LEON FM 745 (3282-01-008)
Items: 47
County: LEON
Length: N/A
Highway: FM 745
District: BRYAN
Control Number: 3282-01-008
DBE Goal: 350.0%
Project: STP 2023(206)TAPS
Guaranty: N/A
Time: 50 WORKING DAYS
Engineer's Estimate: $681,780.10
Date: 01/05/2024 (2 years ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
DELMY REYES
MATT HENSARLING
Informational
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$681,780.10 | |||
| $783,652.00 |
14.94%
$101,871.90
|
|||
| $862,775.42 |
26.55%
$180,995.32
|
10.1%
$79,123.42
|
||
| $920,663.00 |
35.04%
$238,882.90
|
17.48%
$137,011.00
|
-6.71%
-$57,887.58
|
|
| $969,685.02 |
42.23%
$287,904.92
|
23.74%
$186,033.02
|
-5.32%
-$49,022.02
|
|
| $1,163,452.14 |
70.65%
$481,672.04
|
48.47%
$379,800.14
|
-19.98%
-$193,767.12
|
|
| $1,212,318.00 |
77.82%
$530,537.90
|
54.7%
$428,666.00
|
-4.20%
-$48,865.86
|
|
| $1,328,336.00 |
94.83%
$646,555.90
|
69.51%
$544,684.00
|
-9.57%
-$116,018.00
|
|
| $1,530,013.86 |
124.41%
$848,233.76
|
95.24%
$746,361.86
|
-15.18%
-$201,677.86
|
E
Engineer's Estimate
$681,780.10
1
Awarded
$783,652.00
Over/Under Est:
14.94%
$101,871.90
$862,775.42
Over/Under Est:
26.55%
$180,995.32
Amt Left:
10.1%
$79,123.42
$920,663.00
Over/Under Est:
35.04%
$238,882.90
Amt Left:
17.48%
$137,011.00
Delta:
-6.71%
-$57,887.58
$969,685.02
Over/Under Est:
42.23%
$287,904.92
Amt Left:
23.74%
$186,033.02
Delta:
-5.32%
-$49,022.02
$1,163,452.14
Over/Under Est:
70.65%
$481,672.04
Amt Left:
48.47%
$379,800.14
Delta:
-19.98%
-$193,767.12
$1,212,318.00
Over/Under Est:
77.82%
$530,537.90
Amt Left:
54.7%
$428,666.00
Delta:
-4.20%
-$48,865.86
$1,328,336.00
Over/Under Est:
94.83%
$646,555.90
Amt Left:
69.51%
$544,684.00
Delta:
-9.57%
-$116,018.00
$1,530,013.86
Over/Under Est:
124.41%
$848,233.76
Amt Left:
95.24%
$746,361.86
Delta:
-15.18%
-$201,677.86
Bid Items & Bid Tabulations
47
Total
0 of 47