LIBERTY COUNTY ROAD 2307 (0920-02-097)

Items: 122

County: LIBERTY
Length: 0.9500 MILES
Highway: COUNTY ROAD 2307
District: BEAUMONT
Control Number: 0920-02-097
DBE Goal: 4.0%
Project: BR 2024(178)
Guaranty: $100,000.00
Time: 217 WORKING DAYS
Engineer's Estimate: $5,454,555.45
Date: 06/05/2025 (1 year ago)
Contract Number: 6253216
Type: BRIDGE REPLACEMENT
Project ID: A00190138
Contract Type: Federal
Project Description: MILLER RD(CR 2307) @ GAYLOR CREEK-BRIDGE REPLACEMENT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ROBERTO RODRIGUEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$5,454,555.45
$5,682,862.55
Over/Under Est: 4.19% $228,307.10
Over/Under Est: 4.41% $240,729.94
Amt Left: 0.22% $12,422.84
Over/Under Est: 46.67% $2,545,628.59
Amt Left: 40.78% $2,317,321.49
Delta: -40.47% -$2,304,898.65
Subcontractor Percentage Amount
WEBER-BALKE FOUNDATION COMPANY, INC 11.59% $658,643.77
GMJ PAVING CO. 6.46% $367,112.92
TRAFFIC SIGNS & LINES, LLC 3.79% $215,380.49
TOM-MAC, INC. 1.70% $96,608.66
J.KRU LAND SERVICES, LLC 0.68% $38,643.47
LONESTAR TRAFFIC SAFETY, LLC 0.40% $22,731.45
ASHTON SAWING AND DRILLING LLC 0.21% $11,934.01
Total: 24.83% $1,411,054.77

Bid Items & Bid Tabulations

122 Total 0 of 122
LIBERTY  |  COUNTY ROAD 2307  |  BEAUMONT  |  0920-02-097  |  06/05/2025  |  $5,454,555.45  |  BR 2024(178)  |  BRIDGE REPL  |  217 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BRICE HIGHWAY LLC
FORDE CONSTRUCTION COMPANY, INC.
TEXAS MATERIALS GROUP, INC.
PREPARING ROW
STA 17.430 $10,000.000 $21,000.000 $10,000.000 $29,363.900
REMOV CONC (MOWSTRIP)
SY 302.000 $10.000 $20.750 $34.000 $32.400
REMOV CONC (RIPRAP)
SY 92.000 $32.000 $33.220 $104.000 $21.600
REMOV CONC (DRIVEWAYS)
SY 60.000 $23.000 $49.990 $79.000 $32.400
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 252.000 $22.000 $24.940 $41.000 $64.800
REMOV CONC (CURB RAMP)
SY 71.000 $250.000 $22.330 $65.000 $64.800
REMOV CONC (INTER ART CONC BLOCKS)
SY 107.000 $50.000 $28.920 $135.000 $263.120
RMV (2"-6") TRT/UNTRT BASE & ASPH PAV
SY 7,810.000 $7.000 $0.960 $10.000 $2.050
RMV (10"-14") TRT/UNTRT BASE & ASPH PAV
SY 374.000 $8.000 $8.780 $34.000 $43.640
RMV (9") TRT/UNTRT BASE & ASPH PAV
SY 3,476.000 $8.000 $6.010 $25.000 $13.800
EXCAV (ROADWAY)
CY 940.740 $30.000 $19.240 $39.000 $103.580
EMBANK (FNL)(DC)(TY C)
CY 2,366.640 $35.000 $34.910 $53.000 $95.760
FURN & PLACE TOPSOIL (6")
SY 50.000 $10.000 $25.000 $36.000 $103.060
BROADCAST SEED (PERM_RURAL_SAND)
SY 8,904.000 $2.500 $0.180 $0.750 $0.130
BROADCAST SEED (TEMP_WARM)
SY 4,327.000 $2.000 $0.180 $0.750 $0.260
BROADCAST SEED (TEMP_COOL)
SY 4,327.000 $2.000 $0.210 $0.750 $3.230
VEGETATIVE WATERING
TGL 137.710 $60.000 $42.640 $132.000 $66.360
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 995.000 $200.000 $158.120 $152.000 $169.450
CM TRT(PT MX)(CL M)(TYA)(GR1-2)(FN POS)
CY 624.000 $150.000 $140.780 $155.000 $194.370
PRIME COAT (AE-P)
GAL 1,864.000 $7.000 $5.250 $4.500 $7.990
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 616.000 $150.000 $146.000 $175.000 $197.690
D-GR HMA TY-D PG 64-22 (EXEMPT)
TON 590.000 $130.000 $163.000 $178.000 $232.950
TACK COAT
GAL 981.000 $10.000 $4.750 $4.500 $37.320
STRUCT EXCAV (PIPE)
CY 50.000 $40.000 $15.120 $100.000 $12.960
CEM STABIL BKFL
CY 321.000 $250.000 $255.590 $133.000 $144.170
SHEET PILING (PZ - 27)
SF 4,385.000 $75.000 $77.370 $65.000 $90.200
DRILL SHAFT (24 IN)
LF 966.000 $280.000 $352.570 $325.000 $463.160
DRILL SHAFT (36 IN)
LF 610.000 $350.000 $434.230 $685.000 $734.120
CL C CONC (ABUT)
CY 117.200 $2,000.000 $1,432.740 $2,500.000 $2,968.630
CL C CONC (CAP)
CY 16.000 $2,000.000 $2,533.250 $3,000.000 $5,571.330
CL C CONC (COLUMN)
CY 7.200 $2,000.000 $1,982.490 $5,400.000 $7,138.060
