LUBBOCK VA (0905-00-105)

Items: 84

County: LUBBOCK
Length: N/A
Highway: VA
District: LUBBOCK
Control Number: 0905-00-105
DBE Goal: N/A
Project: STP 2019(998)
Guaranty: N/A
Time: 336 WORKING DAYS
Engineer's Estimate: $2,713,037.10
Date: 06/05/2019 (7 years ago)
Contract Number: N/A
Type: PEDESTRIAN, SIDEWALKS, & CURB RAMPS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$2,713,037.10
$3,291,800.00
Over/Under Est: 21.33% $578,762.90
$3,808,363.75
Over/Under Est: 40.37% $1,095,326.65
Amt Left: 15.69% $516,563.75

Bid Items & Bid Tabulations

84 Total 0 of 84
LUBBOCK  |  VA  |  LUBBOCK  |  0905-00-105  |  06/05/2019  |  $2,713,037.10  |  STP 2019(998)  |  PEDESTRIAN, SIDEWALKS, & CURB RAMPS  |  336 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TI-ZACK CONCRETE, INC.
ENCINO LANDSCAPE, INC.
REMOVING CONC (PAV)
SY 260.000 $15.000 $25.000 $12.000
REMOVING CONC (MEDIANS)
SY 8.000 $30.000 $25.000 $20.000
REMOVING CONC (DRIVEWAYS)
SY 2,595.000 $14.000 $20.000 $20.000
REMOVING CONC (CURB OR CURB & GUTTER)
LF 5,266.000 $6.000 $10.000 $10.000
REMOVING CONC (SIDEWALK OR RAMP)
SY 244.000 $25.000 $12.000 $20.000
REMOVING STAB BASE AND ASPH PAV(0"-16")
SY 4,281.000 $15.000 $12.000 $15.000
EXCAVATION (SPECIAL)
CY 660.000 $10.000 $1.000 $12.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 357.000 $7.500 $1.000 $20.000
FURNISHING AND PLACING TOPSOIL (4")
SY 9,837.000 $1.500 $4.000 $1.000
BLOCK SODDING
SY 9,837.000 $5.500 $4.000 $5.000
VEGETATIVE WATERING
MG 166.000 $10.000 $1.000 $15.000
FOG SEAL (CSS-1H)
GAL 38.000 $3.250 $15.000 $5.000
D-GR HMA(SQ) TY-C PG76-22
TON 150.000 $125.000 $200.000 $300.000
PLANE ASPH CONC PAV(0" TO 4")
SY 250.000 $16.000 $25.000 $3.000
CONC PVMT (CONT REINF - CRCP) (12")
SY 18.000 $80.000 $125.000 $80.000
CONC PAV (JOINT REINF) (10")
SY 250.000 $60.000 $125.000 $90.000
CL A CONC (MISC)
CY 24.000 $895.000 $1,000.000 $750.000
CL C CONC (MISC)
CY 1.000 $895.000 $1,000.000 $900.000
RIPRAP (CONC)(5 IN)
CY 1.000 $1,000.000 $1,000.000 $500.000
RIPRAP (MOW STRIP)(4 IN)
CY 4.000 $600.000 $1,000.000 $500.000
RAIL (HANDRAIL)(TY B)
LF 22.000 $110.000 $85.000 $200.000
RAIL (HANDRAIL)(TY F)
LF 36.000 $135.000 $115.000 $200.000
CONC BOX CULV (4 FT X 3 FT)(EXTEND)
LF 6.000 $700.000 $500.000 $700.000
INLET (COMP) (TY SIDEWALK BRIDGE)
EA 4.000 $8,500.000 $3,000.000 $7,500.000
WINGWALL (FW - 0) (HW=3 FT)
EA 1.000 $3,500.000 $5,000.000 $6,500.000
GRATE & FRAME
EA 2.000 $2,500.000 $1,000.000 $800.000
ADJUSTING MANHOLES
EA 1.000 $600.000 $500.000 $800.000
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 7.000 $250.000 $150.000 $600.000
REMOV STR (WINGWALL)
EA 2.000 $1,500.000 $1,500.000 $1,200.000
REMOVE STR (RAIL)
LF 107.000 $50.000 $25.000 $15.000
MOBILIZATION
LS 1.000 $259,000.000 $250,000.000 $350,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 21.000 $5,000.000 $1,000.000 $9,000.000
SANDBAGS FOR EROSION CONTROL
EA 2,000.000 $2.500 $0.100 $7.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,000.000 $2.000 $0.100 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,000.000 $0.750 $0.100 $1.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 500.000 $7.500 $0.100 $4.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,500.000 $4.000 $0.100 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,000.000 $1.000 $0.100 $1.000
