LAVACA COUNTY ROAD 130 (0913-29-062)

Items: 43

County: LAVACA
Length: 0.1730 MILES
Highway: COUNTY ROAD 130
District: YOAKUM
Control Number: 0913-29-062
DBE Goal: 3.0%
Project: BR 2023(681)
Guaranty: $32,000.00
Time: 171 WORKING DAYS
Engineer's Estimate: $1,600,279.30
Date: 07/02/2025 (11 months ago)
Contract Number: 7253225
Type: BRIDGE REPLACEMENT
Project ID: A00134793
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
COVEY MORROW
CHASE HERMES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$1,600,279.30
1
$1,541,728.76
Over/Under Est: -3.66% -$58,550.54
$1,578,109.60
Over/Under Est: -1.39% -$22,169.70
Amt Left: 2.36% $36,380.84
Over/Under Est: -0.13% -$2,107.45
Amt Left: 3.66% $56,443.09
Delta: -1.27% -$20,062.25
Over/Under Est: 6.03% $96,483.33
Amt Left: 10.06% $155,033.87
Delta: -6.17% -$98,590.78
Over/Under Est: 9.17% $146,688.79
Amt Left: 13.31% $205,239.33
Delta: -2.96% -$50,205.46
Over/Under Est: 12.08% $193,366.90
Amt Left: 16.34% $251,917.44
Delta: -2.67% -$46,678.11
$2,139,136.81
Over/Under Est: 33.67% $538,857.51
Amt Left: 38.75% $597,408.05
Delta: -19.26% -$345,490.61
Subcontractor Percentage Amount
GREGORY PILE DRIVING, INC. 12.88% $198,574.66
LONE STAR PAVING COMPANY 4.70% $72,461.25
LONE STAR EROSION CONTROL 1.74% $26,826.08
HIGHWAY BARRICADES AND SERVICES, LLC 0.60% $9,250.37
HERMANOS STEEL, LLC 0.16% $2,466.77
Total: 20.08% $309,579.13

