LIMESTONE SH 7 (0382-03-038)

Items: 73

County: LIMESTONE
Length: 0.0000 MILES
Highway: SH 7
District: WACO
Control Number: 0382-03-038
DBE Goal: 0.0%
Project: C 382-3-38
Guaranty: $100,000.00
Time: 165 WORKING DAYS
Engineer's Estimate: $18,679,272.34
Date: 10/09/2025 (8 months ago)
Contract Number: 10253205
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00182265
Project Description: REHAB
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JOSH VOILES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$18,679,272.34
$13,941,159.05
Over/Under Est: -25.37% -$4,738,113.29
Over/Under Est: -21.85% -$4,082,256.00
Amt Left: 4.7% $655,857.29
Over/Under Est: -12.96% -$2,420,498.52
Amt Left: 16.62% $2,317,614.77
Delta: -11.38% -$1,661,757.48
$18,392,180.12
Over/Under Est: -1.54% -$287,092.22
Amt Left: 31.93% $4,451,021.07
Delta: -13.12% -$2,133,406.30
Subcontractor Percentage Amount
LINEAR TRAFFIC MARKINGS LLC 1.11% $152,620.94
FORTSON CONTRACTING, INC. 0.87% $119,621.82
CEN TEX HYDROSEED, INC. 0.32% $43,998.83
SURFACE PREPARATION TECHNOLOGIES, LLC 0.20% $27,499.27
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC 0.16% $21,999.41
TEXAS TRAFFIC AND BARRICADE, LLC 0.00% $0.00
Total: 2.66% $365,740.27

