LIMESTONE US0084 (6323-45-001)

Items: 14

County: LIMESTONE
Length: N/A
Highway: US0084
District: WACO
Control Number: 6323-45-001
DBE Goal: N/A
Project: RMC - 632345001
Guaranty: N/A
Time: 70 W
Engineer's Estimate: $148,874.34
Date: 11/14/2017 (8 years ago)
Contract Number: N/A
Type: TREE TRIMMING AND REMOVAL
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$148,874.34
$137,009.26
Over/Under Est: -7.97% -$11,865.08
$144,968.00
Over/Under Est: -2.62% -$3,906.34
Amt Left: 5.81% $7,958.74
Over/Under Est: 0.47% $695.66
Amt Left: 9.17% $12,560.74
Delta: -3.17% -$4,602.00
Over/Under Est: 15.5% $23,075.66
Amt Left: 25.5% $34,940.74
Delta: -14.96% -$22,380.00
Over/Under Est: 26.28% $39,125.66
Amt Left: 37.22% $50,990.74
Delta: -9.33% -$16,050.00
Over/Under Est: 27.31% $40,654.66
Amt Left: 38.33% $52,519.74
Delta: -0.81% -$1,529.00
Over/Under Est: 75.38% $112,225.66
Amt Left: 90.57% $124,090.74
Delta: -37.76% -$71,571.00

Bid Items & Bid Tabulations

14 Total 0 of 14
LIMESTONE  |  US0084  |  WACO  |  6323-45-001  |  11/14/2017  |  $148,874.34  |  RMC - 632345001  |  TREE TRIM AND RMVL  |  70 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
C.E.S. CONTRACTOR
LONESTAR HAWK, INC.
DEKALB TREE SPECIALIST
CHAMPION INFRASTRUCTURE, LLC
KASPARIAN UNDERGROUND, LLC
CROSS PLUS CONSTRUCTION, LLC
DREWERY CONSTRUCTION COMPANY, INCORPORATED
MOBILIZATION (CALLOUT)
EA 3.000 $3,587.330 $1,000.000 $1.000 $1.000 $500.000 $100.000 $100.000 $1,500.000
MOBILIZATION (EMERGENCY)
EA 5.000 $717.470 $1,500.000 $1.000 $1.000 $1,000.000 $100.000 $100.000 $2,500.000
TREE TRIMMING / BRUSH REMOVAL
MI 55.000 $2,000.000 $1,396.120 $1,850.000 $2,077.000 $2,000.000 $2,500.000 $2,500.000 $3,100.000
TREE TRIMMING / BRUSH REMOVAL(CHANNELS)
AC 6.000 $1,500.000 $6,139.610 $3,000.000 $1,900.000 $2,800.000 $3,000.000 $3,000.000 $6,500.000
TREE REMOVAL (4" - 12" DIA)
EA 85.000 $50.000 $45.000 $75.000 $76.000 $120.000 $60.000 $100.000 $85.000
TREE REMOVAL (12" - 18" DIA)
EA 23.000 $75.000 $60.000 $95.000 $135.000 $200.000 $100.000 $123.000 $125.000
TREE REMOVAL (18" - 24" DIA)
EA 31.000 $100.000 $90.000 $150.000 $177.000 $300.000 $300.000 $200.000 $125.000
TREE REMOVAL (24" - 30" DIA)
EA 11.000 $150.000 $120.000 $320.000 $250.000 $400.000 $400.000 $400.000 $325.000
TREE REMOVAL (30" - 36" DIA)
EA 9.000 $250.000 $200.000 $320.000 $300.000 $500.000 $500.000 $700.000 $450.000
TREE REMOVAL (36" - 42" DIA)
EA 1.000 $350.000 $400.000 $400.000 $500.000 $750.000 $850.000 $800.000 $1,500.000
TREE REMOVAL (42" - 48" DIA)
EA 1.000 $450.000 $435.000 $500.000 $500.000 $900.000 $1,000.000 $900.000 $2,200.000
TREE REMOVAL (48" - 60" DIA)
EA 2.000 $500.000 $120.000 $1,500.000 $650.000 $1,200.000 $1,000.000 $1,000.000 $2,900.000
TREE REMOVAL (60" - 72" DIA)
EA 1.000 $600.000 $120.000 $1,500.000 $875.000 $1,500.000 $1,250.000 $1,200.000 $3,000.000
STUMP REMOVAL (GREATER THAN 12")
EA 1.000 $150.000 $575.000 $200.000 $250.000 $100.000 $1,000.000 $100.000 $500.000
Totals: $148,874.340 $137,009.260 $144,968.000 $149,570.000 $171,950.000 $188,000.000 $189,529.000 $261,100.000