Bid Items & Bid Tabulations

43 Total 0 of 43
LAVACA  |  COUNTY ROAD 130  |  YOAKUM  |  0913-29-062  |  07/02/2025  |  $1,600,279.30  |  BR 2023(681)  |  BRIDGE REPL  |  171 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
3LW CIVIL LLC
CONSTAR CONSTRUCTION
ACME BRIDGE COMPANY, INC.
PRESIDIO CONTRACTING, LLC
TEXAS STEEL INDUSTRIAL PLACING, LLC
E-Z BEL CONSTRUCTION, LLC
C. E. BARKER, LTD.
PREPARING ROW
STA 6.700 $5,000.000 $2,743.720 $2,000.000 $2,940.000 $6,975.000 $5,000.000 $6,000.000 $30,000.000
OBLITERATING ABANDONED ROAD
STA 0.700 $7,350.000 $2,415.130 $1,820.000 $1,007.540 $3,120.000 $3,150.000 $1,200.000 $11,296.950
EXCAV (ROADWAY)
CY 490.000 $22.000 $19.490 $22.000 $25.700 $33.250 $20.000 $50.000 $37.660
EXCAV (CHANNEL)
CY 1,115.000 $20.000 $18.840 $18.000 $23.300 $32.150 $25.000 $20.000 $37.660
EMBANK (FNL)(OC)(TY C)
CY 146.000 $30.000 $102.130 $27.000 $52.300 $8.500 $30.000 $60.000 $32.280
BLADING
HR 40.000 $120.000 $164.920 $50.000 $67.400 $50.000 $75.000 $70.000 $112.970
BROADCAST SEED (PERM_RURAL_SAND)
SY 3,138.000 $1.000 $0.910 $0.350 $0.800 $0.800 $0.780 $1.000 $0.840
BROADCAST SEED (TEMP_WARM)
SY 786.000 $1.000 $1.590 $0.350 $2.100 $1.650 $1.500 $2.000 $1.610
BROADCAST SEED (TEMP_COOL)
SY 786.000 $1.000 $1.580 $0.350 $2.100 $1.650 $1.500 $2.000 $1.610
VEGETATIVE WATERING
TGL 26.450 $100.000 $159.300 $120.000 $88.600 $75.000 $25.000 $84.000 $112.970
SOIL RET BLKT(SL_STEEP_SAND_WLDLFE)
SY 82.000 $10.000 $11.890 $6.000 $5.300 $23.500 $12.000 $5.000 $11.670
FL BS (CMP IN PLC)(TY E GR 5)(FNAL POS)
CY 486.000 $125.000 $29.840 $140.000 $131.000 $126.700 $160.000 $200.000 $116.200
ASPH (RC-250)
GAL 408.000 $15.000 $56.360 $25.000 $13.000 $19.700 $10.000 $19.000 $10.760
AGGR (TY-E, GR-5)(SAC-B)
CY 14.000 $600.000 $1,180.000 $1,840.000 $1,300.000 $1,425.000 $700.000 $1,370.000 $1,613.850
AGGR (TY-PE, GR-4)(SAC-B)
CY 16.000 $600.000 $1,309.800 $1,640.000 $1,160.000 $1,270.000 $700.000 $1,220.000 $1,613.850
ASPH (AC 20-5TR OR AC-20XP OR CRS-2P)
GAL 693.000 $15.000 $36.160 $21.000 $9.800 $16.900 $10.000 $16.000 $21.520
CEM STABIL BKFL
CY 68.100 $180.000 $292.840 $115.000 $198.000 $288.250 $200.000 $380.000 $126.420
DRILL SHAFT (24 IN)
LF 765.000 $260.000 $332.150 $288.000 $253.000 $255.200 $330.000 $240.000 $350.210
CL C CONC (ABUT)
CY 47.200 $1,300.000 $914.350 $1,000.000 $1,300.000 $1,245.000 $1,400.000 $2,100.000 $3,324.530
CL C CONC (CAP)
CY 23.100 $1,500.000 $1,776.320 $1,600.000 $1,840.000 $2,310.000 $2,000.000 $2,200.000 $3,270.740
CL C CONC (COLUMN)
CY 16.200 $2,000.000 $1,082.160 $1,800.000 $1,320.000 $1.000 $2,000.000 $1,200.000 $3,270.740
REINF CONC SLAB (SLAB BEAM)
SF 5,330.000 $25.000 $20.400 $22.000 $23.700 $27.250 $23.000 $24.000 $30.130
PRESTR CONC SLAB BEAM (5SB15)
LF 1,011.740 $245.000 $232.660 $290.000 $290.000 $250.000 $280.000 $310.000 $232.140
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,142.000 $200.000 $199.210 $175.000 $171.000 $170.700 $215.000 $220.000 $180.750
RAIL (TY T223)
LF 466.000 $140.000 $156.570 $140.000 $116.000 $160.000 $150.000 $220.000 $127.910
ARMOR JOINT (SEALED)
LF 102.000 $130.000 $134.030 $85.000 $155.000 $150.000 $150.000 $144.000 $157.620
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $30,000.000 $5,100.880 $19,000.000 $27,300.000 $35,650.000 $30,000.000 $25,630.000 $32,277.000
MOBILIZATION
LS 1.000 $145,250.000 $141,129.470 $110,000.000 $118,000.000 $169,600.000 $175,000.000 $100,000.000 $180,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $2,500.000 $638.680 $1,100.000 $2,530.000 $3,500.000 $1,250.000 $2,500.000 $4,808.990
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 200.000 $50.000 $45.370 $47.000 $61.000 $43.450 $50.000 $58.000 $53.800
ROCK FILTER DAMS (REMOVE)
LF 200.000 $10.000 $11.620 $10.000 $17.500 $10.000 $20.000 $17.000 $12.910
SANDBAGS FOR EROSION CONTROL
EA 200.000 $5.000 $9.070 $6.000 $9.000 $10.000 $12.000 $9.000 $12.910
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,490.000 $5.000 $3.840 $5.000 $4.500 $5.900 $4.000 $4.000 $4.300
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,490.000 $2.000 $1.070 $1.000 $0.800 $1.000 $1.000 $1.000 $1.080
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 5.000 $2,400.000 $1,838.510 $2,900.000 $3,080.000 $2,950.000 $2,000.000 $2,125.000 $37.660
GUARDRAIL END TREATMENT (INSTALL)
EA 5.000 $2,000.000 $2,404.630 $4,800.000 $3,790.000 $3,760.000 $3,000.000 $3,400.000 $3,765.650
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 3.000 $30,000.000 $35,177.510 $39,000.000 $37,200.000 $31,200.000 $29,500.000 $31,000.000 $37,656.500
WIRE FENCE (TY A)
LF 388.000 $25.000 $36.100 $10.000 $28.100 $26.000 $20.000 $27.000 $53.800
WIRE FENCE (WATER GAP)
LF 60.000 $50.000 $8.100 $45.000 $31.300 $70.000 $50.000 $30.000 $53.800
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 4.000 $600.000 $734.290 $400.000 $498.000 $780.000 $750.000 $470.000 $806.930
REMOVE SM RD SN SUP&AM
EA 8.000 $200.000 $80.320 $100.000 $106.000 $75.000 $100.000 $100.000 $161.390
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 14.000 $40.000 $21.170 $30.000 $25.500 $25.000 $30.000 $24.000 $37.660
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 10.000 $40.000 $36.950 $300.000 $31.800 $50.000 $30.000 $30.000 $37.660
Totals: $1,600,279.300 $1,541,728.766 $1,578,109.600 $1,598,171.848 $1,696,762.625 $1,746,968.090 $1,793,646.200 $2,139,136.805
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $500.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,500.00
Total: $2,000.00