LIVE OAK US0281 (6203-87-001)
Items: 3
County: LIVE OAK
Length: N/A
Highway: US0281
District: CORPUS CHRISTI
Control Number: 6203-87-001
DBE Goal: N/A
Project: RMC - 620387001
Guaranty: N/A
Time: 603 CALENDAR DAYS
Engineer's Estimate: $205,980.50
Date: 02/23/2010 (16 years ago)
Contract Number: N/A
Type: MOWING HIGHWAY RIGHT OF WAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$205,980.50 | |||
| $168,257.82 |
-18.31%
-$37,722.68
|
|||
| $183,170.70 |
-11.07%
-$22,809.80
|
8.86%
$14,912.88
|
||
| $200,894.50 |
-2.47%
-$5,086.00
|
19.4%
$32,636.68
|
-9.68%
-$17,723.80
|
|
| $214,928.82 |
4.34%
$8,948.32
|
27.74%
$46,671.00
|
-6.99%
-$14,034.32
|
|
| $215,042.00 |
4.4%
$9,061.50
|
27.81%
$46,784.18
|
-0.05%
-$113.18
|
E
Engineer's Estimate
$205,980.50
$168,257.82
Over/Under Est:
-18.31%
-$37,722.68
$183,170.70
Over/Under Est:
-11.07%
-$22,809.80
Amt Left:
8.86%
$14,912.88
$200,894.50
Over/Under Est:
-2.47%
-$5,086.00
Amt Left:
19.4%
$32,636.68
Delta:
-9.68%
-$17,723.80
$214,928.82
Over/Under Est:
4.34%
$8,948.32
Amt Left:
27.74%
$46,671.00
Delta:
-6.99%
-$14,034.32
$215,042.00
Over/Under Est:
4.4%
$9,061.50
Amt Left:
27.81%
$46,784.18
Delta:
-0.05%
-$113.18
Bid Items & Bid Tabulations
3
Total
0 of 3