CL C CONC (RAIL FOUNDATION)
CY 10.000 $1,000.000 $755.730 $1,000.000 $2,356.750
CL C CONC (COLLAR)
EA 1.000 $3,000.000 $1,484.200 $1,800.000 $918.000
CL C CONC (COPING)
LF 119.000 $150.000 $283.050 $220.000 $591.540
REINF CONC SLAB
SF 8,687.000 $32.000 $32.530 $32.000 $72.500
APPROACH SLAB
CY 175.300 $900.000 $1,186.250 $900.000 $1,014.740
PRESTR CONC GIRDER (TX28)
LF 486.500 $280.000 $303.280 $287.000 $381.620
PRESTR CONC SLAB BEAM (4SB12)
LF 178.050 $250.000 $297.060 $270.000 $232.090
PRESTR CONC SLAB BEAM (5SB15)
LF 839.920 $250.000 $266.090 $292.000 $254.740
RIPRAP (MOW STRIP)(4 IN)
CY 31.000 $800.000 $615.890 $870.000 $1,728.000
RIPRAP (STONE PROTECTION)(21 IN)
CY 703.000 $200.000 $243.700 $263.000 $324.000
RAIL (TY T221)
LF 204.000 $120.000 $217.890 $183.000 $172.800
RAIL (TY T223)
LF 433.000 $200.000 $221.700 $187.000 $211.680
RAIL (TY PR11)
LF 204.000 $130.000 $143.590 $144.000 $156.600
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 102.000 $220.000 $318.370 $236.000 $79.740
RC PIPE (CL III)(12 IN)
LF 28.000 $100.000 $82.700 $76.000 $70.200
RC PIPE (CL III)(18 IN)
LF 73.000 $120.000 $99.050 $72.000 $75.600
SET (TY II) (12 IN) (RCP) (3: 1) (C)
EA 2.000 $1,200.000 $2,070.450 $2,000.000 $972.000
SET (TY II) (18 IN) (RCP) (3: 1) (C)
EA 3.000 $2,500.000 $1,776.570 $2,000.000 $1,080.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 2.000 $1,500.000 $2,410.110 $2,200.000 $1,296.000
CAST-IN-PLACE TRENCH DRAIN
LF 24.000 $150.000 $606.960 $685.000 $972.000
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 3.000 $500.000 $1,860.230 $125.000 $1,620.000
REMOV STR (SET)
EA 2.000 $580.000 $494.140 $800.000 $648.000
REMOV STR (PIPE)
LF 33.000 $25.000 $42.230 $80.000 $54.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 4.000 $20,000.000 $33,000.000 $52,000.000 $47,405.000
MOBILIZATION
LS 1.000 $396,000.000 $500,000.000 $455,000.000 $611,500.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $7,000.000 $3,594.900 $3,600.000 $2,545.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 100.000 $100.000 $339.820 $150.000 $81.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 305.000 $55.000 $46.000 $48.000 $45.900
ROCK FILTER DAMS (REMOVE)
LF 305.000 $15.000 $15.000 $16.000 $10.800
TEMP SEDMT CONT FENCE (INSTALL)
LF 6,326.000 $5.000 $4.000 $4.250 $3.240
TEMP SEDMT CONT FENCE (REMOVE)
LF 6,326.000 $1.000 $1.000 $1.000 $1.080
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 100.000 $10.000 $5.000 $5.600 $8.640
BIODEG EROSN CONT LOGS (REMOVE)
LF 100.000 $2.000 $1.000 $1.000 $2.160
CONSTRUCTING DETOURS
SY 1,665.000 $130.000 $79.980 $94.000 $122.630
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 840.000 $75.000 $69.700 $40.000 $89.740
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 570.000 $15.000 $14.550 $34.000 $8.160
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 840.000 $30.000 $15.520 $28.000 $26.530
PORT CTB (PINNING)
EA 156.000 $10.000 $286.750 $72.000 $119.390
DRIVEWAYS (CONC)
SY 67.000 $120.000 $216.450 $225.000 $243.000
DRIVEWAYS (ACP)
SY 403.000 $50.000 $82.720 $69.000 $87.470
DRIVEWAYS (BASE)
SY 49.000 $40.000 $162.120 $110.000 $154.160
CONC SIDEWALKS (6")
SY 3,947.000 $115.000 $104.040 $54.000 $205.200
CURB RAMPS (TY 1)
EA 4.000 $2,000.000 $2,952.350 $3,800.000 $3,780.000
CURB RAMPS (TY 2)
EA 1.000 $2,000.000 $2,952.380 $3,800.000 $3,780.000
CURB RAMPS (TY 3)
EA 1.000 $2,500.000 $2,952.380 $3,800.000 $3,780.000
CURB RAMPS (TY 6)
EA 1.000 $2,000.000 $5,177.090 $3,800.000 $3,780.000
CURB RAMPS (TY 7)
EA 11.000 $2,500.000 $2,952.350 $3,800.000 $3,780.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 2,530.000 $3.000 $0.590 $1.500 $0.640
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 1,680.000 $3.500 $0.670 $1.700 $0.720
