LAMB US 84 (0052-04-053)
Items: 27
County: LAMB
Length: N/A
Highway: US 84
District: LUBBOCK
Control Number: 0052-04-053
DBE Goal: N/A
Project: F 2024(390)
Guaranty: N/A
Time: 64 WORKING DAYS
Engineer's Estimate: $23,256,130.20
Date: 11/02/2023 (2 years ago)
Contract Number: N/A
Type: SEAL COAT
Mail/Deliver Bids To: N/A
ED GOEBEL
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$23,256,130.20 | |||
| $22,788,746.19 |
-2.01%
-$467,384.01
|
|||
| $23,777,571.24 |
2.24%
$521,441.04
|
4.34%
$988,825.05
|
||
| $25,168,768.95 |
8.22%
$1,912,638.75
|
10.44%
$2,380,022.76
|
-5.85%
-$1,391,197.71
|
E
Engineer's Estimate
$23,256,130.20
1
$22,788,746.19
Over/Under Est:
-2.01%
-$467,384.01
$23,777,571.24
Over/Under Est:
2.24%
$521,441.04
Amt Left:
4.34%
$988,825.05
$25,168,768.95
Over/Under Est:
8.22%
$1,912,638.75
Amt Left:
10.44%
$2,380,022.76
Delta:
-5.85%
-$1,391,197.71
| Subcontractor | Percentage | Amount |
|---|---|---|
| FLAT LINE, INC. | 5.74% | $1,319,397.56 |
| RED SIXTEEN CONSTRUCTION, INC | 0.80% | $183,888.16 |
| Total: | 6.54% | $1,503,285.72 |