate: $1,526,904.15
Date: 11/02/2023 (2 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
HEATH BOZEMAN
KRISTIN PHILLIP
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$1,526,904.15
$1,420,057.00
Over/Under Est: -7% -$106,847.15
$1,446,809.00
Over/Under Est: -5.25% -$80,095.15
Amt Left: 1.88% $26,752.00
Over/Under Est: -0.43% -$6,628.15
Amt Left: 7.06% $100,219.00
Delta: -5.08% -$73,467.00
$1,542,820.00
Over/Under Est: 1.04% $15,915.85
Amt Left: 8.64% $122,763.00
Delta: -1.48% -$22,544.00
$1,695,986.00
Over/Under Est: 11.07% $169,081.85
Amt Left: 19.43% $275,929.00
Delta: -9.93% -$153,166.00
Over/Under Est: 28.93% $441,755.45
Amt Left: 38.63% $548,602.60
Delta: -16.08% -$272,673.60
$2,440,135.96
Over/Under Est: 59.81% $913,231.81
Amt Left: 71.83% $1,020,078.96
Delta: -23.95% -$471,476.36

Bid Items & Bid Tabulations

27 Total 0 of 27
LUBBOCK  |  VA  |  LUBBOCK  |  0905-00-134  |  11/02/2023  |  $1,526,904.15  |  BR 2024(179)  |  BRIDGE MAINT  |  284 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ICOS MANAGEMENT, LLC
STX CIVIL
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
MIJELUM, L.L.C.
DIGG COMMERCIAL, LLC
SCR CIVIL CONSTRUCTION, LLC
GILVIN-TERRILL, LTD.
REMOVING CONC (RIPRAP)
SY 30.000 $50.000 $160.000 $29.000 $50.000 $250.000 $100.000 $500.000 $600.000
REMOVING CONC (SIDEWALKS)
SY 6.000 $50.000 $525.000 $18.000 $50.000 $700.000 $100.000 $800.000 $600.000
CEM STABIL BKFL
CY 50.000 $600.000 $325.000 $409.000 $300.000 $170.000 $300.000 $620.000 $1,000.000
BRIDGE SIDEWALK
SF 54.000 $110.000 $215.000 $29.000 $50.000 $20.000 $70.000 $116.000 $500.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 1,194.000 $225.000 $99.000 $99.000 $300.000 $200.000 $130.000 $110.000 $230.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 1,158.000 $200.000 $220.000 $88.000 $275.000 $130.000 $300.000 $220.000 $200.000
RIPRAP (CONC)(4 IN)
CY 103.000 $700.000 $375.000 $409.000 $750.000 $550.000 $800.000 $650.000 $1,500.000
CLEANING AND SEALING EXISTING JOINTS
LF 160.000 $100.000 $85.000 $88.000 $65.000 $30.000 $60.000 $27.000 $150.000
ARMOR JOINT (SEALED)
LF 864.000 $200.000 $345.000 $99.000 $225.000 $250.000 $70.000 $595.000 $480.000
MOBILIZATION
LS 1.000 $131,527.650 $15,000.000 $93,510.000 $150,000.000 $20,000.000 $85,000.000 $163,800.000 $240,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $5,000.000 $1.000 $1,265.000 $1,500.000 $10,000.000 $7,000.000 $3,900.000 $13,600.000
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 880.000 $35.000 $55.000 $41.000 $25.000 $120.000 $10.000 $45.000 $15.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 2,580.000 $30.000 $43.000 $29.000 $20.000 $15.000 $10.000 $38.000 $15.000
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 1,510.000 $30.000 $55.000 $41.000 $20.000 $15.000 $10.000 $30.000 $15.000
PCTB MOVE&RESET(F-SHAPE OR SNGL SLPTY1
LF 2,830.000 $15.000 $43.000 $35.000 $10.000 $80.000 $75.000 $32.000 $15.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 14.000 $3,000.000 $5,250.000 $1,753.000 $1,500.000 $4,000.000 $1,000.000 $1,600.000 $3,500.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $2,000.000 $5,250.000 $1,169.000 $1,500.000 $1,000.000 $1,000.000 $1,000.000 $2,350.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $10,000.000 $11,000.000 $5,844.000 $10,000.000 $14,000.000 $7,000.000 $8,000.000 $15,000.000
WK ZN PAV MRK REMOV (REFL) TY I-A
EA 189.000 $3.500 $5.000 $12.000 $35.000 $20.000 $10.000 $40.100 $35.000
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 231.000 $4.500 $5.000 $12.000 $35.000 $20.000 $10.000 $40.100 $35.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 84.000 $4.500 $5.000 $12.000 $35.000 $20.000 $15.000 $40.100 $35.000
WK ZN PAV MRK REMOV (TRAF BTN) TY W
EA 693.000 $4.000 $5.000 $12.000 $28.000 $10.000 $8.000 $32.100 $28.000
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
EA 819.000 $4.500 $5.000 $12.000 $28.000 $10.000 $8.000 $32.100 $28.000
BRIDGE JOINT REPAIR (PARTIAL DEPTH)
LF 300.000 $120.000 $110.000 $234.000 $100.000 $250.000 $80.000 $160.000 $1,100.000
REPLACE ELASTOMERIC BEARING PADS
EA 12.000 $7,000.000 $11,000.000 $44,416.000 $7,500.000 $4,600.000 $7,000.000 $7,775.000 $3,818.330
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 400.000 $115.000 $1.000 $13.000 $20.000 $50.000 $1,000.000 $125.000 $95.000
TMA (STATIONARY)
DAY 400.000 $200.000 $1.000 $13.000 $10.000 $50.000 $10.000 $350.000 $275.000
Totals: $1,526,904.150 $1,420,057.000 $1,446,809.000 $1,520,276.000 $1,542,820.000 $1,695,986.000 $1,968,659.600 $2,440,135.960