MTL W-BEAM GD FEN (TIM POST)
LF 537.500 $35.000 $28.860 $30.000 $29.700
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $2,000.000 $2,079.000 $2,100.000 $2,160.000
TL-2 31" SHORT RADIUS (COMPLETE)
EA 1.000 $5,000.000 $25,275.000 $20,000.000 $30,240.000
REMOVE METAL BEAM GUARD FENCE
LF 375.000 $6.000 $3.000 $6.350 $2.700
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $300.000 $250.000 $318.000 $270.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,500.000 $3,349.000 $3,300.000 $3,240.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $280.000 $250.000 $318.000 $270.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 5.000 $2,000.000 $3,400.000 $1,770.000 $2,052.000
CRASH CUSH ATTEN (REMOVE)
EA 9.000 $1,500.000 $2,200.000 $860.000 $972.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL2)
EA 2.000 $25,000.000 $27,950.000 $33,000.000 $28,809.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 2.000 $30,000.000 $27,950.000 $33,000.000 $28,809.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 9.000 $10,000.000 $9,650.000 $8,735.000 $8,634.600
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 30.000 $125.000 $587.000 $620.000 $729.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $500.000 $852.000 $900.000 $1,161.000
REMOVE SM RD SN SUP&AM
EA 39.000 $125.000 $79.000 $84.000 $102.600
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
EA 6.000 $30.000 $15.500 $60.000 $22.680
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 4.000 $35.000 $16.250 $60.000 $16.200
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 15.000 $35.000 $22.000 $40.000 $37.800
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 3.000 $35.000 $27.000 $40.000 $37.800
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 88.000 $5.000 $4.000 $5.100 $6.480
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 5,535.000 $1.250 $1.000 $1.300 $1.520
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 150.000 $12.000 $8.500 $11.000 $17.820
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 7,000.000 $2.000 $1.000 $1.300 $1.570
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 671.000 $1.000 $7.850 $10.000 $16.740
RE PM TY II (W) 6" (SLD)
LF 340.000 $1.250 $1.100 $1.400 $0.810
RE PM TY II (W) 24" (SLD)
LF 671.000 $2.000 $7.500 $9.500 $3.240
RE PM TY II (Y) 6" (BRK)
LF 50.000 $1.600 $2.000 $2.600 $1.130
RE PM TY II (Y) 6" (SLD)
LF 170.000 $1.000 $2.000 $2.600 $0.970
RE PROFILE PM TY I(W)6"(SLD)(090MIL)
LF 340.000 $2.000 $2.250 $2.900 $5.240
RE PROFILE PM TY I(Y)6"(SLD)(090MIL)
LF 170.000 $2.000 $1.450 $1.850 $8.260
RE PROFILE PM TY I(Y)6"(BRK)(090MIL)
LF 45.000 $3.200 $2.500 $3.200 $8.260
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 2,765.000 $1.000 $1.000 $1.300 $1.030
REFL PAV MRK TY I (Y)6"(BRK)(090MIL)
LF 290.000 $1.250 $1.500 $1.900 $1.460
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 1,955.000 $1.000 $1.000 $1.300 $1.030
REFL PAV MRKR TY II-A-A
EA 37.000 $5.000 $6.000 $7.700 $7.560
ELIM EXT PM & MRKS (4")
LF 6,760.000 $0.750 $0.500 $0.650 $0.580
ELIM EXT PM & MRKS (24")
LF 40.000 $2.500 $5.000 $6.400 $2.700
PAV SURF PREP FOR MRK (6")
LF 560.000 $0.500 $0.500 $0.650 $0.650
PAV SURF PREP FOR MRK (24")
LF 671.000 $1.000 $1.000 $1.300 $3.240
TEMP TRAF SIGNALS
EA 1.000 $70,000.000 $50,000.000 $25,000.000 $42,015.000
INTRLCK ART CONC BLKS W/CABLE (6" MIN)
SF 3,090.000 $50.000 $9.850 $16.000 $41.500
RESIDENTIAL DRIVEWAY TEMP SIGNAL SYSTEM
MO 5.000 $10,000.000 $8,800.000 $4,000.000 $2,500.000
Totals: $5,454,555.450 $5,682,862.551 $5,695,285.390 $8,000,184.034
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $55,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $13,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $11,000.00
Total: $79,000.00