Bid Items & Bid Tabulations

73 Total 0 of 73
LIMESTONE  |  SH 7  |  WACO  |  0382-03-038  |  10/09/2025  |  $18,679,272.34  |  C 382-3-38  |  REHAB EXIST ROADWAY  |  165 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
TEXAS MATERIALS GROUP, INC.
KNIFE RIVER CORPORATION - SOUTH
A. L. HELMCAMP, INC.
REMOV CONC (PAV)
SY 510.000 $50.000 $25.000 $57.000 $34.000 $29.500
REMOV CONC (MOWSTRIP)
LF 2,558.000 $11.000 $15.000 $15.000 $11.000 $26.300
RMV (0"-4") TRT/UNTRT BASE & ASPH PAV
SY 5,245.000 $10.000 $10.000 $16.000 $9.000 $3.200
SUBGR WIDEN (OC)
SY 342.000 $16.000 $15.000 $75.000 $15.000 $49.200
BACKFILL (TY B)
STA 491.000 $215.000 $225.000 $175.000 $240.000 $180.000
BLADING
STA 10.000 $500.000 $500.000 $600.000 $250.000 $177.000
DRILL SEED (PERM_RURAL_CLAY)
SY 1,493.000 $0.350 $1.500 $2.000 $1.350 $1.300
DRILL SEED (TEMP_WARM_COOL)
SY 1,493.000 $0.280 $1.500 $2.000 $1.000 $1.100
VEGETATIVE WATERING
TGL 24.400 $33.300 $25.000 $78.000 $65.000 $55.750
FL BS (RDWY DEL) (TY D GR 5) (IN VEH)
CY 241.000 $215.000 $100.000 $95.000 $80.000 $112.000
CEMENT
TON 1,311.000 $225.000 $250.000 $228.000 $240.000 $235.000
ASPHALT BINDER (PG 64-22)
TON 4,109.000 $675.000 $550.000 $520.000 $705.000 $535.000
FOAM ASPH TRT (EXIST MATL) (10")
SY 261,830.000 $3.410 $3.000 $4.500 $3.850 $6.750
FOG SEAL (CSS-1H)
GAL 26,218.000 $3.550 $5.000 $2.600 $11.000 $3.000
ASPH (CRS-2P)
GAL 157,110.000 $4.330 $2.000 $2.950 $3.150 $3.000
AGGR (TY-D OR L, GR-4)
CY 2,767.000 $152.360 $117.000 $143.000 $145.000 $150.000
SP MIXES SP-B PG64-22
TON 42,789.000 $130.000 $88.500 $98.300 $106.000 $126.000
SP MIXES SP-C SAC-B PG76-22
TON 28,322.000 $125.250 $94.000 $119.000 $117.000 $131.000
TACK COAT
GAL 49,016.000 $9.100 $1.000 $2.300 $1.850 $4.350
PLANE ASPH CONC PAV(3")
SY 244,651.000 $2.250 $2.500 $1.700 $0.850 $2.650
PLANE ASPH CONC PAV (3" TO 5")
SY 6,608.000 $3.550 $5.000 $4.900 $3.250 $2.000
TEMPORARY SPL SHORING
SF 1,306.000 $60.000 $50.000 $41.000 $35.000 $63.000
RIPRAP (MOW STRIP)(4 IN)
CY 148.000 $542.250 $650.000 $700.000 $690.000 $1,100.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 82.000 $210.000 $150.000 $375.000 $315.000 $278.000
WINGWALL (PW - 1) (HW=5 FT)
EA 1.000 $22,000.000 $20,000.000 $24,000.000 $18,700.000 $23,100.000
WINGWALL (PW - 1) (HW=6 FT)
EA 1.000 $22,000.000 $25,000.000 $35,000.000 $20,300.000 $26,300.000
WINGWALL (PW - 1) (HW=7 FT)
EA 2.000 $36,000.000 $45,000.000 $48,000.000 $23,700.000 $33,600.000
CLEAN EXIST CULVERTS
EA 2.000 $4,750.000 $3,500.000 $4,000.000 $1,700.000 $2,600.000
REMOV STR (WINGWALL)
EA 4.000 $2,500.000 $3,500.000 $900.000 $1,850.000 $2,600.000
MOBILIZATION
LS 1.000 $1,725,749.839 $1,387,000.000 $551,600.000 $1,335,000.000 $1,500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $10,000.000 $5,000.000 $1,950.000 $15,000.000 $15,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 120.000 $140.000 $150.000 $54.130 $125.000 $249.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $9,500.000 $10,000.000 $5,600.000 $15,000.000 $20,700.000
TMA (STATIONARY)
DAY 394.000 $260.000 $150.000 $270.630 $25.000 $263.000
TMA (MOBILE OPERATION)
DAY 66.000 $90.000 $250.000 $270.630 $25.000 $680.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 368.000 $36.350 $35.000 $37.000 $33.000 $33.600
ROCK FILTER DAMS (REMOVE)
LF 368.000 $9.000 $10.000 $12.000 $10.000 $10.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 5,805.000 $4.690 $4.000 $4.000 $5.000 $3.400
TEMP SEDMT CONT FENCE (REMOVE)
LF 5,805.000 $1.760 $1.000 $1.000 $1.000 $1.100
INTERSECTIONS (ACP)
SY 193.000 $63.000 $30.000 $23.000 $60.000 $133.000
DRIVEWAYS (ACP)
SY 4,913.000 $58.000 $25.000 $34.000 $40.000 $50.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 83,728.000 $0.550 $0.250 $0.310 $0.210 $0.190
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 41,186.000 $0.470 $0.250 $0.460 $0.210 $0.200
MTL W-BEAM GD FEN (STEEL POST)
LF 1,450.000 $33.000 $35.000 $29.000 $30.700 $30.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,821.250 $2,900.000 $3,100.000 $3,450.000 $2,700.000
REMOVE METAL BEAM GUARD FENCE
LF 1,392.000 $2.750 $4.000 $3.500 $3.700 $3.700
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $237.250 $250.000 $250.000 $265.000 $550.000
GUARDRAIL END TREATMENT (INSTALL)
EA 16.000 $3,165.500 $3,000.000 $2,950.000 $3,100.000 $3,100.000
GUARDRAIL END TREATMENT (REMOVE)
EA 16.000 $266.750 $250.000 $250.000 $265.000 $263.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 3.000 $700.000 $705.000 $705.000 $600.000 $670.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 17.000 $325.000 $375.000 $360.000 $380.000 $242.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 3.000 $275.000 $400.000 $400.000 $385.000 $284.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $800.000 $510.000 $650.000 $540.000 $690.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 30.000 $45.000 $50.000 $45.000 $47.000 $47.300
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 191,666.000 $0.450 $0.200 $0.190 $0.190 $0.210
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 914.000 $0.450 $0.600 $0.580 $0.480 $2.900
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 648.000 $4.000 $3.000 $3.000 $2.120 $6.400
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 19,280.000 $0.240 $0.250 $0.240 $0.320 $0.270
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 95,594.000 $0.280 $0.200 $0.200 $0.320 $0.210
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 10,555.000 $1.250 $1.500 $1.000 $1.500 $0.700
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 282.000 $1.950 $1.250 $1.250 $1.060 $1.200
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 457.000 $2.250 $1.000 $1.000 $1.060 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 276.000 $12.000 $9.000 $7.000 $12.700 $6.900
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 96,493.000 $0.710 $0.550 $0.500 $0.580 $0.600
TY I HIGH PERF PM (Y)6"(BRK)(100MIL)
LF 9,610.000 $1.050 $0.650 $0.540 $0.600 $0.700
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 48,610.000 $1.070 $0.550 $0.510 $0.600 $0.700
PREFAB PM TY C (W)(ARROW)
EA 4.000 $300.000 $250.000 $180.000 $315.000 $213.000
PREFAB PM TY C (W)(WORD)
EA 4.000 $350.000 $250.000 $240.000 $395.000 $267.000
PREFAB PM TY C (W)(RR XING)
EA 2.000 $800.000 $400.000 $350.000 $840.000 $630.000
PREFAB PM TY C (W)(36")(YLD TRI)
EA 5.000 $78.000 $75.000 $68.000 $68.000 $69.250
REFL PAV MRKR TY I-C
EA 24.000 $9.000 $4.000 $4.000 $9.500 $4.000
REFL PAV MRKR TY II-A-A
EA 1,498.000 $6.500 $4.000 $3.680 $6.350 $4.000
ELIM EXT PM & MRKS (36")(YLD TRI)
EA 5.000 $30.000 $25.000 $10.000 $21.000 $80.000
Totals: $18,679,272.339 $13,941,159.050 $14,597,016.340 $16,258,773.820 $18,392,180.120
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $20,000.00
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (NON-PART) $10,000.00
Total: $50,000.00