LEE US 77 (0211-04-027)

Items: 45

County: LEE
Length: N/A
Highway: US 77
District: AUSTIN
Control Number: 0211-04-027
DBE Goal: 0.0%
Project: BR 2024(835)
Guaranty: N/A
Time: 130 WORKING DAYS
Engineer's Estimate: $1,448,309.80
Date: 04/05/2024 (2 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$1,448,309.80
1
$1,282,363.92
Over/Under Est: -11.46% -$165,945.88
$1,489,675.06
Over/Under Est: 2.86% $41,365.26
Amt Left: 16.17% $207,311.14
Over/Under Est: 3.62% $52,413.56
Amt Left: 17.03% $218,359.44
Delta: -0.74% -$11,048.30
$1,598,422.00
Over/Under Est: 10.36% $150,112.20
Amt Left: 24.65% $316,058.08
Delta: -6.51% -$97,698.64
$1,618,611.50
Over/Under Est: 11.76% $170,301.70
Amt Left: 26.22% $336,247.58
Delta: -1.26% -$20,189.50
Over/Under Est: 12.5% $180,983.62
Amt Left: 27.05% $346,929.50
Delta: -0.66% -$10,681.92
$1,658,395.50
Over/Under Est: 14.51% $210,085.70
Amt Left: 29.32% $376,031.58
Delta: -1.79% -$29,102.08
Subcontractor Percentage Amount
CHEROKEE SERVICES 0.00% $0.00
DIIBS SPECIALISTS, LLC 0.00% $0.00
FLASHER EQUIPMENT COMPANY 0.00% $0.00
S & S BRIDGE PAINTING, INC. 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

