LIBERTY FM 787 (0813-01-101)

Items: 32

County: LIBERTY
Length: N/A
Highway: FM 787
District: BEAUMONT
Control Number: 0813-01-101
DBE Goal: N/A
Project: STP 2018(756)HES
Guaranty: N/A
Time: 90 WORKING DAYS
Engineer's Estimate: $638,519.02
Date: 04/03/2018 (8 years ago)
Contract Number: N/A
Type: SAFETY TREAT FIXED OBJECTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$638,519.02
$539,803.00
Over/Under Est: -15.46% -$98,716.02
Over/Under Est: -10.87% -$69,410.52
Amt Left: 5.43% $29,305.50
Over/Under Est: -5.77% -$36,869.02
Amt Left: 11.46% $61,847.00
Delta: -5.72% -$32,541.50
Over/Under Est: -4.91% -$31,369.02
Amt Left: 12.48% $67,347.00
Delta: -0.91% -$5,500.00
Over/Under Est: -2.17% -$13,878.02
Amt Left: 15.72% $84,838.00
Delta: -2.88% -$17,491.00
Over/Under Est: 2.27% $14,522.98
Amt Left: 20.98% $113,239.00
Delta: -4.55% -$28,401.00
Over/Under Est: 14.52% $92,706.98
Amt Left: 35.46% $191,423.00
Delta: -11.97% -$78,184.00
Over/Under Est: 50.25% $320,868.98
Amt Left: 77.73% $419,585.00
Delta: -31.20% -$228,162.00

