LUBBOCK VARIOUS (0905-00-132)
Items: 56
County: LUBBOCK
Length: 0.0000 MILES
Highway: VARIOUS
District: LUBBOCK
Control Number: 0905-00-132
DBE Goal: 0.0%
Project: F 2026(430)
Guaranty: $35,000.00
Time: 90 WORKING DAYS
Engineer's Estimate: $1,736,848.60
Date: 03/05/2026 (3 months ago)
Contract Number: 3263214
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00191311
Contract Type: Federal
Project Description: FY 26 STRIPING-SPECIALTY MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
SEE PLANS OR PROPOSAL BOOK
LUBBOCK VARIOUS (0905-00-132)
Project Name: N/A
Project: F 2026(430)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: VARIOUS LOCATIONS IN
Limits To: THE LUBBOCK DISTRICT
Project Description: FY 26 STRIPING-SPECIALTY MARKINGS
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,736,848.60 | |||
| $1,984,573.40 |
14.26%
$247,724.80
|
|||
| $2,289,373.10 |
31.81%
$552,524.50
|
15.36%
$304,799.70
|
||
| $2,649,266.05 |
52.53%
$912,417.45
|
33.49%
$664,692.65
|
-15.72%
-$359,892.95
|
|
| $2,962,318.78 |
70.56%
$1,225,470.18
|
49.27%
$977,745.38
|
-11.82%
-$313,052.73
|
|
| $3,251,105.95 |
87.18%
$1,514,257.35
|
63.82%
$1,266,532.55
|
-9.75%
-$288,787.17
|
E
Engineer's Estimate
$1,736,848.60
1
Awarded
$1,984,573.40
Over/Under Est:
14.26%
$247,724.80
$2,289,373.10
Over/Under Est:
31.81%
$552,524.50
Amt Left:
15.36%
$304,799.70
$2,649,266.05
Over/Under Est:
52.53%
$912,417.45
Amt Left:
33.49%
$664,692.65
Delta:
-15.72%
-$359,892.95
$2,962,318.78
Over/Under Est:
70.56%
$1,225,470.18
Amt Left:
49.27%
$977,745.38
Delta:
-11.82%
-$313,052.73
$3,251,105.95
Over/Under Est:
87.18%
$1,514,257.35
Amt Left:
63.82%
$1,266,532.55
Delta:
-9.75%
-$288,787.17
Bid Items & Bid Tabulations
56
Total
0 of 56
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $0.01 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $35,000.00 |
| Total: | $35,000.01 |