45 Total 0 of 45
LEE  |  US 77  |  AUSTIN  |  0211-04-027  |  04/05/2024  |  $1,448,309.80  |  BR 2024(835)  |  BRIDGE MAINT  |  130 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RELMCO, INC.
3LW CIVIL LLC
ACME BRIDGE COMPANY, INC.
ENCINO LANDSCAPE, INC.
DAN WILLIAMS COMPANY
MB WESTERN INDUSTRIAL CONTRACTING CO.
ICOS MANAGEMENT, LLC
PREPARING ROW
STA 14.300 $2,513.000 $5,000.000 $3,849.650 $3,670.000 $10,000.000 $10,500.000 $5,000.000 $550.000
REMOVING CONC (RIPRAP)
SY 550.000 $25.000 $20.000 $35.000 $34.100 $50.000 $45.000 $75.000 $110.000
CEM STABIL BKFL
CY 80.000 $225.000 $200.000 $350.000 $294.000 $50.000 $275.000 $250.000 $275.000
FLOWABLE BACKFILL
CY 30.000 $1,000.000 $200.000 $350.000 $365.000 $1,000.000 $450.000 $650.000 $275.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 1,406.000 $10.000 $15.450 $66.000 $20.300 $50.000 $40.000 $20.000 $44.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 105.000 $240.000 $400.000 $550.000 $473.000 $300.000 $350.000 $350.000 $440.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 15.000 $200.000 $185.000 $175.000 $279.000 $300.000 $450.000 $300.000 $385.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 529.000 $300.000 $175.000 $175.000 $206.000 $300.000 $230.000 $300.000 $305.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 530.000 $20.000 $44.000 $60.000 $64.100 $50.000 $50.000 $82.000 $88.000
RETROFIT RAIL (TY T131RC)
LF 344.000 $350.000 $342.720 $275.000 $324.000 $250.000 $400.000 $263.000 $495.000
RETROFIT RAIL (TY T631)
LF 560.000 $350.000 $86.350 $160.000 $179.000 $120.000 $220.000 $112.000 $330.000
RAISING EXIST STRUCT
LS 1.000 $15,000.000 $85,000.000 $49,500.000 $277,000.000 $60,000.000 $70,000.000 $100,000.000 $11,000.000
MOBILIZATION
LS 1.000 $140,000.000 $135,000.000 $195,000.000 $102,000.000 $140,000.000 $150,000.000 $150,000.000 $35,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $7,500.000 $4,500.000 $8,500.000 $10,400.000 $5,000.000 $15,000.000 $2,500.000 $1.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 120.000 $50.000 $60.000 $1.000 $69.100 $100.000 $51.000 $64.000 $10.000
ROCK FILTER DAMS (REMOVE)
LF 120.000 $25.000 $40.000 $1.000 $35.300 $10.000 $26.000 $34.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,379.000 $5.000 $6.000 $1.000 $7.900 $20.000 $5.800 $7.500 $2.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,379.000 $1.000 $4.000 $1.000 $1.500 $1.000 $1.100 $1.450 $1.000
PTB(FRN&INSTL)(SSCB OR CSB)(TY1)OR(STL)
LF 2,606.000 $60.000 $38.000 $90.100 $20.400 $65.000 $30.000 $100.000 $66.000
PTB(REMOVE)(SSCB OR CSB)(TY1)OR(STL)
LF 2,606.000 $25.000 $38.000 $35.000 $19.800 $20.000 $20.000 $25.000 $44.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,362.500 $29.000 $26.950 $27.000 $33.700 $30.000 $40.000 $35.000 $44.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,800.000 $2,090.000 $2,800.000 $3,310.000 $2,500.000 $3,000.000 $2,700.000 $5,500.000
REMOVE METAL BEAM GUARD FENCE
LF 1,362.500 $4.000 $2.750 $3.000 $1.100 $10.000 $5.000 $3.550 $3.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,500.000 $3,300.000 $3,600.000 $4,310.000 $3,500.000 $5,000.000 $4,250.000 $5,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $370.000 $275.000 $500.000 $502.000 $300.000 $400.000 $355.000 $550.000
CRASH CUSH ATTEN (REMOVE)
EA 8.000 $1,000.000 $900.000 $1,250.000 $1,150.000 $1,200.000 $500.000 $1,210.000 $5,500.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 8.000 $10,000.000 $9,000.000 $6,875.000 $11,100.000 $12,000.000 $8,000.000 $11,600.000 $8,800.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 30.000 $40.000 $30.860 $35.000 $57.400 $50.000 $40.000 $51.000 $55.000
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 1,884.000 $1.000 $0.750 $0.760 $0.940 $2.000 $0.550 $0.800 $1.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 11,608.000 $1.000 $0.520 $0.530 $0.650 $2.000 $0.550 $0.800 $1.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 6,674.000 $1.000 $0.520 $0.530 $0.650 $2.000 $0.650 $0.900 $1.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 7,092.000 $1.000 $1.320 $1.320 $1.650 $2.000 $0.850 $1.200 $1.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 11,579.000 $1.000 $1.100 $1.100 $1.350 $2.000 $1.250 $1.800 $2.000
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 2,990.000 $1.000 $1.320 $1.320 $1.650 $1.000 $0.850 $1.200 $1.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 12,733.000 $1.000 $1.100 $1.100 $1.350 $1.000 $1.250 $1.800 $2.000
REFL PAV MRKR TY I-C
EA 580.000 $5.000 $7.150 $7.150 $8.800 $10.000 $12.500 $18.000 $17.000
ELIM EXT PAV MRK & MRKS (4")
LF 28,431.000 $0.400 $0.820 $0.830 $1.000 $1.000 $0.500 $0.800 $1.000
GRAFFITI REMOVAL (PAINTING)
SF 65.000 $5.000 $6.000 $22.000 $6.800 $5.000 $50.000 $10.000 $220.000
INSTALL FTB
LF 300.000 $250.000 $20.000 $0.100 $16.100 $150.000 $50.000 $178.000 $220.000
REMOVE FTB
LF 300.000 $20.000 $15.000 $0.100 $13.400 $40.000 $16.000 $28.000 $55.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 60.000 $100.000 $300.000 $92.300 $87.200 $150.000 $200.000 $100.000 $330.000
TMA (STATIONARY)
DAY 60.000 $225.000 $300.000 $150.000 $141.000 $300.000 $250.000 $200.000 $330.000
TMA (MOBILE OPERATION)
DAY 10.000 $960.000 $300.000 $225.000 $602.000 $300.000 $650.000 $200.000 $550.000
REML & DISPL DRIFTWOOD & DEBRIS
CY 24.000 $200.000 $1,000.000 $500.000 $667.000 $150.000 $250.000 $1,500.000 $550.000
REML & DESPL DRIFTWOOD & DEBRIS-SITE 1
LS 1.000 $5,000.000 $35,000.000 $5,000.000 $14,600.000 $20,000.000 $75,000.000 $1,500.000 $22,000.000
Totals: $1,448,309.800 $1,282,363.930 $1,489,675.065 $1,500,723.360 $1,598,422.000 $1,618,611.500 $1,629,293.425 $1,658,395.500