Bid Items & Bid Tabulations

32 Total 0 of 32
LIBERTY  |  FM 787  |  BEAUMONT  |  0813-01-101  |  04/03/2018  |  $638,519.02  |  STP 2018(756)HES  |  SAFETY TREAT FIXED OBJECTS  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
L.C. JORDAN & SON
ISI CONTRACTING, INC.
TALBRAN ENTERPRISES LLC
FNH CONSTRUCTION, LLC
LONGVIEW BRIDGE AND ROAD, LTD.
NORMAN HIGHWAY CONSTRUCTORS, INC.
MAIN LANE INDUSTRIES LTD.
SJ&J CONSTRUCTION, LLC
REMOVING CONCRETE(MOW STRIP)
LF 1,666.000 $6.230 $20.000 $13.500 $12.000 $12.000 $12.000 $20.000 $2.000 $8.000
BLOCK SODDING
SY 184.000 $4.500 $6.000 $4.000 $7.000 $7.000 $10.000 $10.000 $4.000 $6.000
VEGETATIVE WATERING
MG 14.000 $17.800 $150.000 $14.000 $80.000 $80.000 $30.000 $93.000 $100.000 $60.000
CUT & RESTORE ASPH PAVING
SY 266.000 $112.000 $110.000 $63.000 $175.000 $175.000 $215.000 $90.000 $70.000 $120.000
CUT AND RESTORE PAV (FLEX BASE)
SY 382.000 $275.000 $40.000 $47.000 $80.000 $80.000 $60.000 $80.000 $30.000 $60.000
RIPRAP (MOW STRIP)(4 IN)
CY 60.000 $510.000 $450.000 $720.000 $500.000 $500.000 $480.000 $550.000 $600.000 $800.000
RETROFIT RAIL (TY T223)
LF 166.000 $221.000 $210.000 $100.000 $120.000 $120.000 $367.000 $240.000 $650.000 $250.000
RETROFIT RAIL (TY T552)
LF 188.000 $100.000 $210.000 $75.000 $225.000 $225.000 $320.000 $240.000 $400.000 $250.000
RC PIPE (CL III)(18 IN)
LF 214.000 $60.000 $48.000 $138.000 $80.000 $80.000 $60.000 $180.000 $150.000 $80.000
SET (TY II) (18 IN) (CMP) (6: 1) (C)
EA 22.000 $838.000 $700.000 $1,000.000 $150.000 $150.000 $725.000 $850.000 $1,000.000 $1,800.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 126.000 $842.000 $700.000 $1,000.000 $250.000 $250.000 $665.000 $850.000 $1,000.000 $1,900.000
SET (TY II) (24 IN) (CMP) (6: 1) (C)
EA 4.000 $1,700.000 $950.000 $750.000 $2,500.000 $2,500.000 $1,000.000 $1,100.000 $1,200.000 $2,100.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 18.000 $1,500.000 $950.000 $750.000 $3,000.000 $3,000.000 $1,000.000 $1,100.000 $1,200.000 $2,500.000
SET (TY II) (30 IN) (RCP) (6: 1) (C)
EA 4.000 $2,050.000 $2,500.000 $1,600.000 $4,500.000 $4,500.000 $3,000.000 $2,000.000 $1,500.000 $4,000.000
REMOV STR (PIPE)
LF 201.000 $17.930 $10.000 $21.000 $5.000 $5.000 $40.000 $35.000 $10.000 $80.000
MOBILIZATION
LS 1.000 $50,000.000 $70,000.000 $56,000.000 $54,000.000 $60,000.000 $50,000.000 $65,300.000 $68,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $3,500.000 $2,000.000 $1,400.000 $9,000.000 $10,000.000 $4,000.000 $600.000 $6,000.000 $5,000.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 120.000 $30.000 $45.000 $100.000 $75.000 $75.000 $60.000 $100.000 $50.000 $80.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 120.000 $3.000 $25.000 $21.000 $50.000 $50.000 $25.000 $25.000 $50.000 $40.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 120.000 $3.000 $45.000 $40.000 $40.000 $40.000 $36.000 $40.000 $20.000 $30.000
MTL W-BEAM GD FEN (TIM POST)
LF 350.000 $19.540 $26.000 $24.000 $28.000 $28.000 $22.000 $27.000 $19.000 $30.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 10.000 $1,636.000 $1,600.000 $2,200.000 $1,800.000 $1,800.000 $1,500.000 $1,800.000 $1,600.000 $1,500.000
REMOVE METAL BEAM GUARD FENCE
LF 1,399.000 $2.510 $3.000 $1.500 $5.000 $5.000 $3.000 $5.000 $2.000 $4.000
REMOVE TERMINAL ANCHOR SECTION
EA 12.000 $210.000 $300.000 $100.000 $300.000 $300.000 $300.000 $150.000 $75.000 $600.000
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $2,250.000 $2,500.000 $2,600.000 $3,000.000 $3,000.000 $2,200.000 $2,500.000 $2,200.000 $3,000.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,712.650 $2,500.000 $1,600.000 $10,000.000 $5,000.000 $1,500.000 $17,000.000 $2,000.000 $15,000.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,053.460 $3,000.000 $1,200.000 $5,000.000 $1,000.000 $1,200.000 $2,700.000 $1,000.000 $2,000.000
CRASH CUSH ATTEN (INSTL)(R)(N)(TL3)
EA 2.000 $19,196.000 $8,000.000 $16,000.000 $1,000.000 $9,300.000 $15,000.000 $3,000.000 $25,000.000 $25,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $12,513.000 $8,000.000 $10,500.000 $12,000.000 $9,300.000 $10,000.000 $11,000.000 $10,000.000 $25,000.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 12.000 $51.000 $65.000 $75.000 $100.000 $125.000 $40.000 $60.000 $50.000 $60.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 36.000 $25.000 $65.000 $32.000 $100.000 $125.000 $30.000 $50.000 $20.000 $60.000
TMA (STATIONARY)
DAY 90.000 $285.000 $120.000 $315.000 $200.000 $190.000 $220.000 $230.000 $200.000 $200.000
Totals: $638,519.020 $539,803.000 $569,108.500 $601,650.000 $607,150.000 $624,641.000 $653,042.000 $731,226.000 $959,388.000