CONC CURB (TY II)
LF 170.000 $20.000 $40.000 $15.000
CONC CURB & GUTTER (TY I)
LF 26.000 $30.000 $40.000 $25.000
CONC CURB & GUTTER (TY II)
LF 636.000 $30.000 $40.000 $25.000
CONC CURB & GUTTER (ARMOR CURB)
LF 30.000 $300.000 $300.000 $400.000
DRIVEWAYS (CONC)
SY 8,015.000 $65.000 $89.000 $80.000
DRIVEWAYS (ACP)
SY 144.000 $100.000 $95.000 $80.000
DRIVEWAYS (BASE)
SY 195.000 $20.000 $25.000 $50.000
CONC SIDEWALKS (4")
SY 13,069.000 $50.000 $89.000 $75.000
CONC SIDEWALKS (5")
SY 300.000 $85.000 $80.000 $75.000
CURB RAMPS (TY 1)
SY 168.000 $80.000 $120.000 $120.000
CURB RAMPS (TY 2)
SY 33.000 $80.000 $120.000 $120.000
CURB RAMPS (TY 3)
SY 246.000 $80.000 $120.000 $120.000
CURB RAMPS (TY 6)
SY 141.000 $80.000 $120.000 $120.000
CURB RAMPS (TY 7)
SY 812.000 $80.000 $120.000 $120.000
CONC SIDEWALKS (SPECIAL) (TYPE B)
SY 1,946.000 $95.000 $175.000 $350.000
CONDT (PVC) (SCH 80) (3")
LF 45.000 $10.000 $45.000 $10.000
CONDT (PVC) (SCH 80) (3") (BORE)
LF 50.000 $50.000 $60.000 $50.000
ELEC CONDR (NO.6) BARE
LF 45.000 $10.000 $15.000 $1.000
GROUND BOX TY C (162911)
EA 13.000 $875.000 $750.000 $800.000
GROUND BOX TY C (162911)W/APRON
EA 2.000 $1,100.000 $950.000 $1,000.000
REMOVE GROUND BOX
EA 15.000 $410.000 $50.000 $200.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 38.000 $900.000 $150.000 $400.000
RELOCATE SM RD SN SUP&AM TY S80
EA 35.000 $1,000.000 $150.000 $400.000
PREFAB PAV MRK TY B (W)(12")(SLD)
LF 2,562.000 $9.000 $14.000 $6.000
PREFAB PAV MRK TY B (W)(24")(SLD)
LF 706.000 $20.000 $28.000 $15.000
PREFAB PAV MRK TY B (Y)(MED NOSE)
EA 1.000 $500.000 $500.000 $300.000
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 1,445.000 $6.500 $9.000 $6.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 353.000 $14.000 $18.000 $14.000
ELIM EXT PAV MRK & MRKS (4")
LF 165.000 $1.000 $2.000 $0.500
ELIM EXT PAV MRK & MRKS (8")
LF 227.000 $2.000 $4.000 $0.750
ELIM EXT PAV MRK & MRKS (12")
LF 1,670.000 $3.000 $2.500 $1.500
ELIM EXT PAV MRK & MRKS (24")
LF 1,249.000 $3.500 $5.000 $3.000
PAV SURF PREP FOR MRK (12")
LF 2,562.000 $2.000 $1.000 $1.000
PAV SURF PREP FOR MRK (24")
LF 706.000 $3.600 $2.000 $2.000
TRF SIG CBL (TY A)(14 AWG)(4 CONDR)
LF 147.000 $5.000 $12.000 $2.000
TRF SIG CBL (TY A)(14 AWG)(10 CONDR)
LF 147.000 $2.500 $12.000 $5.000
PED POLE ASSEMBLY
EA 1.000 $2,000.000 $3,500.000 $1,800.000
RELOCATE PED POLE ASSEMBLY
EA 1.000 $1,200.000 $3,500.000 $1,200.000
PED DETECT PUSH BUTTON (STANDARD)
EA 24.000 $395.000 $250.000 $400.000
INSTALL OF VEHICLE DETECTORS
LF 10,000.000 $3.800 $0.010 $0.100
REMOVAL OF PEDESTRIAN PUSH BUTTONS
EA 24.000 $200.000 $50.000 $50.000
LITTER REMOVAL
CYC 1.000 $3,500.000 $2,500.000 $1,400.000
RETROFIT DET WARN SURF(SURF APPLIED)
EA 5.000 $500.000 $500.000 $350.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,000.000 $5,000.000 $13,500.000
TMA (STATIONARY)
DAY 672.000 $250.000 $20.000 $200.000
TMA (MOBILE OPERATION)
DAY 10.000 $490.000 $250.000 $250.000
Totals: $2,713,037.100 $3,291,800.000 $3,808,363.750