LEE US 290 (0114-07-082)
Items: 11
County: LEE
Length: N/A
Highway: US 290
District: AUSTIN
Control Number: 0114-07-082
DBE Goal: N/A
Project: STP 1702(665)HES
Guaranty: N/A
Time: 118 WORKING DAYS
Engineer's Estimate: $1,518,924.55
Date: 08/09/2017 (8 years ago)
Contract Number: N/A
Type: INSTALL MEDIAN BARRIER
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,518,924.55 | |||
| $1,336,982.72 |
-11.98%
-$181,941.83
|
|||
| $1,553,871.10 |
2.3%
$34,946.55
|
16.22%
$216,888.38
|
||
| $1,670,342.15 |
9.97%
$151,417.60
|
24.93%
$333,359.43
|
-7.50%
-$116,471.05
|
|
| $1,690,124.85 |
11.27%
$171,200.30
|
26.41%
$353,142.13
|
-1.18%
-$19,782.70
|
|
| $1,742,837.25 |
14.74%
$223,912.70
|
30.36%
$405,854.53
|
-3.12%
-$52,712.40
|
|
| $2,211,073.71 |
45.57%
$692,149.16
|
65.38%
$874,090.99
|
-26.87%
-$468,236.46
|
E
Engineer's Estimate
$1,518,924.55
1
Awarded
$1,336,982.72
Over/Under Est:
-11.98%
-$181,941.83
$1,553,871.10
Over/Under Est:
2.3%
$34,946.55
Amt Left:
16.22%
$216,888.38
$1,670,342.15
Over/Under Est:
9.97%
$151,417.60
Amt Left:
24.93%
$333,359.43
Delta:
-7.50%
-$116,471.05
$1,690,124.85
Over/Under Est:
11.27%
$171,200.30
Amt Left:
26.41%
$353,142.13
Delta:
-1.18%
-$19,782.70
$1,742,837.25
Over/Under Est:
14.74%
$223,912.70
Amt Left:
30.36%
$405,854.53
Delta:
-3.12%
-$52,712.40
$2,211,073.71
Over/Under Est:
45.57%
$692,149.16
Amt Left:
65.38%
$874,090.99
Delta:
-26.87%
-$468,236.46
Bid Items & Bid Tabulations
11
Total
0 of 11