LIVE OAK CR 216 (0916-29-016)
Items: 88
County: LIVE OAK
Length: 0.0000 MILES
Highway: CR 216
District: CORPUS CHRISTI
Control Number: 0916-29-016
DBE Goal: 5.0%
Project: BR 2024(936)
Guaranty: $100,000.00
Time: 529 WORKING DAYS
Engineer's Estimate: $7,223,072.75
Date: 06/04/2025 (1 year ago)
Contract Number: 6253014
Type: BRIDGE REPLACEMENT
Project ID: A00136607
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES AT SALT CREEK BRIDGE.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ERIC MARTINEZ
LUCIA ADAME
LIVE OAK CR 216 (0916-29-016)
Project Name: N/A
Project: BR 2024(936)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: STR. (AA0156001) SALT CREEK
Limits To: APPROX. .70 MI E OF SH 72
Project Description: REPLACE BRIDGE AND APPROACHES AT SALT CREEK BRIDGE.
LIVE OAK CARMEL DR (0916-29-018)
Project Name: CARMEL HILLS DR LIVEOAK BELDON HOLLOW CR
Project: BR 2024(967)
Length: 0.0000 MILES
Project Type: BRIDGE REPLACEMENT
Limits From: STR. (AA0271001) BELDON HOLLOW CREEK
Limits To: APPROX. 1.8 MIL SE OF FM 534
Project Description: REPLACE BRIDGE AND APPROACHES AT BELDON HOLLOW CREEK BRIDGE.
LIVE OAK PORTER RD (0916-29-020)
Project Name: LIVE OAK BR ON PORTER @ LAGARTO RE-LET
Project: BR 2025(571)
Length: 0.0000 MILES
Project Type: BRIDGE REPLACEMENT
Limits From: STR (AA00352001) CM PORTER @ LAGARTO
Limits To: APPROX 0.3 MILES NORTH OF CR 174
Project Description: REPLACE BRIDGE AND APPROACHES
LIVE OAK COUNTY ROAD 414 (0916-29-017)
Project Name: CR 414 LIVE OAK SALT BRANCH BRIDGE
Project: BR 2024(966)
Length: 0.0000 MILES
Project Type: BRIDGE REPLACEMENT
Limits From: STR. (AA0177001) SALT BRANCH
Limits To: APPROX. .80 MI NW OF FM 99
Project Description: REPLACE BRIDGE AND APPROACHES AT SALT BRANCH CREEK.
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$7,223,072.75 | |||
| $4,876,307.11 |
-32.49%
-$2,346,765.64
|
|||
| $5,221,047.30 |
-27.72%
-$2,002,025.45
|
7.07%
$344,740.19
|
||
| $6,969,270.60 |
-3.51%
-$253,802.15
|
42.92%
$2,092,963.49
|
-33.48%
-$1,748,223.30
|
|
| $6,977,000.00 |
-3.41%
-$246,072.75
|
43.08%
$2,100,692.89
|
-0.11%
-$7,729.40
|
|
| $7,536,248.52 |
4.34%
$313,175.77
|
54.55%
$2,659,941.41
|
-8.02%
-$559,248.52
|
|
| $7,751,280.00 |
7.31%
$528,207.25
|
58.96%
$2,874,972.89
|
-2.85%
-$215,031.48
|
|
| $8,537,705.57 |
18.2%
$1,314,632.82
|
75.09%
$3,661,398.46
|
-10.15%
-$786,425.57
|
E
Engineer's Estimate
$7,223,072.75
1
Awarded
$4,876,307.11
Over/Under Est:
-32.49%
-$2,346,765.64
$5,221,047.30
Over/Under Est:
-27.72%
-$2,002,025.45
Amt Left:
7.07%
$344,740.19
$6,969,270.60
Over/Under Est:
-3.51%
-$253,802.15
Amt Left:
42.92%
$2,092,963.49
Delta:
-33.48%
-$1,748,223.30
$6,977,000.00
Over/Under Est:
-3.41%
-$246,072.75
Amt Left:
43.08%
$2,100,692.89
Delta:
-0.11%
-$7,729.40
$7,536,248.52
Over/Under Est:
4.34%
$313,175.77
Amt Left:
54.55%
$2,659,941.41
Delta:
-8.02%
-$559,248.52
$7,751,280.00
Over/Under Est:
7.31%
$528,207.25
Amt Left:
58.96%
$2,874,972.89
Delta:
-2.85%
-$215,031.48
$8,537,705.57
Over/Under Est:
18.2%
$1,314,632.82
Amt Left:
75.09%
$3,661,398.46
Delta:
-10.15%
-$786,425.57
| Subcontractor | Percentage | Amount |
|---|---|---|
| ANCORTEX, INC. | 9.00% | $438,867.64 |
| A K FUQUAY CONSTRUCTION | 2.21% | $107,766.39 |
| DIIBS SPECIALISTS, LLC | 2.04% | $99,476.67 |
| HIGHWAY BARRICADES AND SERVICES, LLC | 0.52% | $25,356.80 |
| Total: | 13.77% | $671,467.50 |
Bid Items & Bid Tabulations
88
Total
0 of 88
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| Total: | $15,000.00 |