LUBBOCK VA (0905-00-096)

Items: 10

County: LUBBOCK
Length: N/A
Highway: VA
District: LUBBOCK
Control Number: 0905-00-096
DBE Goal: N/A
Project: STP 2019(615)
Guaranty: N/A
Time: 75 WORKING DAYS
Engineer's Estimate: $290,745.00
Date: 03/05/2019 (7 years ago)
Contract Number: N/A
Type: REPAIR SETS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$290,745.00
$277,650.00
Over/Under Est: -4.5% -$13,095.00
Over/Under Est: 0.04% $105.00
Amt Left: 4.75% $13,200.00
Over/Under Est: 0.16% $455.00
Amt Left: 4.88% $13,550.00
Delta: -0.12% -$350.00
Over/Under Est: 8.48% $24,652.50
Amt Left: 13.6% $37,747.50
Delta: -8.31% -$24,197.50
Over/Under Est: 25.01% $72,705.00
Amt Left: 30.9% $85,800.00
Delta: -15.24% -$48,052.50
Over/Under Est: 37.8% $109,905.00
Amt Left: 44.3% $123,000.00
Delta: -10.24% -$37,200.00

Bid Items & Bid Tabulations

10 Total 0 of 10
LUBBOCK  |  VA  |  LUBBOCK  |  0905-00-096  |  03/05/2019  |  $290,745.00  |  STP 2019(615)  |  REPAIR SETS  |  75 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TI-ZACK CONCRETE, INC.
TALBRAN ENTERPRISES LLC
SJ&J CONSTRUCTION, LLC
SCR CIVIL CONSTRUCTION, LLC
CHAMPION INFRASTRUCTURE, LLC
GILVIN-TERRILL, LTD.
CONC STR REPAIR (STANDARD)
SF 64.500 $200.000 $200.000 $400.000 $100.000 $345.000 $240.000 $700.000
RIPRAP (CONC)(5 IN)
CY 19.000 $1,000.000 $1,000.000 $1,200.000 $2,500.000 $3,385.000 $860.000 $3,550.000
ANCHOR BOLTS
EA 25.000 $200.000 $40.000 $200.000 $100.000 $158.000 $150.000 $500.000
SET (PIPE RUNNER ASSEMBLY)
EA 36.000 $4,000.000 $3,000.000 $3,200.000 $1,350.000 $3,275.000 $4,800.000 $4,000.000
SET (REPLACE PIPE RUNNER)
EA 26.000 $1,200.000 $2,000.000 $1,000.000 $1,200.000 $1,300.000 $2,300.000 $1,000.000
CLEAN EXIST CULVERTS
CY 27.000 $200.000 $100.000 $500.000 $1,200.000 $165.000 $240.000 $1,000.000
MOBILIZATION
LS 1.000 $23,795.000 $30,000.000 $30,000.000 $80,000.000 $31,500.000 $35,000.000 $39,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,000.000 $5,000.000 $5,000.000 $6,000.000 $3,500.000 $4,500.000 $2,500.000
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
EA 13.000 $150.000 $350.000 $100.000 $100.000 $75.000 $100.000 $350.000
TMA (STATIONARY)
DAY 75.000 $300.000 $300.000 $350.000 $150.000 $250.000 $400.000 $300.000
Totals: $290,745.000 $277,650.000 $290,850.000 $291,200.000 $315,397.500 $363,450.000 $400,650.000